Pattullo Bridge replacement

A four-lane cable-stayed bridge over the Fraser River between New Westminster and Surrey, replacing the 1937 Pattullo Bridge. Built by Fraser Crossing Partners for the province.

Pattullo Bridge replacement was first priced at $1.38 billion in 2021 by the Province of British Columbia. The latest official estimate is $1.38 billion (2024, BC Ministry of Transportation), the same as the first price. It opened 2 years, 2 months after the original opening target of 2023.

Also called: Riverview Bridge, stal̕əw̓asəm Bridge

Reviewed monthly. Last review: 5 Nov 2026. How we update

No increase so far.

First price 2021, Province of British Columbia
$1.7B
Latest estimate 2024, BC Ministry of Transportation
$1.5B

Adjusted for inflation to 2026 dollars.

Days since announced
3,223
Status
Operational
Owner
Province of British Columbia, with federal funding
Scope
Unchanged

Every estimate

Government

2 public cost estimates from 2021 to 2024.

Schedule

Original opening target
Set in 2018
2023
Opened
Feb 2026
Delay
2 years, 2 months

A target given only as a year counts as the end of that year.

Location

Timeline

  1. Feb 2026
    Status

    All four lanes open

    Province of British ColumbiaReNew Canada[4]

  2. 20 Jun 2024
    Cost

    Still $1.38B

    BC Ministry of TransportationBurnaby Now[3]

  3. 27 May 2024
    Schedule

    Now fall 2025

    Province of British ColumbiaNew West Record[1]

  4. 1 Apr 2021
    Cost

    $1.377B, on budget

    The province's 2018 announcement figure is not yet sourced directly; this is the first sourced statement of it.

    Province of British ColumbiaGlobal News[2]First price

  5. 1 Apr 2021
    Schedule

    Moved to 2024

    Province of British ColumbiaGlobal News[2]

  6. 2018
    Schedule

    Opening 2023

    Province of British ColumbiaNew West Record[1]

Sources

  1. New West Record, 28 May 2024
    “When work on the new bridge first began, it was projected to open in 2023.”
    ““As a result, the new bridge is expected to open in fall 2025.” That’s two years later than originally projected.”
  2. Global News, 1 Apr 2021
    “The government said the new bridge, estimated to cost $1.377-billion, is still on budget.”
    “The opening date for the new toll-free Pattullo Bridge replacement has been moved from late 2023 to sometime in 2024.”
  3. Burnaby Now, 20 Jun 2024
    “According to the ministry, the bridge cost remains $1.38 billion and the subway price tag remains $2.83 billion.”
  4. ReNew Canada, 23 Feb 2026
    “The Government of British Columbia announced that all four lanes on the stal̕əw̓asəm (Riverview) Bridge have now been opened to vehicle traffic between Surrey and New Westminster.”