Pattullo Bridge replacement
A four-lane cable-stayed bridge over the Fraser River between New Westminster and Surrey, replacing the 1937 Pattullo Bridge. Built by Fraser Crossing Partners for the province.
Pattullo Bridge replacement was first priced at $1.38 billion in 2021 by the Province of British Columbia. The latest official estimate is $1.38 billion (2024, BC Ministry of Transportation), the same as the first price. It opened 2 years, 2 months after the original opening target of 2023.
Also called: Riverview Bridge, stal̕əw̓asəm Bridge
Reviewed monthly. Last review: 5 Nov 2026. How we update
No increase so far.
- First price 2021, Province of British Columbia
- Latest estimate 2024, BC Ministry of Transportation
Adjusted for inflation to 2026 dollars.
- Days since announced
- 3,223
- Status
- Operational
- Owner
- Province of British Columbia, with federal funding
- Scope
- Unchanged
Every estimate
Government
2 public cost estimates from 2021 to 2024.
Schedule
- Original opening targetSet in 2018
- 2023
- Opened
- Feb 2026
- Delay
- 2 years, 2 months
A target given only as a year counts as the end of that year.
Location
Timeline
- Feb 2026Status
All four lanes open
Province of British ColumbiaReNew Canada[4]
- 20 Jun 2024Cost
Still $1.38B
BC Ministry of TransportationBurnaby Now[3]
- 27 May 2024Schedule
Now fall 2025
Province of British ColumbiaNew West Record[1]
- 1 Apr 2021Cost
$1.377B, on budget
The province's 2018 announcement figure is not yet sourced directly; this is the first sourced statement of it.
Province of British ColumbiaGlobal News[2]First price
- 1 Apr 2021Schedule
Moved to 2024
Province of British ColumbiaGlobal News[2]
- 2018Schedule
Opening 2023
Province of British ColumbiaNew West Record[1]
Sources
- New West Record, 28 May 2024
“When work on the new bridge first began, it was projected to open in 2023.”
““As a result, the new bridge is expected to open in fall 2025.” That’s two years later than originally projected.”
- Global News, 1 Apr 2021
“The government said the new bridge, estimated to cost $1.377-billion, is still on budget.”
“The opening date for the new toll-free Pattullo Bridge replacement has been moved from late 2023 to sometime in 2024.”
- Burnaby Now, 20 Jun 2024
“According to the ministry, the bridge cost remains $1.38 billion and the subway price tag remains $2.83 billion.”
- ReNew Canada, 23 Feb 2026
“The Government of British Columbia announced that all four lanes on the stal̕əw̓asəm (Riverview) Bridge have now been opened to vehicle traffic between Surrey and New Westminster.”