Boundary Dam 3 carbon capture
A rebuilt coal unit at SaskPower's Boundary Dam station near Estevan with a carbon capture plant, the first of its kind at commercial scale. Funded by SaskPower with a federal contribution.
Boundary Dam 3 carbon capture was first priced at $1.24 billion in 2011 by the Government of Saskatchewan. The final cost was $1.35 billion (2014, SaskPower), up 9% in dollars as announced, but no more than inflation.
Also called: BD3
Reviewed monthly. Last review: 5 Nov 2026. How we update
Up 9% as announced, but no more than inflation.
- First price 2011, Government of Saskatchewan
- Final cost 2014, SaskPower
- Independent estimate 2015, Canadian Centre for Policy Alternatives
The independent figure is in line with the latest official estimate.
Hatching shows the range given. Adjusted for inflation to 2026 dollars.
- Days since announced
- 5,696
- Status
- Operational
- Owner
- SaskPower
- Scope
- Unchanged
Every estimate
Government Project owner Other
3 public cost estimates from 2011 to 2015.
Location
Timeline
- Jan 2015Cost
CCPA: final cost will top $1.4B
Canadian Centre for Policy AlternativesCanadian Centre for Policy Alternatives (Saskatchewan)[1]
- 2 Oct 2014Cost
$1.35B at opening
SaskPowerCanadian Centre for Policy Alternatives (Saskatchewan)[1]
- 2 Oct 2014Status
Carbon capture unit opens
SaskPowerCanadian Centre for Policy Alternatives (Saskatchewan)[1]
- 26 Apr 2011Cost
Approved at $1.24B
Government of Saskatchewan (Minister responsible for SaskPower, Rob Norris)Canadian Centre for Policy Alternatives (Saskatchewan)[1]First price
Sources
- Canadian Centre for Policy Alternatives (Saskatchewan), 1 Jan 2015
“It would be among the first commercial-scale carbon capture and storage facilities in the world and would cost an estimated $1.24 billion.”
“Three years later on October 2, 2014, SaskPower stated that it “will officially start the $1.35 billion Boundary Dam power plant”
“Final costs will exceed $1.4 billion.”