QEII Health Sciences Centre redevelopment
Nova Scotia's replacement for the aging Victoria General hospital: announced in 2016 as a multi-site QEII redevelopment, now centred on a 14-floor acute-care tower at the Halifax Infirmary, built and maintained under a public-private partnership with Plenary PCL Health.
QEII Health Sciences Centre redevelopment was first priced at $2 billion in 2018 by the Government of Nova Scotia. Later figures measure something different, so they are not compared.
Also called: QEII New Generation, Halifax Infirmary expansion, QEII redevelopment
Checked for new figures on 19 Nov 2026. How we update
No comparable estimate since the first price. Later figures measure something different.
- First price 2018, Government of Nova Scotia
Adjusted for inflation to 2026 dollars.
- Days since announced
- 2,977
- Status
- Under construction
- Owner
- Province of Nova Scotia
- Scope
- Unchanged
Every estimate
So far only the first price ($2B, 2018) measures this, so there is nothing to chart yet.
Left out because they measure something else: $3B+ capital cost (Halifax Infirmary only), 2022; $7.4B P3 total to 2061 (infirmary tower construction plus 30 years of maintenance), 2025.
Schedule
- Opening targetSet in 2025
- 2031
- Delay
- None so far
A target given only as a year counts as the end of that year.
Location
Timeline
- 19 Feb 2025Cost
P3 deal: $7.4B to 2061
Includes 30 years of maintenance, so it is not compared with construction-only figures.
Government of Nova ScotiaGovernment of Nova Scotia[3]
- 19 Feb 2025Status
Main construction phase begins
Government of Nova ScotiaGovernment of Nova Scotia[3]
- 19 Feb 2025Schedule
Tower open to patients in fall 2031
Government of Nova ScotiaGovernment of Nova Scotia[3]
- 18 Aug 2022Cost
Infirmary alone: more than $3B
CBC reported the estimate without naming who made it. It covers the infirmary only, so it is not compared with the 2018 total.
CBC News (unattributed estimate)CBC News[2]
- 4 Oct 2018Cost
About $2B for the whole redevelopment
Covered several sites, including a new cancer centre and the Halifax Infirmary.
Government of Nova Scotia (Premier Stephen McNeil)Global News[1]First price
Sources
- Global News, 4 Oct 2018
“The redevelopment of Nova Scotia’s largest hospital complex will cost about $2 billion – the bulk of which will be funded through a public-private partnership, says Premier Stephen McNeil.”
- CBC News, 18 Aug 2022
“CBC News has learned the estimated price of the Halifax Infirmary redevelopment project has ballooned to more than $3 billion, a number so high that the group bidding on the work has concerns about its ability to get sufficient insurance coverage.”
- Government of Nova Scotia, 19 Feb 2025
“The project’s total cost between now and 2061 will be $7.4 billion.”
“The next phase of construction will soon begin, with the government finalizing an agreement with Plenary PCL Health to build the tower.”
“The new tower is expected to be fully complete and open to patients and providers in the fall of 2031.”