Calgary Green Line LRT

A light rail line planned from Calgary's north to its southeast, funded by the federal government, the Province of Alberta and the City of Calgary. Alberta pulled its funding share in 2024, and the route has since been redesigned several times, with southeast construction under way since June 2025.

Calgary Green Line LRT was first priced at $4.65 billion in 2017 by the Government of Alberta. The latest official estimate is $6.25 billion (2026, the City of Calgary), up 34% in dollars as announced, but no more than inflation.

Reviewed monthly. Last review: 5 Nov 2026. How we update

Up 34% as announced, but no more than inflation.

First price 2017, Government of Alberta
$6.1B
Latest estimate 2026, City of Calgary
$6.3B

Adjusted for inflation to 2026 dollars.

Days since announced
3,433
Status
Under construction
Owner
City of Calgary
Scope
Changed in 2021, 2024, 2025, 2026

Every estimate

Government Project owner

5 public cost estimates from 2017 to 2026.

Schedule

Completion target
Set in 2017
2026
Delay
None so far

A target given only as a year counts as the end of that year.

Route

Timeline

  1. 22 Sep 2026
    Announcement

    Council approves the surface downtown route

    Provincial and federal confirmation of the new route was still pending.

    Calgary City CouncilWestern Standard[10]

  2. 8 Sep 2026
    Scope

    Surface downtown route endorsed

    The executive committee endorsed a surface alignment along 10 Avenue S.W. for the downtown section, replacing the elevated option. It still needs city council approval and formal confirmation from the provincial and federal governments.

    City of Calgary (Executive Committee)CTV News Calgary[9]

  3. 8 Sep 2026
    Cost

    Approved budget still $6.25B

    The province's preferred elevated option was estimated to cost approximately $1 billion more than the available budget.

    City of Calgary (Executive Committee)CTV News Calgary[9]

  4. 8 Sep 2026
    Schedule

    Southeast section to open in 2031

    Applies to the southeast portion between Shepard and the Event Centre/Grand Central Station area, where construction is underway. The city has not established an opening date for the downtown section.

    City of Calgary (Executive Committee)CTV News Calgary[9]

  5. 18 Mar 2025
    Cost

    Province: $6.24B for Shepard to 7 Avenue SW

    Ottawa confirmed it would still contribute $1.5B, approving the updated route.

    Government of AlbertaCTV News Calgary[8]

  6. 28 Jan 2025
    Scope

    Elevated downtown alignment replaces tunnel

    Alberta released a revised alignment in December 2024 with an elevated section through downtown and no downtown tunnel. Calgary City Council approved the new plan in January 2025, after the province threatened to pull its $1.53B share.

    Government of Alberta and City of CalgaryGlobal News[6]CBC News[7]

  7. 3 Sep 2024
    Announcement

    Alberta pulls its funding share

    Alberta's share of funding was $1.53B.

    Government of Alberta (Transportation Minister Devin Dreeshen)CBC News[5]

  8. 30 Jul 2024
    Cost

    Council approves $6.25B for a shorter line

    The Green Line board chair said it was broadly $1 billion more, and $1 billion of funding that the project did not have.

    City of Calgary (Council and Green Line Board)CTV News Calgary[4]

  9. 30 Jul 2024
    Scope

    Line cut back to Eau Claire to Lynnwood/Millican

    Revised route and delivery model approved by Calgary City Council. The line would run from Eau Claire to Lynnwood/Millican, five stops short of the original route to Shepard.

    City of Calgary (Council and Green Line Board)CTV News Calgary[4]

  10. 14 May 2024
    Cost

    Phase 1 budget $5.5B, bids coming in higher

    City of CalgaryCTV News Calgary[3]

  11. 7 Jul 2021
    Scope

    Rebuilt as a two-phase project

    Construction was reorganized into two phases, with phase one running from Shepard to Eau Claire. Stage 1 as announced in 2017 ran from Shepard to 160 Avenue N.

    Government of Alberta and City of CalgaryLiveWire Calgary[2]

  12. 6 Jul 2017
    Cost

    Stage 1 estimated at $4.65B

    Stage 1 ran from Shepard in the southeast to 160 Avenue N, with a tunnel under the Bow River.

    Government of AlbertaGlobal News[1]First price

  13. 6 Jul 2017
    Schedule

    Stage 1 complete in 2026

    Government of AlbertaGlobal News[1]

In the news

Links to outside coverage. All news

Sources

  1. Global News, 6 Jul 2017
    “It’s estimated stage one of the project will cost $4.65 billion dollars, with the province covering one-third of the cost.”
    “The province said it expects 20,000 jobs will be created by the time the first stage of the green line is complete in 2026.”
  2. LiveWire Calgary, 7 Jul 2021
    “This was changed earlier this year with it shifting to a two-phased construction, rather than three phases.”
    “Phase one is from Shepard to Eau Claire.”
  3. CTV News Calgary, 14 May 2024
    “The price tag for phase one is set at $5.5 billion, but city staff said estimates from contractors are all coming in higher than that.”
  4. CTV News Calgary, 1 Aug 2024
    “For $6.248 billion, the line will run from Eau Claire to Lynnwood/Millican, five stops short of the original route to Shepard in the southeast.”
  5. CBC News, 18 Sep 2024
    “Dreeshen maintained he didn't kill the Green Line when he pulled the province's share of funding for it Sept. 3, contrary to claims by multiple members of Calgary city council that the LRT project was dead the moment the transportation minister made that move.”
  6. Global News, 29 Jan 2025
    “The decision follows an ultimatum from the provincial government, which commissioned an engineering firm to find an elevated alignment through the downtown core instead of the previously approved tunnel.”
  7. CBC News, 13 Dec 2024
    “This iteration of the Green Line will feature no tunneling through Calgary's downtown, which was a major point of criticism from the province in the project's last alignment.”
  8. CTV News Calgary, 19 Mar 2025
    “According to the province, the cost for a line from Shepard to Seventh Avenue S.W. downtown is $6.236 billion.”
  9. CTV News Calgary, 10 Sep 2026
    “The city’s executive committee voted 12-1 Tuesday to endorse a surface alignment along 10 Avenue S.W., sending the proposal to city council for approval.”
    “The surface alignment was the only one of three options presented to committee that could fit within the Green Line’s approved $6.248-billion project budget.”
    “That portion is targeted to begin carrying passengers in 2031.”
  10. Western Standard, 22 Sep 2026
    “The Executive Committee recommended council approve Option 3, which it did on Tuesday by a vote of 12 to 2, with very little debate.”