Valley Line Southeast LRT

A 13 km low-floor light rail line from downtown Edmonton to Mill Woods, built and operated by the TransEd consortium under a public-private partnership.

Valley Line Southeast LRT was first priced at $1.8 billion in 2016 by the City of Edmonton. No newer official estimate has been published. It opened 2 years, 11 months after the original opening target of Dec 2020.

Also called: Valley Line

Reviewed monthly. Last review: 5 Nov 2026. How we update

No new estimate since the first price.

First price 2016, City of Edmonton
$2.4B

Adjusted for inflation to 2026 dollars.

Days since announced
3,929
Status
Operational
Owner
City of Edmonton, with federal and provincial funding
Scope
Unchanged

Every estimate

So far only the first price ($1.8B, 2016) measures this, so there is nothing to chart yet.

Schedule

Original opening target
Set in 2016
Dec 2020
Opened
4 Nov 2023
Delay
2 years, 11 months

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 4 Nov 2023
    Status

    Opened nearly three years late

    City of EdmontonThe Nugget[2]

  2. Dec 2021
    Schedule

    Delayed to late 2022

    TransEdThe Nugget[2]

  3. Oct 2021
    Schedule

    Delayed to early 2022

    TransEdThe Nugget[2]

  4. Apr 2016
    Status

    Ground broken

    City of Edmonton and TransEdCBC News[1]

  5. 2016
    Cost

    $1.8B public-private partnership

    Signed with the TransEd consortium in 2016.

    City of EdmontonCBC News[1]First price

  6. 2016
    Schedule

    Open December 2020

    City of EdmontonThe Nugget[2]

Sources

  1. CBC News, 3 Nov 2023
    “The $1.8-billion project, a public-private partnership with Trans-Ed, was supposed to be operational in December 2020.”
    “A groundbreaking ceremony, in which then-mayor Don Iveson was joined by then-federal infrastructure minister and current Mayor Amerjeet Sohi, was held in April 2016, as the ink dried on the city's new contract with TransEd.”
  2. The Nugget, 16 Nov 2023
    “The Valley Line Southeast was originally meant to be operational in December 2020.”
    “This second delay pushed the opening date to early 2022.”
    “Unfortunately, two months later in December 2021, the completion date was pushed back to late 2022.”
    “After almost a three-year delay, the long-awaited Valley Line Southeast LRT finally opened for passenger service on November 4, 2023.”