Gordie Howe International Bridge
A six-lane cable-stayed bridge and two ports of entry linking Windsor, Ontario and Detroit, Michigan, delivered by the Windsor-Detroit Bridge Authority. Canada is paying the full upfront cost and expects to recover it through tolls.
Gordie Howe International Bridge was first priced at $5.7 billion in 2018 by Windsor-Detroit Bridge Authority. The latest official estimate is $6.4 billion (2024, Windsor-Detroit Bridge Authority), up 12% in dollars as announced, but no more than inflation. It opened 1 year, 7 months after the original opening target of 31 Dec 2024.
Also called: Detroit River International Crossing
Reviewed monthly. Last review: 5 Nov 2026. How we update
Up 12% as announced, but no more than inflation.
- First price 2018, Windsor-Detroit Bridge Authority
- Latest estimate 2024, Windsor-Detroit Bridge Authority
Adjusted for inflation to 2026 dollars.
- Days since announced
- 2,985
- Status
- Operational
- Owner
- Windsor-Detroit Bridge Authority
- Scope
- Unchanged
Every estimate
Project owner
2 public cost estimates from 2018 to 2024.
Schedule
- Original opening targetSet in 2018
- 31 Dec 2024
- Opened
- 27 Jul 2026
- Delay
- 1 year, 7 months
A target given only as a year counts as the end of that year.
Location
Timeline
- 27 Jul 2026Status
Opened to traffic July 27, 2026
Opening came about 19 months after the original end-of-2024 target.
Windsor-Detroit Bridge AuthorityBNN Bloomberg (The Canadian Press)[5]Sarnia News Today[6]
- 16 Oct 2025Schedule
Opening as soon as early 2026
Windsor-Detroit Bridge AuthorityblogTO[4]
- 4 Jan 2024Cost
Now $6.4B, all paid by Canada
The increase is tied to a 10-month delay after the pandemic.
Windsor-Detroit Bridge AuthorityCBC News[2]
- 4 Jan 2024Schedule
Opening moved to September 2025
Windsor-Detroit Bridge AuthorityCBS News Detroit[3]
- 27 Sep 2018Cost
Fixed-price contract at $5.7B
Set at financial close. Includes the design-build phase and the operation, maintenance and rehabilitation phase, so it is the first figure that is comparable with later totals.
Windsor-Detroit Bridge AuthorityGordie Howe International Bridge (WDBA)[1]First price
- 27 Sep 2018Schedule
Bridge in service by end of 2024
Windsor-Detroit Bridge AuthorityGordie Howe International Bridge (WDBA)[1]
Sources
- Gordie Howe International Bridge (WDBA), 27 Sep 2018
“The fixed-priced contract is valued at $5.7 billion (nominal value), which includes the design-build (DB) phase and the operation, maintenance, rehabilitation (OMR) phase.”
“Bridging North America has presented a 74-month construction schedule to complete the four components of the project with the bridge scheduled to be in service by the end of 2024.”
- CBC News, 4 Jan 2024
“The new targeted opening date means the international border crossing will now cost $6.4 billion Cdn, up from the original $5.7-billion cost estimate”
- CBS News Detroit, 4 Jan 2024
“The target now is September 2025, though the bridge deck should be finished this year.”
- blogTO, 16 Oct 2025
“"The project team is progressing well toward construction completion this year with opening of the Gordie Howe International Bridge as soon as early 2026."”
- BNN Bloomberg (The Canadian Press), 27 Jul 2026
“And so, I think that makes today all the more amazing that it has actually opened today, and a lot of people are very happy."”
- Sarnia News Today, 27 Jul 2026
“Construction began in 2018 with the opening originally planned for 2024.”