Valley Line Southeast LRT
A 13 km low-floor light rail line from downtown Edmonton to Mill Woods, built and operated by the TransEd consortium under a public-private partnership.
Valley Line Southeast LRT was first priced at $1.8 billion in 2016 by the City of Edmonton. No newer official estimate has been published. It opened 2 years, 11 months after the original opening target of Dec 2020.
Also called: Valley Line
Reviewed monthly. Last review: 5 Nov 2026. How we update
No new estimate since the first price.
- First price 2016, City of Edmonton
Adjusted for inflation to 2026 dollars.
- Days since announced
- 3,929
- Status
- Operational
- Owner
- City of Edmonton, with federal and provincial funding
- Scope
- Unchanged
Every estimate
So far only the first price ($1.8B, 2016) measures this, so there is nothing to chart yet.
Schedule
- Original opening targetSet in 2016
- Dec 2020
- Opened
- 4 Nov 2023
- Delay
- 2 years, 11 months
A target given only as a year counts as the end of that year.
Route
Timeline
- 4 Nov 2023Status
Opened nearly three years late
City of EdmontonThe Nugget[2]
- Dec 2021Schedule
Delayed to late 2022
TransEdThe Nugget[2]
- Oct 2021Schedule
Delayed to early 2022
TransEdThe Nugget[2]
- Apr 2016Status
Ground broken
City of Edmonton and TransEdCBC News[1]
- 2016Cost
$1.8B public-private partnership
Signed with the TransEd consortium in 2016.
City of EdmontonCBC News[1]First price
- 2016Schedule
Open December 2020
City of EdmontonThe Nugget[2]
Sources
- CBC News, 3 Nov 2023
“The $1.8-billion project, a public-private partnership with Trans-Ed, was supposed to be operational in December 2020.”
“A groundbreaking ceremony, in which then-mayor Don Iveson was joined by then-federal infrastructure minister and current Mayor Amerjeet Sohi, was held in April 2016, as the ink dried on the city's new contract with TransEd.”
- The Nugget, 16 Nov 2023
“The Valley Line Southeast was originally meant to be operational in December 2020.”
“This second delay pushed the opening date to early 2022.”
“Unfortunately, two months later in December 2021, the completion date was pushed back to late 2022.”
“After almost a three-year delay, the long-awaited Valley Line Southeast LRT finally opened for passenger service on November 4, 2023.”