Centre Block rehabilitation

The gutting and restoration of Parliament's Centre Block in Ottawa, closed since 2018, including a new underground visitor centre. Run by Public Services and Procurement Canada.

Centre Block rehabilitation was first priced at $4.5 billion to $5 billion in 2021 by Public Services and Procurement Canada. The latest official estimate is $4.5 billion to $5 billion (2024, Public Services and Procurement Canada), the same as the first price.

Also called: Centre Block renovation, Parliament Hill

Reviewed monthly. Last review: 5 Nov 2026. How we update

No increase so far.

First price 2021, Public Services and Procurement Canada
$5.4–6B
Latest estimate 2024, Public Services and Procurement Canada
$4.8–5.3B

Hatching shows the range given. Adjusted for inflation to 2026 dollars.

Days since announced
1,991
Status
Under construction
Owner
Government of Canada
Scope
Unchanged

Every estimate

Government

2 public cost estimates from 2021 to 2024.

Schedule

Original completion target
Set in 2021
2030
Current completion target
Set in 2024
2030
Delay
None

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 14 Nov 2024
    Schedule

    Complete in 2030 or 2031, reopening 2032

    Public Services and Procurement CanadaThe Canadian Press, via CJME[1]

  2. 28 Jun 2024
    Cost

    Unchanged: $4.5B to $5B

    Public Services and Procurement CanadaThe Globe and Mail[3]

  3. 17 Jun 2021
    Cost

    First estimate: $4.5B to $5B

    Public Services and Procurement CanadaThe Canadian Press, via The Globe and Mail[2]First price

  4. 17 Jun 2021
    Schedule

    Work to continue until at least 2030

    Public Services and Procurement CanadaThe Canadian Press, via The Globe and Mail[2]

  5. 2018
    Status

    Building closed for renovation

    Public Services and Procurement CanadaThe Canadian Press, via CJME[1]

Sources

  1. The Canadian Press, via CJME, 14 Nov 2024
    “The renovation began in 2018 and is expected to be complete in either 2030 or 2031.”
  2. The Canadian Press, via The Globe and Mail, 17 Jun 2021
    “Construction on the traditional seat of the House of Commons and Senate is expected to wrap before 2032, with a cost of between $4.5-billion and $5-billion, Public Services and Procurement Canada said Thursday in a release.”
    “The massive restoration project under way at Parliament’s Centre Block will cost up to $5-billion and continue at least until 2030, federal officials say.”
  3. The Globe and Mail, 2 Jul 2024
    “Of the project’s forecast cost of between $4.5-billion and $5-billion, $896-million has been spent so far, says the June 28 update from the Public Services and Procurement Canada on work involving the main building on Parliament Hill.”