Point Lepreau nuclear refurbishment

The life-extension overhaul of New Brunswick's only nuclear reactor, done by Atomic Energy of Canada Limited for NB Power. Planned as an 18-month job, it took three years longer.

Point Lepreau nuclear refurbishment was first priced at $1.4 billion in 2005 by the Province of New Brunswick. No newer official estimate has been published.

Also called: Lepreau

Reviewed monthly. Last review: 5 Nov 2026. How we update

No new estimate since the first price.

First price 2005, Province of New Brunswick
$2.2B

Adjusted for inflation to 2026 dollars.

Days since announced
7,779
Status
Complete
Owner
NB Power
Scope
Unchanged

Every estimate

Government Other

2 public cost estimates from 2005 to 2019.

Location

Timeline

  1. 12 Dec 2019
    Cost

    About $2.4B: $1B over budget

    CBC's account: the $1.4B budget plus $1B of overruns. No NB Power final-cost statement has been sourced yet, so this is shown as a media figure.

    CBC NewsCBC News[2]Sum of $1.4B + $1B

  2. Nov 2012
    Status

    Back online, three years late

    NB PowerCBC News[2]

  3. 2008
    Status

    Reactor shut for refurbishment

    NB PowerCBC News[2]

  4. 12 Aug 2005
    Cost

    Refurbishment approved at $1.4B

    Province of New BrunswickCanadian Consulting Engineer[1]First price

Sources

  1. Canadian Consulting Engineer, 12 Aug 2005
    “However, the province is going to have to spend an estimated $1.4 billion on the overhaul.”
  2. CBC News, 12 Dec 2019
    “AECL, a federal Crown corporation, was hired by NB Power as the contractor to overhaul Point Lepreau beginning in 2008, as the plant was nearing the end of its initial 25-year lifespan.”
    “In its first seven operational years since coming back online in November 2012, the rebuilt reactor has run at an average of 82 per cent capacity, well below the 91 per cent level NB Power predicted for those early years during hearings in 2013 on that issue.”
    “The work was expected to take 18 months and cost NB Power $1.4 billion but became mired in a number of problems and eventually took three years longer than expected. Those delays pushed costs $1 billion over budget.”