Finch West LRT
An 11 km light rail line along Finch Avenue West in Toronto from Finch West station to Humber College, built by Metrolinx with the Mosaic Transit Group and run by the TTC as Line 6.
Finch West LRT was first priced at $1.2 billion in 2015 by Metrolinx and Infrastructure Ontario. The latest official estimate is $1.2 billion (2017, the Government of Ontario), the same as the first price. It opened 2 years after the original opening target of 2023.
Also called: Line 6 Finch West, Finch LRT
Reviewed monthly. Last review: 5 Nov 2026. How we update
No increase so far.
- First price 2015, Metrolinx and Infrastructure Ontario
- Latest estimate 2017, Government of Ontario
Adjusted for inflation to 2026 dollars.
- Days since announced
- 4,098
- Status
- Operational
- Owner
- Metrolinx
- Scope
- Unchanged
Every estimate
Government Project owner
2 public cost estimates from 2015 to 2017.
Left out because they measure something else: $2.5B total including construction contract and 30-year maintenance, 2018; $3.7B total including lifecycle, operating and maintenance, 2025.
Schedule
- Original opening targetSet in 2018
- 2023
- Opened
- 7 Dec 2025
- Delay
- 2 years
A target given only as a year counts as the end of that year.
Route
Timeline
- 7 Dec 2025Cost
Total cost $3.7B including maintenance
Includes lifecycle, operating and maintenance costs, so it is not comparable with the $1.2B construction figure or the $2.5B contract.
Report cited by CTV News and The Canadian PressCTV News[5]Progressive Railroading, citing The Canadian Press[4]
- 7 Dec 2025Status
Opens as TTC Line 6
Opened with free rides. The TTC says it runs under soft-opening conditions until spring 2026.
Toronto Transit CommissionCTV News[5]
- 7 May 2018Cost
Contract signed at $2.5B
The contract is for design, build, finance and maintenance, so it is not comparable with the $1.2B capital figure.
Metrolinx and Infrastructure OntarioReNew Canada[3]Progressive Railroading, citing The Canadian Press[4]
- 7 May 2018Schedule
Mosaic to deliver the LRT by 2023
Metrolinx and Infrastructure OntarioReNew Canada[3]
- 26 Jun 2017Cost
Province repeats $1.2B as Ottawa adds $333M
Government of Ontario (Transportation Minister Steven Del Duca)Railway Track & Structures[2]
- 10 Sep 2015Cost
Estimated at $1.2B at procurement
Earliest figure found, from the launch of the build tender. It is the capital cost to build the line.
Metrolinx and Infrastructure Ontario (procurement launch)Railway PRO[1]First price
Sources
- Railway PRO, 10 Sep 2015
“The cost is estimated at CA$1.2bn (EUR 820 million).”
- Railway Track & Structures, 26 Jun 2017
“The Finch West LRT project is estimated to cost CA$1.2 billion (US$906 million) and will consist of 6.8 miles of light-rail line along Finch Ave.”
- ReNew Canada, 7 May 2018
“has signed a contract valued at $2.5 billion to design, build, finance, and maintain”
“Mosaic’s successful proposal will deliver the LRT by 2023.”
- Progressive Railroading, citing The Canadian Press, 10 Dec 2025
“The line's total cost, including the construction contract to Mosaic Transit Group and a 30-year maintenance contract to Bombardier Transportation, was originally estimated at C$2.5 billion.”
“However, the final cost came in at C$3.7 billion, according to the report.”
- CTV News, 7 Dec 2025
“A report earlier this fall pegged the total cost of the line at $3.7 billion, including lifecycle, operating and maintenance expenses.”
“Finch West LRT opens with free rides today”
“The TTC says Line 6 will run under “soft opening” conditions until spring 2026.”