Gordie Howe International Bridge

A six-lane cable-stayed bridge and two ports of entry linking Windsor, Ontario and Detroit, Michigan, delivered by the Windsor-Detroit Bridge Authority. Canada is paying the full upfront cost and expects to recover it through tolls.

Gordie Howe International Bridge was first priced at $5.7 billion in 2018 by Windsor-Detroit Bridge Authority. The latest official estimate is $6.4 billion (2024, Windsor-Detroit Bridge Authority), up 12% in dollars as announced, but no more than inflation. It opened 1 year, 7 months after the original opening target of 31 Dec 2024.

Also called: Detroit River International Crossing

Reviewed monthly. Last review: 5 Nov 2026. How we update

Up 12% as announced, but no more than inflation.

First price 2018, Windsor-Detroit Bridge Authority
$7.3B
Latest estimate 2024, Windsor-Detroit Bridge Authority
$6.8B

Adjusted for inflation to 2026 dollars.

Days since announced
2,985
Status
Operational
Owner
Windsor-Detroit Bridge Authority
Scope
Unchanged

Every estimate

Project owner

2 public cost estimates from 2018 to 2024.

Schedule

Original opening target
Set in 2018
31 Dec 2024
Opened
27 Jul 2026
Delay
1 year, 7 months

A target given only as a year counts as the end of that year.

Location

Timeline

  1. 27 Jul 2026
    Status

    Opened to traffic July 27, 2026

    Opening came about 19 months after the original end-of-2024 target.

    Windsor-Detroit Bridge AuthorityBNN Bloomberg (The Canadian Press)[5]Sarnia News Today[6]

  2. 16 Oct 2025
    Schedule

    Opening as soon as early 2026

    Windsor-Detroit Bridge AuthorityblogTO[4]

  3. 4 Jan 2024
    Cost

    Now $6.4B, all paid by Canada

    The increase is tied to a 10-month delay after the pandemic.

    Windsor-Detroit Bridge AuthorityCBC News[2]

  4. 4 Jan 2024
    Schedule

    Opening moved to September 2025

    Windsor-Detroit Bridge AuthorityCBS News Detroit[3]

  5. 27 Sep 2018
    Cost

    Fixed-price contract at $5.7B

    Set at financial close. Includes the design-build phase and the operation, maintenance and rehabilitation phase, so it is the first figure that is comparable with later totals.

    Windsor-Detroit Bridge AuthorityGordie Howe International Bridge (WDBA)[1]First price

  6. 27 Sep 2018
    Schedule

    Bridge in service by end of 2024

    Windsor-Detroit Bridge AuthorityGordie Howe International Bridge (WDBA)[1]

Sources

  1. Gordie Howe International Bridge (WDBA), 27 Sep 2018
    “The fixed-priced contract is valued at $5.7 billion (nominal value), which includes the design-build (DB) phase and the operation, maintenance, rehabilitation (OMR) phase.”
    “Bridging North America has presented a 74-month construction schedule to complete the four components of the project with the bridge scheduled to be in service by the end of 2024.”
  2. CBC News, 4 Jan 2024
    “The new targeted opening date means the international border crossing will now cost $6.4 billion Cdn, up from the original $5.7-billion cost estimate”
  3. CBS News Detroit, 4 Jan 2024
    “The target now is September 2025, though the bridge deck should be finished this year.”
  4. blogTO, 16 Oct 2025
    “"The project team is progressing well toward construction completion this year with opening of the Gordie Howe International Bridge as soon as early 2026."”
  5. BNN Bloomberg (The Canadian Press), 27 Jul 2026
    “And so, I think that makes today all the more amazing that it has actually opened today, and a lot of people are very happy."”
  6. Sarnia News Today, 27 Jul 2026
    “Construction began in 2018 with the opening originally planned for 2024.”

How we count