{"source":"https://www.overruns.ca/","generated_at":"2026-11-28T18:21:28.378Z","credit":"Overruns (overruns.ca)","notes":["Costs are in billions of Canadian dollars as announced; dollar_year is the year whose dollars a figure is expressed in.","first_price and latest_estimate compare like with like (same covers). Multiples are after inflation using Statistics Canada CPI.","Every figure has at least one source URL and a verbatim quote containing it."],"projects":[{"slug":"alto-high-speed-rail","name":"Alto high-speed rail","short_name":"Alto high-speed rail","sector":"rail","jurisdiction":"federal","status":"planning","owner":"Government of Canada (via Alto, a federal Crown corporation, with the Cadence consortium)","url":"https://www.overruns.ca/projects/alto-high-speed-rail","first_announced":"2015-01-29","first_price":"$3.5B+","first_price_date":"2015-01-29","first_price_speaker":"VIA Rail (Yves Desjardins-Siciliano, CEO)","latest_estimate":"$60–90B","latest_estimate_date":"2025-02-19","latest_estimate_speaker":"Alto (Martin Imbleau, CEO)","cost_basis":"capital cost","multiple_after_inflation":16.86,"multiple_as_announced":21.43,"delay_months":216,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A dedicated passenger rail line between Toronto and Québec City. It began as VIA Rail's plan for its own tracks, became 'high-frequency rail', and in 2025 was rescoped to 300 km/h high-speed rail run by the Crown corporation Alto.","observations":[{"kind":"cost","statement_date":"2015-01-29","date_precision":"day","speaker":{"type":"proponent","name":"VIA Rail (Yves Desjardins-Siciliano, CEO)"},"cost":{"low":3.5,"high":null,"point":null,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"VIA pitches its own tracks: upwards of $3.5B","note":"Track only, for VIA's existing diesel trains. VIA's CEO said high-speed rail would cost at least three times as much.","sources":[{"url":"https://www.cbc.ca/news/business/dedicated-quebec-city-windsor-track-would-improve-on-time-performance-via-rail-ceo-says-1.2937951","outlet":"CBC News","published_at":"2015-01-30","quote":"He estimates upwards of $3.5 billion of investment in track alone would be necessary to carry Via's current diesel engines, which can go about 100 mph (160 kph)."}]},{"kind":"cost","statement_date":"2015-06-04","date_precision":"day","speaker":{"type":"proponent","name":"VIA Rail (Yves Desjardins-Siciliano, CEO)"},"cost":{"low":null,"high":null,"point":3,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"$3B pitch to investors, Toronto-Ottawa-Montréal","sources":[{"url":"https://www.theglobeandmail.com/report-on-business/via-rail-looks-to-private-investment-for-3-billion-dedicated-track-plan/article24814969/","outlet":"The Globe and Mail","published_at":"2015-06-04","quote":"Yves Desjardins-Siciliano told a room full of bankers, pension-fund managers and developers the $3-billion proposal to buy and build dedicated passenger train tracks in the busy Toronto-Ottawa-Montreal corridor could bring double-digit returns to a consortium of investors in the Crown corporation."}]},{"kind":"cost","statement_date":"2016-04-15","date_precision":"day","speaker":{"type":"proponent","name":"VIA Rail (Yves Desjardins-Siciliano, CEO)"},"cost":{"low":null,"high":null,"point":4,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"High-frequency, electrified: $4B","sources":[{"url":"https://www.cbc.ca/lite/story/1.3537019","outlet":"The Canadian Press, via CBC News","published_at":"2016-04-15","quote":"With any luck, the $4-billion project will be \"shovel ready'' a year from now, with the first of the new fleet carrying passengers by 2019, says Via president and CEO Yves Desjardins-Siciliano."}]},{"kind":"completion_target","statement_date":"2016-04-15","date_precision":"day","speaker":{"type":"proponent","name":"VIA Rail (Yves Desjardins-Siciliano, CEO)"},"target":{"date":"2019-01-01","precision":"year","event":"first_service"},"headline":"First trains by fall 2019","sources":[{"url":"https://www.cbc.ca/lite/story/1.3537019","outlet":"The Canadian Press, via CBC News","published_at":"2016-04-15","quote":"The fall of 2019, the dedicated corridor would exist between Montreal, Ottawa and Toronto at a minimum and even possibly all the way to Quebec City at that point,"}]},{"kind":"scope_change","statement_date":"2016-04-15","date_precision":"day","speaker":{"type":"proponent","name":"VIA Rail"},"scope":{"description":"Plan refocused from diesel trains on dedicated track to electrified 'high-frequency' rail."},"headline":"Refocused on electrified track","sources":[{"url":"https://www.cbc.ca/lite/story/1.3537019","outlet":"The Canadian Press, via CBC News","published_at":"2016-04-15","quote":"But the proposal was recently refined to focus on building electrified tracks after Justin Trudeau was elected with a Liberal government committed to spend massively on infrastructure projects."}]},{"kind":"cost","statement_date":"2017-08-24","date_precision":"day","speaker":{"type":"proponent","name":"VIA Rail"},"cost":{"low":4,"high":6,"point":null,"currency":"CAD","dollar_year":2017,"covers":"capital cost","derived":[{"field":"high","sum_of":[4,2]}]},"headline":"$4B, or $6B fully electrified","note":"The higher figure includes full electrification.","sources":[{"url":"https://www.theglobeandmail.com/news/what-to-do-with-via-rail-ottawa-weighs-multibillion-dollar-boost-to-passengerrail/article36082017/","outlet":"The Globe and Mail","published_at":"2017-08-24","quote":"Via estimates the project would cost $4-billion, plus an additional $2-billion if the service was fully electrified."}]},{"kind":"milestone","statement_date":"2019-06-25","date_precision":"day","speaker":{"type":"government","name":"Government of Canada / Canada Infrastructure Bank"},"milestone":{"title":"$71M in federal money for assessment and design work","achieved":true},"headline":"First federal money for studies","sources":[{"url":"https://www.cbc.ca/news/canada/montreal/windsor-quebec-via-rail-1.5188770","outlet":"CBC News","published_at":"2019-06-25","quote":"The infrastructure bank money, totalling $55 million, will be largely used for environmental assessment, consultations with Indigenous communities and a technical and financial review to help the government make a final funding decision."}]},{"kind":"cost","statement_date":"2020-03-11","date_precision":"day","speaker":{"type":"proponent","name":"VIA Rail"},"cost":{"low":null,"high":null,"point":4.4,"currency":"CAD","dollar_year":2020,"covers":"capital cost"},"headline":"VIA's high-frequency plan: $4.4B","sources":[{"url":"https://globalnews.ca/news/6635203/via-rail-survival-hfr/","outlet":"Global News","published_at":"2020-03-11","quote":"The so-called “High Frequency Rail” plan would cost an estimated $4.4 billion and allow Via to take control of its own infrastructure, including some currently underused train tracks on the modified route between Toronto, Ottawa, Montreal and Quebec City."}]},{"kind":"cost","statement_date":"2021-07-06","date_precision":"day","speaker":{"type":"government","name":"Transport Minister Omar Alghabra"},"cost":{"low":6,"high":12,"point":null,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"Ottawa adopts the plan at $6-12B","sources":[{"url":"https://globalnews.ca/news/8670251/high-frequency-rail-project-quebec-city-toronto-call-for-proposals/","outlet":"Global News","published_at":"2022-03-09","quote":"Alghabra had pegged the cost in July 2021 at between $6 billion to $12 billion, but he told reporters Wednesday he preferred not to estimate a price tag due to inflation and other considerations."},{"url":"https://thelogic.co/briefing/liberals-to-launch-procurement-for-high-frequency-rail-between-quebec-city-toronto-this-fall/","outlet":"The Logic","published_at":"2021-07-06","quote":"The project could cost as much as $12 billion and is to be completed by 2030, he said."}]},{"kind":"completion_target","statement_date":"2021-07-06","date_precision":"day","speaker":{"type":"government","name":"Transport Minister Omar Alghabra"},"target":{"date":"2030-01-01","precision":"year","event":"completion"},"headline":"Completed by 2030","sources":[{"url":"https://thelogic.co/briefing/liberals-to-launch-procurement-for-high-frequency-rail-between-quebec-city-toronto-this-fall/","outlet":"The Logic","published_at":"2021-07-06","quote":"The project could cost as much as $12 billion and is to be completed by 2030, he said."}]},{"kind":"scope_change","statement_date":"2025-02-19","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Prime Minister Justin Trudeau)"},"scope":{"description":"High-frequency rail replaced by high-speed rail at up to 300 km/h, with the Cadence consortium as private partner."},"headline":"High-frequency becomes high-speed","sources":[{"url":"https://www.cbc.ca/1.7462538","outlet":"CBC News","published_at":"2025-02-19","quote":"As Radio-Canada first reported in October, the Liberal government had opted for a high-speed train rather than a slower high-frequency train project to transport passengers between Quebec City and Toronto."}]},{"kind":"announcement","statement_date":"2025-02-19","date_precision":"day","speaker":{"type":"government","name":"Prime Minister Justin Trudeau"},"headline":"Alto launched with $3.9B for design","sources":[{"url":"https://www.cbc.ca/1.7462538","outlet":"CBC News","published_at":"2025-02-19","quote":"The Liberal government launched a six-year, $3.9-billion design and development plan Wednesday that Prime Minister Justin Trudeau says will eventually connect Quebec City and Toronto with a high-speed rail line."}]},{"kind":"cost","statement_date":"2025-02-19","date_precision":"day","speaker":{"type":"proponent","name":"Alto (Martin Imbleau, CEO)"},"cost":{"low":60,"high":90,"point":null,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"High-speed estimate: $60-90B","note":"Announced by Alto's CEO at launch. In 2024 dollars.","sources":[{"url":"https://ici.radio-canada.ca/tele/le-telejournal-18h/site/segments/reportage/1998613/martin-imbleau-president-tgv-toronto-quebec-justin","outlet":"Radio-Canada, Le Téléjournal","published_at":"2025-02-19","quote":"Toutefois, le président et directeur général du projet nommé Alto, Martin Imbleau, entrevoit plutôt des coûts entre 60 et 90 milliards de dollars."},{"url":"https://www.trains.com/trn/news-reviews/news-wire/canadian-high-speed-project-estimates-full-service-could-come-in-2041/","outlet":"Trains","published_at":"2025-02-21","quote":"He also said the early estimate of the cost of the 1,000-kilometer (620-mile) Toronto-Montreal-Quebec City project is Ca$60 billion to $90 billion ($42.3 billion to $63.5 billion)."},{"url":"https://distribution-a617274656661637473.pbo-dpb.ca/e031ec0f85788f30621888cf22221dc68cbf38c37f4db4d191bf5a82e40d61ef","outlet":"Office of the Parliamentary Budget Officer","published_at":"2026-10-01","quote":"The Government estimates that it will cost $60–$90 billion (2024 dollars)."}]},{"kind":"completion_target","statement_date":"2025-02-20","date_precision":"day","speaker":{"type":"proponent","name":"Alto (Martin Imbleau, CEO)"},"target":{"date":"2041-01-01","precision":"year","event":"full_service"},"headline":"Full operation no earlier than 2041","sources":[{"url":"https://www.trains.com/trn/news-reviews/news-wire/canadian-high-speed-project-estimates-full-service-could-come-in-2041/","outlet":"Trains","published_at":"2025-02-21","quote":"It will be at least 2041 before Canada’s high speed rail line begins full operation, according to the head of the Crown corporation that will oversee its construction."}]},{"kind":"completion_target","statement_date":"2025-02-20","date_precision":"day","speaker":{"type":"proponent","name":"Alto (Martin Imbleau, CEO)"},"target":{"date":"2037-01-01","precision":"year","event":"first_service"},"headline":"First section in service by 2037","sources":[{"url":"https://www.trains.com/trn/news-reviews/news-wire/canadian-high-speed-project-estimates-full-service-could-come-in-2041/","outlet":"Trains","published_at":"2025-02-21","quote":"Imbleau said the plan is to begin operations on a portion of the route by 2037, but it has not yet been decided which cities will be served first."}]},{"kind":"milestone","statement_date":"2025-09-12","date_precision":"day","speaker":{"type":"government","name":"Minister Dominic LeBlanc"},"milestone":{"title":"Government says construction should begin within four years","achieved":false},"headline":"Construction to start within four years","sources":[{"url":"https://www.cp24.com/news/canada/2025/09/12/high-speed-rail-construction-could-begin-in-four-years-leblanc-says/","outlet":"The Canadian Press, via CP24","published_at":"2025-09-12","quote":"The federal government wants construction on a planned high-speed rail line between Toronto and Quebec City to begin within four years."}]},{"kind":"completion_target","statement_date":"2025-12-12","date_precision":"day","speaker":{"type":"government","name":"Transport Canada"},"target":{"date":"2029-01-01","precision":"year","event":"construction_start"},"headline":"Ottawa-Montréal chosen first; construction in 2029","sources":[{"url":"https://www.canada.ca/en/transport-canada/news/2025/12/full-speed-ahead-ottawamontreal-chosen-as-starting-point-for-alto-high-speed-rail.html","outlet":"Transport Canada","published_at":"2025-12-12","quote":"Construction of the Ottawa-Montreal segment is expected to begin in 2029."}]},{"kind":"completion_target","statement_date":"2026-03-25","date_precision":"day","speaker":{"type":"proponent","name":"Alto (Martin Imbleau, CEO)"},"target":{"date":"2030-01-01","precision":"year","event":"construction_start"},"headline":"'Real construction' slips to 2030","note":"Site work in 2029; main construction in 2030 in Ottawa, Montréal and Laval.","sources":[{"url":"https://www.cbc.ca/news/canada/ottawa/alto-s-ceo-answers-questions-about-the-high-speed-rail-project-9.7141845","outlet":"CBC News (Ottawa Morning)","published_at":"2026-03-25","quote":"A: We start construction and mobilizing in 2029, and then real construction in 2030 here in Ottawa, in Montreal and in Laval."}]},{"kind":"scope_change","statement_date":"2026-06-22","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"scope":{"description":"A southern route between Peterborough and Ottawa with a possible stop in Kingston. Ottawa asked Alto to assess it; Alto says it is still evaluating the option.","proposed":true},"headline":"Proposed: a southern route with a Kingston stop","note":"Under study, not decided. The budget officer’s October 2026 estimate leaves this option out.","sources":[{"url":"https://distribution-a617274656661637473.pbo-dpb.ca/e031ec0f85788f30621888cf22221dc68cbf38c37f4db4d191bf5a82e40d61ef","outlet":"Office of the Parliamentary Budget Officer","published_at":"2026-10-01","quote":"This analysis does not scope in the Government’s announcement on June 22, 2026, that it had directed Alto to develop a plan to assess a Southern route option between Peterborough and Ottawa that includes a potential stop in Kingston"},{"url":"https://globalnews.ca/news/11986274/kingston-transport-alto/","outlet":"Global News","published_at":"2026-07-23","quote":"For now, however, Alto said in a statement that it’s evaluating whether Kingston should be added to the route or not."}]},{"kind":"cost","statement_date":"2026-10-01","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":75,"high":113,"point":null,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Budget officer: $75-113B","note":"For the route without Kingston, assuming costs like recent European projects.","sources":[{"url":"https://distribution-a617274656661637473.pbo-dpb.ca/e031ec0f85788f30621888cf22221dc68cbf38c37f4db4d191bf5a82e40d61ef","outlet":"Office of the Parliamentary Budget Officer","published_at":"2026-10-01","quote":"From the estimated results, PBO calculates a base cost for Canada’s HSR of $88 million to $133 million per kilometre of track ($75 to $113 billion in total, $2024)."},{"url":"https://www.cbc.ca/news/politics/alto-high-speed-rail-cost-estimate-pbo-9.7365065","outlet":"CBC News","published_at":"2026-10-01","quote":"Building the proposed high‑speed rail project between Toronto and Quebec City could cost between $75 billion and $113 billion — higher than some of the official initial estimates, according to a new report from the Parliamentary Budget Office."}]}]},{"slug":"arctic-economic-security-corridor","name":"Arctic Economic and Security Corridor (Slave Geological Province Corridor)","short_name":"Arctic corridor road","sector":"road_bridge","jurisdiction":"NT","status":"planning","owner":"Government of the Northwest Territories, Tłı̨chǫ Government and Yellowknives Dene First Nation; federal funding","url":"https://www.overruns.ca/projects/arctic-economic-security-corridor","first_announced":"2019-03-04","first_price":"$1.1B","first_price_date":"2019-08-14","first_price_speaker":"Government of the Northwest Territories","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A proposed ~400 km all-season road from near Yellowknife through the mineral-rich Slave Geological Province toward the Nunavut border, where it would meet the Grays Bay road. Led by the Government of the Northwest Territories with the Tłı̨chǫ Government and Yellowknives Dene First Nation.","observations":[{"kind":"announcement","statement_date":"2019-03-04","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories"},"headline":"Planning money for a road into the Slave Geological Province","note":"No cost given.","sources":[{"url":"https://cabinradio.ca/13656/news/economy/nwt-plans-to-start-new-road-toward-nunavut-within-5-years/","outlet":"Cabin Radio","published_at":"2019-03-04","quote":"$2.7 million in federal funding, announced on Monday, will help the territory plan the road into an area known as the Slave Geological Province."}]},{"kind":"cost","statement_date":"2019-08-14","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories"},"cost":{"low":null,"high":null,"point":1.1,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"$1.1B for 413 km","sources":[{"url":"https://www.gov.nt.ca/en/newsroom/slave-geological-province-sgp-corridor-one-step-closer-reality-funding-commitment-made","outlet":"Government of the Northwest Territories","published_at":"2019-08-14","quote":"Proposed road includes a two-lane gravel infrastructure corridor that is 413 km in length and is estimated to cost $1.1 billion"},{"url":"https://www.cbc.ca/lite/story/1.5246771","outlet":"CBC News","published_at":"2019-08-14","quote":"Along with the proposed 413-kilometre, two-lane gravel road — which is estimated to cost $1.1 billion — the long-term project also includes plans for a hydro transmission line."}]},{"kind":"milestone","statement_date":"2019-08-14","date_precision":"day","speaker":{"type":"government","name":"Transport Canada and GNWT"},"milestone":{"title":"$40M committed for environmental reviews and planning","achieved":true},"headline":"$40M for regulatory reviews and planning","sources":[{"url":"https://www.gov.nt.ca/en/newsroom/slave-geological-province-sgp-corridor-one-step-closer-reality-funding-commitment-made","outlet":"Government of the Northwest Territories","published_at":"2019-08-14","quote":"The project will receive a total of $40 million to support environmental regulatory reviews and planning studies."}]}]},{"slug":"arctic-offshore-patrol-ships","name":"Arctic and Offshore Patrol Ships (Harry DeWolf class)","short_name":"Arctic patrol ships","sector":"defence","jurisdiction":"federal","status":"construction","owner":"Government of Canada (Department of National Defence)","url":"https://www.overruns.ca/projects/arctic-offshore-patrol-ships","first_announced":"2007-07-09","first_price":"$3.1B","first_price_date":"2007-07-09","first_price_speaker":"Government of Canada (Prime Minister Stephen Harper)","latest_estimate":"$4.1B","latest_estimate_date":"2020-07-31","latest_estimate_speaker":"Government of Canada","cost_basis":"acquisition","multiple_after_inflation":1.08,"multiple_as_announced":1.32,"delay_months":60,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Ice-capable patrol ships for the Royal Canadian Navy, built by Irving Shipbuilding in Halifax under the National Shipbuilding Strategy. Announced in 2007 for delivery from 2013; the first ship arrived in 2020.","observations":[{"kind":"cost","statement_date":"2007-07-09","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Prime Minister Stephen Harper)"},"cost":{"low":null,"high":null,"point":3.1,"currency":"CAD","dollar_year":2007,"covers":"acquisition"},"headline":"Announced: $3.1B for six to eight ships","note":"A further $4.3B was set aside for operations and maintenance over 25 years.","sources":[{"url":"https://www.defencetalk.com/new-arctic-offshore-patrol-ships-for-canada-12478","outlet":"Defence Talk","published_at":"2007-07-11","quote":"The estimated cost of acquiring the Arctic Offshore Patrol Ships is C$3.1 billion, with approximately C$4.3 billion provided for operations and maintenance over their 25-year lifespan."}]},{"kind":"completion_target","statement_date":"2007-07-09","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2013-01-01","precision":"year","event":"first_delivery"},"headline":"First ship due 2013","sources":[{"url":"https://nunatsiaq.com/stories/article/65674halifax_shipyard_nets_arctic_offshore_patrol_ships_project/","outlet":"Nunatsiaq News","published_at":"2012-03-07","quote":"The contract was originally supposed to be awarded in May 2009, with delivery of the first of eight ships set for 2013."}]},{"kind":"cost","statement_date":"2015-01-16","date_precision":"day","speaker":{"type":"government","name":"Government of Canada officials"},"cost":{"low":null,"high":null,"point":3.5,"currency":"CAD","dollar_year":2015,"covers":"acquisition"},"headline":"Budget raised to $3.5B, now for five ships","sources":[{"url":"https://www.defensenews.com/naval/2015/01/25/canada-kicks-off-arctic-patrol-ship-program/","outlet":"Defense News","published_at":"2015-01-25","quote":"The cost of the project to build the Arctic offshore patrol ships has also increased from $3.1 billion to $3.5 billion, government officials confirmed on Jan. 16.The official contract announcement with government and company representatives was held Jan. 23.The ships were originally announced in 2007 by Conservative Prime Minister Stephen Harper and were supposed to be in the water by 2013."}]},{"kind":"scope_change","statement_date":"2015-01-16","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"scope":{"description":"The fleet shrank from six to eight ships to five for the original budget; a sixth ship was added later with more money."},"headline":"Five ships instead of six to eight","sources":[{"url":"https://globalnews.ca/news/7239247/navy-enters-new-era-hmcs-de-wolf/amp","outlet":"Global News","published_at":"2020-07-31","quote":"After work started on the DeWolf in 2015, Irving said it would only be able to build five ships with the $3.1 billion budgeted for the project."}]},{"kind":"completion_target","statement_date":"2015-01-23","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2018-01-01","precision":"year","event":"first_delivery"},"headline":"First ship now due 2018","sources":[{"url":"https://www.defensenews.com/naval/2015/01/25/canada-kicks-off-arctic-patrol-ship-program/","outlet":"Defense News","published_at":"2015-01-25","quote":"The first ship will be ready by 2018."}]},{"kind":"cost","statement_date":"2020-07-31","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":4.1,"currency":"CAD","dollar_year":2020,"covers":"acquisition"},"headline":"Budget $4.1B for six ships","note":"The date is when the figure was reported; the budget increase was decided earlier.","sources":[{"url":"https://globalnews.ca/news/7239247/navy-enters-new-era-hmcs-de-wolf/amp","outlet":"Global News","published_at":"2020-07-31","quote":"The government ended up increasing the budget to $4.1 billion for six."}]},{"kind":"milestone","statement_date":"2020-07-31","date_precision":"day","speaker":{"type":"government","name":"Royal Canadian Navy"},"milestone":{"title":"First ship, HMCS Harry DeWolf, delivered two years behind schedule","achieved":true},"headline":"First ship delivered","sources":[{"url":"https://globalnews.ca/news/7239247/navy-enters-new-era-hmcs-de-wolf/amp","outlet":"Global News","published_at":"2020-07-31","quote":"The DeWolf is the first of six new Arctic and offshore patrol vessels to be built in decades for the Royal Canadian Navy to conduct military operations in the Arctics.But it arrives two years behind schedule and after a lengthy process."}]}]},{"slug":"bipole-iii","name":"Bipole III transmission line","short_name":"Bipole III","sector":"energy","jurisdiction":"MB","status":"complete","owner":"Manitoba Hydro (Province of Manitoba)","url":"https://www.overruns.ca/projects/bipole-iii","first_announced":"2007-01-01","first_price":"$2.2B","first_price_date":"2007-01-01","first_price_speaker":"Manitoba Hydro","latest_estimate":"$5.04B","latest_estimate_date":"2018-01-01","latest_estimate_speaker":"Manitoba Hydro (2017-18 annual report)","cost_basis":"capital cost","multiple_after_inflation":1.91,"multiple_as_announced":2.29,"delay_months":12,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 500-kilovolt direct current transmission line of about 1,400 km running from northern Manitoba down the west side of the province to the Riel converter station near Winnipeg, built by Manitoba Hydro. It entered service in 2018.","observations":[{"kind":"cost","statement_date":"2007-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Manitoba Hydro"},"cost":{"low":null,"high":null,"point":2.2,"currency":"CAD","dollar_year":2007,"covers":"capital cost"},"headline":"First estimate: $2.2B","note":"The figure in place when the province directed Hydro to route the line down the west side of Manitoba.","sources":[{"url":"https://www.cbc.ca/lite/story/1.5343539","outlet":"CBC News","published_at":"2019-10-31","quote":"The cost for the project was originally pegged in 2007 at $2.2 billion."}]},{"kind":"cost","statement_date":"2010-08-25","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro (Bob Brennan, CEO)"},"cost":{"low":null,"high":null,"point":2.247,"currency":"CAD","dollar_year":2010,"covers":"capital cost"},"headline":"West route still put at $2.247B","note":"From a letter by Hydro's CEO to the Brandon Sun. Leaked internal documents at the time put the cost near $4B, which Hydro denied.","sources":[{"url":"https://www.policyalternatives.ca/news-research/ccpa-review-taking-stock-of-the-bipole-iii-debate/","outlet":"Canadian Centre for Policy Alternatives","published_at":"2010-09-22","quote":"“In fact, Manitoba Hydro has estimated that the west side route will be $2.247 billion, while the cost of an east side route would be $1,837 billion."}]},{"kind":"completion_target","statement_date":"2010-09-22","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"target":{"date":"2017-01-01","precision":"year","event":"completion"},"headline":"In service by 2017","note":"From Manitoba Hydro's published project schedule, with construction to start in late 2012.","sources":[{"url":"https://www.policyalternatives.ca/news-research/ccpa-review-taking-stock-of-the-bipole-iii-debate/","outlet":"Canadian Centre for Policy Alternatives","published_at":"2010-09-22","quote":"In-service Date: 2017"}]},{"kind":"cost","statement_date":"2011-03-31","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"cost":{"low":null,"high":null,"point":3.28,"currency":"CAD","dollar_year":2011,"covers":"capital cost"},"headline":"Revised to $3.28B","note":"Includes the line and the two converter stations, whose estimate rose from $1.16B to $1.83B.","sources":[{"url":"https://www.policyalternatives.ca/news-research/fast-facts-mcfadyens-crazy-numbers-wont-fool-manitobans/","outlet":"Canadian Centre for Policy Alternatives","published_at":"2011-04-07","quote":"The revised estimate raised the total cost from $2.24 billion to $3.28 billion."}]},{"kind":"cost","statement_date":"2014-09-22","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"cost":{"low":null,"high":null,"point":4.65,"currency":"CAD","dollar_year":2014,"covers":"capital cost"},"headline":"Budget raised to $4.65B","note":"Reported at the time as $4.6B. The province later cited the exact budget as $4.65B.","sources":[{"url":"https://www.mysteinbach.ca/newsblog/26223.html","outlet":"mySteinbach","published_at":"2014-09-22","quote":"Steinbach MLA, Kelvin Goertzen, says the acknowledgement that the Bipole III hydro transmission line has now doubled in price to $4.6 billion is a further insult to the residents of the southeast and to all Manitobans who will be forced to pay for this boondoggle for years to come."},{"url":"https://news.gov.mb.ca/news/print,index.html?item=39290","outlet":"Government of Manitoba","published_at":"2016-09-21","quote":"the cost for Bipole III is also expected to rise to between $4.9 and $5 billion from the current budget of $4.65 billion"}]},{"kind":"cost","statement_date":"2016-09-21","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro-Electric Board (review)"},"cost":{"low":4.9,"high":5,"point":null,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"Board review: $4.9B to $5B","note":"The same review projected a delay of 12 to 15 months.","sources":[{"url":"https://news.gov.mb.ca/news/print,index.html?item=39290","outlet":"Government of Manitoba","published_at":"2016-09-21","quote":"the cost for Bipole III is also expected to rise to between $4.9 and $5 billion from the current budget of $4.65 billion"}]},{"kind":"completion_target","statement_date":"2017-06-19","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"target":{"date":"2018-07-01","precision":"month","event":"completion"},"headline":"In service by July 2018","sources":[{"url":"https://steinbachonline.com/local/helicoptors-being-used-to-hang-insulators-on-bipole-iii-towers","outlet":"SteinbachOnline","published_at":"2017-06-19","quote":"The anticipated in-service date for Bipole III is July 2018."}]},{"kind":"cost","statement_date":"2018-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Manitoba Hydro (2017-18 annual report)"},"cost":{"low":null,"high":null,"point":5.04,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"Final estimate: $5.04B","note":"From the 2017-18 annual report, after the line entered service.","sources":[{"url":"https://www.cbc.ca/lite/story/1.5343539","outlet":"CBC News","published_at":"2019-10-31","quote":"In its 2018 annual report, Hydro said the total estimated cost was $5.04 billion"}]},{"kind":"status","statement_date":"2018-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Manitoba Hydro"},"new_status":"complete","headline":"Line completed in 2018","sources":[{"url":"https://www.cbc.ca/lite/story/1.5343539","outlet":"CBC News","published_at":"2019-10-31","quote":"The Bipole III transmission line was completed in 2018"}]}]},{"slug":"boundary-dam-3-ccs","name":"Boundary Dam 3 carbon capture (SaskPower)","short_name":"Boundary Dam 3 CCS","sector":"energy","jurisdiction":"SK","status":"operational","owner":"SaskPower (Province of Saskatchewan), federal contribution","url":"https://www.overruns.ca/projects/boundary-dam-3-ccs","first_announced":"2011-04-26","first_price":"$1.24B","first_price_date":"2011-04-26","first_price_speaker":"Government of Saskatchewan (Minister responsible for SaskPower, Rob Norris)","latest_estimate":"$1.35B","latest_estimate_date":"2014-10-02","latest_estimate_speaker":"SaskPower","cost_basis":"capital cost","multiple_after_inflation":1.04,"multiple_as_announced":1.09,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A rebuilt coal unit at SaskPower's Boundary Dam station near Estevan with a carbon capture plant, the first of its kind at commercial scale. Funded by SaskPower with a federal contribution.","observations":[{"kind":"cost","statement_date":"2011-04-26","date_precision":"day","speaker":{"type":"government","name":"Government of Saskatchewan (Minister responsible for SaskPower, Rob Norris)"},"cost":{"low":null,"high":null,"point":1.24,"currency":"CAD","dollar_year":2011,"covers":"capital cost"},"headline":"Approved at $1.24B","sources":[{"url":"https://policyalternatives.ca/wp-content/uploads/attachments/Saskpowers_Carbon_Capture_Project.pdf","outlet":"Canadian Centre for Policy Alternatives (Saskatchewan)","published_at":"2015-01-01","quote":"It would be among the first commercial-scale carbon capture and storage facilities in the world and would cost an estimated $1.24 billion."}]},{"kind":"cost","statement_date":"2014-10-02","date_precision":"day","speaker":{"type":"proponent","name":"SaskPower"},"cost":{"low":null,"high":null,"point":1.35,"currency":"CAD","dollar_year":2014,"covers":"capital cost"},"headline":"$1.35B at opening","sources":[{"url":"https://policyalternatives.ca/wp-content/uploads/attachments/Saskpowers_Carbon_Capture_Project.pdf","outlet":"Canadian Centre for Policy Alternatives (Saskatchewan)","published_at":"2015-01-01","quote":"Three years later on October 2, 2014, SaskPower stated that it “will officially start the $1.35 billion Boundary Dam power plant"}]},{"kind":"status","statement_date":"2014-10-02","date_precision":"day","speaker":{"type":"proponent","name":"SaskPower"},"new_status":"operational","headline":"Carbon capture unit opens","sources":[{"url":"https://policyalternatives.ca/wp-content/uploads/attachments/Saskpowers_Carbon_Capture_Project.pdf","outlet":"Canadian Centre for Policy Alternatives (Saskatchewan)","published_at":"2015-01-01","quote":"Three years later on October 2, 2014, SaskPower stated that it “will officially start the $1.35 billion Boundary Dam power plant"}]},{"kind":"cost","statement_date":"2015-01-01","date_precision":"month","speaker":{"type":"other","name":"Canadian Centre for Policy Alternatives"},"cost":{"low":1.4,"high":null,"point":null,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"CCPA: final cost will top $1.4B","sources":[{"url":"https://policyalternatives.ca/wp-content/uploads/attachments/Saskpowers_Carbon_Capture_Project.pdf","outlet":"Canadian Centre for Policy Alternatives (Saskatchewan)","published_at":"2015-01-01","quote":"Final costs will exceed $1.4 billion."}]}]},{"slug":"broadway-subway","name":"Broadway Subway (Millennium Line extension)","short_name":"Broadway Subway","sector":"transit","jurisdiction":"BC","status":"construction","owner":"Province of British Columbia (Ministry of Transportation and Transit, delivered by Transportation Investment Corporation)","url":"https://www.overruns.ca/projects/broadway-subway","first_announced":"2014-01-01","first_price":"$1.98B","first_price_date":"2014-01-01","first_price_speaker":"TransLink","latest_estimate":"$2.95B","latest_estimate_date":"2025-01-03","latest_estimate_speaker":"Province of British Columbia (Infrastructure BC project page)","cost_basis":"capital cost","multiple_after_inflation":1.14,"multiple_as_announced":1.49,"delay_months":24,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 5.7-kilometre, six-station SkyTrain extension of the Millennium Line from VCC-Clark to Arbutus Street in Vancouver, mostly underground. Funded by the Province of B.C. with contributions from Canada and the City of Vancouver.","observations":[{"kind":"cost","statement_date":"2014-01-01","date_precision":"year","speaker":{"type":"proponent","name":"TransLink"},"cost":{"low":null,"high":null,"point":1.98,"currency":"CAD","dollar_year":2014,"covers":"capital cost"},"headline":"First budgeted at $1.98B in 2014","note":"The first figure found, from TransLink's 2014 plan as reported by Global News in 2018. Global News reported it as the earlier budget for the same Broadway line to Arbutus Street.","sources":[{"url":"https://globalnews.ca/news/4177197/broadway-subway-line-costs-grow","outlet":"Global News","published_at":"2018-04-30","quote":"The project was in 2014 budgeted to cost $1.98 billion."}]},{"kind":"cost","statement_date":"2018-04-30","date_precision":"day","speaker":{"type":"proponent","name":"TransLink"},"cost":{"low":null,"high":null,"point":2.83,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"Estimate rises to $2.83B","note":"Global News said the 2014 figure would be $2.28B in 2018 dollars.","sources":[{"url":"https://globalnews.ca/news/4177197/broadway-subway-line-costs-grow","outlet":"Global News","published_at":"2018-04-30","quote":"Cost of Broadway subway line grows to an estimated $2.83 billion"}]},{"kind":"completion_target","statement_date":"2018-04-30","date_precision":"day","speaker":{"type":"proponent","name":"TransLink"},"target":{"date":"2025-01-01","precision":"year","event":"first_service"},"headline":"Target completion in 2025","sources":[{"url":"https://globalnews.ca/news/4177197/broadway-subway-line-costs-grow","outlet":"Global News","published_at":"2018-04-30","quote":"The construction is expected to start in 2020, with the target completion date of 2025."}]},{"kind":"cost","statement_date":"2021-02-02","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"cost":{"low":null,"high":null,"point":2.83,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"Budgeted at $2.83B at construction start","sources":[{"url":"https://globalnews.ca/news/7614878/bc-government-update-broadway-subway-project","outlet":"Global News","published_at":"2021-02-02","quote":"The Broadway Subway Project is budgeted to cost $2.83 billion."}]},{"kind":"completion_target","statement_date":"2022-11-25","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"target":{"date":"2026-01-01","precision":"quarter","event":"first_service"},"headline":"Delayed to early 2026 after strike","sources":[{"url":"https://amp.cbc.ca/lite/story/1.6663838","outlet":"CBC News","published_at":"2022-11-25","quote":"The B.C. government says the first phase of the Broadway Subway project in Vancouver has been delayed to early 2026 due to a strike in June."}]},{"kind":"completion_target","statement_date":"2024-05-24","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia (Ministry of Transportation)"},"target":{"date":"2027-09-01","precision":"quarter","event":"first_service"},"headline":"Delayed again to fall 2027","sources":[{"url":"https://globalnews.ca/news/10527255/broadway-subway-construction-delay","outlet":"Global News","published_at":"2024-05-27","quote":"The Ministry of Transportation revealed Friday that the projected completion date for the Broadway subway has been pushed back to the fall of 2027."}]},{"kind":"cost","statement_date":"2025-01-03","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia (Infrastructure BC project page)"},"cost":{"low":null,"high":null,"point":2.954,"currency":"CAD","dollar_year":2025,"covers":"capital cost"},"headline":"Project cost now $2.954B","note":"The sources found do not give the date of the increase from $2.83B.","sources":[{"url":"https://infrastructurebc.com/?p=8856","outlet":"Infrastructure BC","published_at":"2025-01-03","quote":"The Broadway Subway Project will cost $2.954 billion, funded and delivered by the Government of B.C., with contributions from the Government of Canada and the City of Vancouver."}]},{"kind":"completion_target","statement_date":"2025-01-03","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia (Infrastructure BC project page)"},"target":{"date":"2027-01-01","precision":"year","event":"first_service"},"headline":"Opening in 2027","sources":[{"url":"https://infrastructurebc.com/?p=8856","outlet":"Infrastructure BC","published_at":"2025-01-03","quote":"Construction of the subway will mostly involve tunneling, with the new extension opening in 2027."}]}]},{"slug":"calgary-green-line","name":"Calgary Green Line LRT","short_name":"Green Line (Calgary)","sector":"transit","jurisdiction":"AB","status":"construction","owner":"City of Calgary","url":"https://www.overruns.ca/projects/calgary-green-line","first_announced":"2017-07-06","first_price":"$4.65B","first_price_date":"2017-07-06","first_price_speaker":"Government of Alberta","latest_estimate":"$6.25B","latest_estimate_date":"2026-09-08","latest_estimate_speaker":"City of Calgary (Executive Committee)","cost_basis":"capital cost","multiple_after_inflation":1.04,"multiple_as_announced":1.34,"delay_months":null,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A light rail line planned from Calgary's north to its southeast, funded by the federal government, the Province of Alberta and the City of Calgary. Alberta pulled its funding share in 2024, and the route has since been redesigned several times, with southeast construction under way since June 2025.","observations":[{"kind":"cost","statement_date":"2017-07-06","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta"},"cost":{"low":null,"high":null,"point":4.65,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"Stage 1 estimated at $4.65B","note":"Stage 1 ran from Shepard in the southeast to 160 Avenue N, with a tunnel under the Bow River.","sources":[{"url":"https://globalnews.ca/news/3579710/alberta-government-pledges-1-53b-for-calgarys-green-line-lrt","outlet":"Global News","published_at":"2017-07-06","quote":"It’s estimated stage one of the project will cost $4.65 billion dollars, with the province covering one-third of the cost."}]},{"kind":"completion_target","statement_date":"2017-07-06","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta"},"target":{"date":"2026-01-01","precision":"year","event":"completion"},"headline":"Stage 1 complete in 2026","sources":[{"url":"https://globalnews.ca/news/3579710/alberta-government-pledges-1-53b-for-calgarys-green-line-lrt","outlet":"Global News","published_at":"2017-07-06","quote":"The province said it expects 20,000 jobs will be created by the time the first stage of the green line is complete in 2026."}]},{"kind":"scope_change","statement_date":"2021-07-07","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta and City of Calgary"},"scope":{"description":"Construction was reorganized into two phases, with phase one running from Shepard to Eau Claire. Stage 1 as announced in 2017 ran from Shepard to 160 Avenue N."},"headline":"Rebuilt as a two-phase project","sources":[{"url":"https://livewirecalgary.com/2021/07/07/alberta-approves-calgarys-green-line-business-case/","outlet":"LiveWire Calgary","published_at":"2021-07-07","quote":"This was changed earlier this year with it shifting to a two-phased construction, rather than three phases."},{"url":"https://livewirecalgary.com/2021/07/07/alberta-approves-calgarys-green-line-business-case/","outlet":"LiveWire Calgary","published_at":"2021-07-07","quote":"Phase one is from Shepard to Eau Claire."}]},{"kind":"cost","statement_date":"2024-05-14","date_precision":"day","speaker":{"type":"proponent","name":"City of Calgary"},"cost":{"low":null,"high":null,"point":5.5,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Phase 1 budget $5.5B, bids coming in higher","sources":[{"url":"https://ctvnews.ca/calgary/article/escalating-costs-a-concern-for-calgarys-green-line-lrt-project-city-says","outlet":"CTV News Calgary","published_at":"2024-05-14","quote":"The price tag for phase one is set at $5.5 billion, but city staff said estimates from contractors are all coming in higher than that."}]},{"kind":"cost","statement_date":"2024-07-30","date_precision":"day","speaker":{"type":"proponent","name":"City of Calgary (Council and Green Line Board)"},"cost":{"low":null,"high":null,"point":6.248,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Council approves $6.25B for a shorter line","note":"The Green Line board chair said it was broadly $1 billion more, and $1 billion of funding that the project did not have.","sources":[{"url":"https://calgary.ctvnews.ca/more-money-for-less-green-line-lrt-approval-reaction-remains-mixed-1.6985312","outlet":"CTV News Calgary","published_at":"2024-08-01","quote":"For $6.248 billion, the line will run from Eau Claire to Lynnwood/Millican, five stops short of the original route to Shepard in the southeast."}]},{"kind":"scope_change","statement_date":"2024-07-30","date_precision":"day","speaker":{"type":"proponent","name":"City of Calgary (Council and Green Line Board)"},"scope":{"description":"Revised route and delivery model approved by Calgary City Council. The line would run from Eau Claire to Lynnwood/Millican, five stops short of the original route to Shepard."},"headline":"Line cut back to Eau Claire to Lynnwood/Millican","sources":[{"url":"https://calgary.ctvnews.ca/more-money-for-less-green-line-lrt-approval-reaction-remains-mixed-1.6985312","outlet":"CTV News Calgary","published_at":"2024-08-01","quote":"For $6.248 billion, the line will run from Eau Claire to Lynnwood/Millican, five stops short of the original route to Shepard in the southeast."}]},{"kind":"announcement","statement_date":"2024-09-03","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta (Transportation Minister Devin Dreeshen)"},"headline":"Alberta pulls its funding share","note":"Alberta's share of funding was $1.53B.","sources":[{"url":"https://www.cbc.ca/1.7326637","outlet":"CBC News","published_at":"2024-09-18","quote":"Dreeshen maintained he didn't kill the Green Line when he pulled the province's share of funding for it Sept. 3, contrary to claims by multiple members of Calgary city council that the LRT project was dead the moment the transportation minister made that move."}]},{"kind":"scope_change","statement_date":"2025-01-28","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta and City of Calgary"},"scope":{"description":"Alberta released a revised alignment in December 2024 with an elevated section through downtown and no downtown tunnel. Calgary City Council approved the new plan in January 2025, after the province threatened to pull its $1.53B share."},"headline":"Elevated downtown alignment replaces tunnel","sources":[{"url":"https://globalnews.ca/news/10982057/calgary-city-council-approves-new-green-line-plan/","outlet":"Global News","published_at":"2025-01-29","quote":"The decision follows an ultimatum from the provincial government, which commissioned an engineering firm to find an elevated alignment through the downtown core instead of the previously approved tunnel."},{"url":"https://www.cbc.ca/1.7409796","outlet":"CBC News","published_at":"2024-12-13","quote":"This iteration of the Green Line will feature no tunneling through Calgary's downtown, which was a major point of criticism from the province in the project's last alignment."}]},{"kind":"cost","statement_date":"2025-03-18","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta"},"cost":{"low":null,"high":null,"point":6.236,"currency":"CAD","dollar_year":2025,"covers":"capital cost"},"headline":"Province: $6.24B for Shepard to 7 Avenue SW","note":"Ottawa confirmed it would still contribute $1.5B, approving the updated route.","sources":[{"url":"https://ctvnews.ca/calgary/article/calgarys-green-line-lrt-back-on-track-following-federal-funding-approval","outlet":"CTV News Calgary","published_at":"2025-03-19","quote":"According to the province, the cost for a line from Shepard to Seventh Avenue S.W. downtown is $6.236 billion."}]},{"kind":"scope_change","statement_date":"2026-09-08","date_precision":"day","speaker":{"type":"proponent","name":"City of Calgary (Executive Committee)"},"scope":{"description":"The executive committee endorsed a surface alignment along 10 Avenue S.W. for the downtown section, replacing the elevated option. It still needs city council approval and formal confirmation from the provincial and federal governments."},"headline":"Surface downtown route endorsed","sources":[{"url":"https://www.ctvnews.ca/calgary/article/calgary-committee-endorses-surface-green-line-route-through-downtown/","outlet":"CTV News Calgary","published_at":"2026-09-10","quote":"The city’s executive committee voted 12-1 Tuesday to endorse a surface alignment along 10 Avenue S.W., sending the proposal to city council for approval."}]},{"kind":"cost","statement_date":"2026-09-08","date_precision":"day","speaker":{"type":"proponent","name":"City of Calgary (Executive Committee)"},"cost":{"low":null,"high":null,"point":6.248,"currency":"CAD","dollar_year":2026,"covers":"capital cost"},"headline":"Approved budget still $6.25B","note":"The province's preferred elevated option was estimated to cost approximately $1 billion more than the available budget.","sources":[{"url":"https://www.ctvnews.ca/calgary/article/calgary-committee-endorses-surface-green-line-route-through-downtown/","outlet":"CTV News Calgary","published_at":"2026-09-10","quote":"The surface alignment was the only one of three options presented to committee that could fit within the Green Line’s approved $6.248-billion project budget."}]},{"kind":"completion_target","statement_date":"2026-09-08","date_precision":"day","speaker":{"type":"proponent","name":"City of Calgary (Executive Committee)"},"target":{"date":"2031-01-01","precision":"year","event":"first_service"},"headline":"Southeast section to open in 2031","note":"Applies to the southeast portion between Shepard and the Event Centre/Grand Central Station area, where construction is underway. The city has not established an opening date for the downtown section.","sources":[{"url":"https://www.ctvnews.ca/calgary/article/calgary-committee-endorses-surface-green-line-route-through-downtown/","outlet":"CTV News Calgary","published_at":"2026-09-10","quote":"That portion is targeted to begin carrying passengers in 2031."}]},{"kind":"announcement","statement_date":"2026-09-22","date_precision":"day","speaker":{"type":"proponent","name":"Calgary City Council"},"headline":"Council approves the surface downtown route","note":"Provincial and federal confirmation of the new route was still pending.","sources":[{"url":"https://www.westernstandard.news/calgary/calgary-city-council-approves-ground-level-green-line/77221","outlet":"Western Standard","published_at":"2026-09-22","quote":"The Executive Committee recommended council approve Option 3, which it did on Tuesday by a vote of 12 to 2, with very little debate."}]}]},{"slug":"canadian-multi-mission-aircraft","name":"Canadian Multi-Mission Aircraft Project (P-8A Poseidon)","short_name":"P-8A patrol aircraft","sector":"defence","jurisdiction":"federal","status":"procurement","owner":"Government of Canada (National Defence)","url":"https://www.overruns.ca/projects/canadian-multi-mission-aircraft","first_announced":"2023-11-30","first_price":"$10.4B","first_price_date":"2023-11-30","first_price_speaker":"Government of Canada (National Defence)","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"project investment (aircraft, equipment, training, sustainment set-up, simulators, infrastructure, weapons)","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":"2026-11-19","last_monthly_review":"2026-11-05","summary":"Replacing the RCAF's CP-140 Aurora maritime patrol planes with up to 16 Boeing P-8A Poseidons, bought sole-source from the U.S. government in November 2023. Based at 14 Wing Greenwood, N.S., and 19 Wing Comox, B.C.","observations":[{"kind":"cost","statement_date":"2023-11-30","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (National Defence)"},"cost":{"low":null,"high":null,"point":10.4,"currency":"CAD","dollar_year":2023,"covers":"project investment (aircraft, equipment, training, sustainment set-up, simulators, infrastructure, weapons)"},"headline":"$10.4B for up to 16 P-8As","note":"Includes the U.S. sale itself plus simulators, infrastructure and weapons. Long-term in-service support is separate.","sources":[{"url":"https://ac-ada.ca/news/canada-purchasing-up-to-16-p-8a-poseidon-multi-mission-aircraft-for-the-royal-canadian-air-force/","outlet":"National Defence news release (reprinted by the Atlantic Canada Aerospace and Defence Association)","published_at":"2023-11-30","quote":"The estimated investment for this project is $10.4 billion CAD; it includes up to $5.9 billion USD for the P-8A, associated equipment, training devices and sustainment set-up. The balance will cover additional investments in simulators, infrastructure and weapons."},{"url":"https://www.theglobeandmail.com/business/article-federal-government-inks-deal-with-us-for-new-boeing-surveillance/","outlet":"The Globe and Mail","published_at":"2023-11-30","quote":"Ottawa will spend $10.4-billion on a new fleet of Boeing maritime patrol aircraft, a sole-source purchase that will replace Canada’s aging surveillance planes amid rising threats in the Arctic and elsewhere."}]},{"kind":"completion_target","statement_date":"2023-11-30","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (National Defence)"},"target":{"date":"2026-01-01","precision":"year","event":"first_delivery"},"headline":"First P-8A in 2026","sources":[{"url":"https://ac-ada.ca/news/canada-purchasing-up-to-16-p-8a-poseidon-multi-mission-aircraft-for-the-royal-canadian-air-force/","outlet":"National Defence news release (reprinted by the Atlantic Canada Aerospace and Defence Association)","published_at":"2023-11-30","quote":"The first P-8A should be delivered in 2026, and with an average of one aircraft delivered per month, all of the aircraft could be delivered as early as fall 2027."},{"url":"https://www.theglobeandmail.com/business/article-federal-government-inks-deal-with-us-for-new-boeing-surveillance/","outlet":"The Globe and Mail","published_at":"2023-11-30","quote":"The first deliveries are expected in 2026 with the final planes arriving about a year later, Defence Minister Bill Blair said at a news conference in Ottawa."}]},{"kind":"completion_target","statement_date":"2023-11-30","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (National Defence)"},"target":{"date":"2027-01-01","precision":"year","event":"final_delivery"},"headline":"All aircraft as early as fall 2027","sources":[{"url":"https://ac-ada.ca/news/canada-purchasing-up-to-16-p-8a-poseidon-multi-mission-aircraft-for-the-royal-canadian-air-force/","outlet":"National Defence news release (reprinted by the Atlantic Canada Aerospace and Defence Association)","published_at":"2023-11-30","quote":"The first P-8A should be delivered in 2026, and with an average of one aircraft delivered per month, all of the aircraft could be delivered as early as fall 2027."}]}]},{"slug":"canadian-patrol-submarine-project","name":"Canadian Patrol Submarine Project","short_name":"New submarines","sector":"defence","jurisdiction":"federal","status":"procurement","owner":"Government of Canada (Department of National Defence)","url":"https://www.overruns.ca/projects/canadian-patrol-submarine-project","first_announced":"2025-08-26","first_price":"up to $43B","first_price_date":"2025-08-26","first_price_speaker":"Government of Canada","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"lifecycle","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":-12,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Up to 12 new conventional submarines to replace the navy's Victoria class. Thyssenkrupp Marine Systems of Germany was picked for negotiations in July 2026.","observations":[{"kind":"cost","statement_date":"2025-08-26","date_precision":"month","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":43,"point":null,"currency":"CAD","dollar_year":2025,"covers":"lifecycle"},"headline":"Up to $43B over the fleet's life","sources":[{"url":"https://thedefensepost.com/2025/08/28/canada-submarine-thyssenkrupp-hanwha/amp/","outlet":"The Defense Post","published_at":"2025-08-28","quote":"Ottawa estimates the program will cost up to 43 billion Canadian dollars ($31.1 billion) over its life cycle, with the first new submarine’s delivery due no later than 2035."}]},{"kind":"completion_target","statement_date":"2025-08-26","date_precision":"month","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2035-01-01","precision":"year","event":"first_delivery"},"headline":"First boat by 2035","sources":[{"url":"https://thedefensepost.com/2025/08/28/canada-submarine-thyssenkrupp-hanwha/amp/","outlet":"The Defense Post","published_at":"2025-08-28","quote":"Ottawa estimates the program will cost up to 43 billion Canadian dollars ($31.1 billion) over its life cycle, with the first new submarine’s delivery due no later than 2035."}]},{"kind":"milestone","statement_date":"2026-07-01","date_precision":"month","speaker":{"type":"government","name":"Government of Canada"},"milestone":{"title":"Talks opened with Thyssenkrupp Marine Systems for 12 submarines","achieved":true},"headline":"TKMS chosen for negotiations","sources":[{"url":"https://www.navalreview.ca/2026/08/two-new-naval-projects-how-realistic-are-they/","outlet":"Naval Review (Jeff Gilmour)","published_at":"2026-08-07","quote":"In early July 2026 the federal government announced that it would begin discussions to purchase 12 submarines from Thyssen-Krupp Marine Systems (TKMS) of Germany under the Canadian Patrol Submarine Project (CPSP)."}]},{"kind":"completion_target","statement_date":"2026-07-01","date_precision":"month","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2034-01-01","precision":"year","event":"first_delivery"},"headline":"First four boats from early 2034","sources":[{"url":"https://www.navalreview.ca/2026/08/two-new-naval-projects-how-realistic-are-they/","outlet":"Naval Review (Jeff Gilmour)","published_at":"2026-08-07","quote":"The formal contracting is scheduled to be completed by the end of 2027, with the first four boats to be delivered at the beginning of 2034."}]},{"kind":"status","statement_date":"2026-07-01","date_precision":"month","speaker":{"type":"government","name":"Government of Canada"},"new_status":"procurement","headline":"In procurement","sources":[{"url":"https://www.navalreview.ca/2026/08/two-new-naval-projects-how-realistic-are-they/","outlet":"Naval Review (Jeff Gilmour)","published_at":"2026-08-07","quote":"The formal contracting is scheduled to be completed by the end of 2027, with the first four boats to be delivered at the beginning of 2034."}]}]},{"slug":"canadian-surface-combatant","name":"Canadian Surface Combatant (River-class destroyers)","short_name":"Surface combatants","sector":"defence","jurisdiction":"federal","status":"construction","owner":"National Defence (Royal Canadian Navy), with Public Services and Procurement Canada","url":"https://www.overruns.ca/projects/canadian-surface-combatant","first_announced":"2008-01-01","first_price":"$26.2B","first_price_date":"2008-01-01","first_price_speaker":"Government of Canada (Conservative government)","latest_estimate":"$60B","latest_estimate_date":"2026-06-12","latest_estimate_speaker":"National Defence","cost_basis":"capital cost","multiple_after_inflation":1.55,"multiple_as_announced":2.29,"delay_months":12,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Fifteen River-class warships being built by Irving Shipbuilding in Halifax to replace the navy's Halifax-class frigates and retired destroyers. Construction began in 2024 and the full order of 15 is not due until 2050.","observations":[{"kind":"cost","statement_date":"2008-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada (Conservative government)"},"cost":{"low":null,"high":null,"point":26.2,"currency":"CAD","dollar_year":2008,"covers":"capital cost"},"headline":"2008 budget of about $26.2B","note":"For 15 ships. The PBO said no detailed documentation exists for how this original figure was built.","sources":[{"url":"https://www.cbc.ca/lite/story/1.4141708","outlet":"The Canadian Press, via CBC News","published_at":"2017-06-01","quote":"more than twice the original 2008 budget of about $26.2 billion."}]},{"kind":"cost","statement_date":"2017-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada (Liberal government)"},"cost":{"low":null,"high":null,"point":60,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"Budget set at $60B in 2017","note":"Date is the year the budget was established, as described in a 2021 report.","sources":[{"url":"https://globalnews.ca/news/7614144/national-defence-60b-warship-project/","outlet":"The Canadian Press, via Global News","published_at":"2021-02-02","quote":"Crosby, however, was adamant that the project remains within the $60-billion budget established by the Liberal government in 2017."}]},{"kind":"cost","statement_date":"2017-06-01","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":null,"point":61.8,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"PBO: $61.8B for 15 ships","sources":[{"url":"https://www.cbc.ca/lite/story/1.4141708","outlet":"The Canadian Press, via CBC News","published_at":"2017-06-01","quote":"The parliamentary budget officer estimates Ottawa will have to spend nearly $61.8 billion to replace 15 ships"}]},{"kind":"cost","statement_date":"2019-01-01","date_precision":"year","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":null,"point":69.8,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"PBO: $69.8B","sources":[{"url":"https://www.defensenews.com/naval/2022/10/27/canadian-surface-combatant-cost-may-rise-9-with-delays-inflation/","outlet":"Defense News","published_at":"2022-10-27","quote":"The procurement cost ticked up to CA$69.8 billion in 2019, after Canada selected Lockheed Martin’s design for the ship, and then to CA$77.3 billion in 2021."}]},{"kind":"completion_target","statement_date":"2021-02-02","date_precision":"day","speaker":{"type":"government","name":"National Defence"},"target":{"date":"2030-01-01","precision":"year","event":"first_delivery"},"headline":"First ship now 2030-31","note":"Reported as years later than expected. The same report says the first ship was originally to be delivered in the mid-2020s.","sources":[{"url":"https://globalnews.ca/news/7614144/national-defence-60b-warship-project/","outlet":"The Canadian Press, via Global News","published_at":"2021-02-02","quote":"“We’re looking at the first ship being delivered to us in the early 2030s. … In this case, we’re really more specifically looking at the 2030-31 timeframe.”"}]},{"kind":"cost","statement_date":"2021-02-24","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":null,"point":77.3,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"PBO: $77.3B","sources":[{"url":"https://www.hilltimes.com/story/2021/03/01/285817/268605","outlet":"The Hill Times","published_at":"2021-03-01","quote":"The Feb. 24, 2021, report from the Parliamentary Budget Officer estimates that it will cost $77.3-billion to acquire 15 Canadian Surface Combatants."}]},{"kind":"cost","statement_date":"2022-10-27","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":null,"point":84.5,"currency":"CAD","dollar_year":2022,"covers":"capital cost"},"headline":"PBO: $84.5B to design and buy","note":"Development and acquisition only. The PBO said the update reflects revised production schedules and inflation projections.","sources":[{"url":"https://www.pbo-dpb.ca/en/news-releases--communiques-de-presse/cost-of-canadian-surface-combatants-to-hit-306-billion-over-65-year-life-cycle-says-pbo-le-cout-des-navires-de-combat-de-surface-canadiens-atteindra-306-milliards-sur-un-cycle-de-vie-de-65-ans-selon-le-dpb","outlet":"Parliamentary Budget Office","published_at":"2022-10-27","quote":"The PBO’s latest estimates for the Development and Acquisition phases have jumped to $84.5 billion."}]},{"kind":"cost","statement_date":"2022-10-27","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":null,"point":306,"currency":"CAD","dollar_year":2022,"covers":"lifecycle"},"headline":"PBO: $306B over the life of the ships","note":"Includes development, acquisition, operations, sustainment and disposal over 65 years. Not comparable with the acquisition budget.","sources":[{"url":"https://www.pbo-dpb.ca/en/publications/RP-2223-016-C--life-cycle-cost-canadian-surface-combatants-fiscal-analysis--cout-cycle-vie-navires-combat-surface-canadien-analyse-financiere","outlet":"Parliamentary Budget Office","published_at":"2022-10-27","quote":"Highlights The total life cycle cost of the CSC program is estimated to be $306.0 billion."}]},{"kind":"completion_target","statement_date":"2022-10-27","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"target":{"date":"2031-01-01","precision":"year","event":"first_delivery"},"headline":"PBO: first ship delivered 2031-32","sources":[{"url":"https://www.pbo-dpb.ca/en/news-releases--communiques-de-presse/cost-of-canadian-surface-combatants-to-hit-306-billion-over-65-year-life-cycle-says-pbo-le-cout-des-navires-de-combat-de-surface-canadiens-atteindra-306-milliards-sur-un-cycle-de-vie-de-65-ans-selon-le-dpb","outlet":"Parliamentary Budget Office","published_at":"2022-10-27","quote":"The Operations and Sustainment phase is estimated at $219.8 billion and is slated to begin in 2031-32, with the delivery of the first ship to the Royal Canadian Navy."}]},{"kind":"cost","statement_date":"2025-03-08","date_precision":"day","speaker":{"type":"government","name":"National Defence"},"cost":{"low":null,"high":null,"point":22.2,"currency":"CAD","dollar_year":2025,"covers":"first three ships only"},"headline":"First three ships: $22.2B","note":"A subset of the fleet, not comparable with the 15-ship figures.","sources":[{"url":"https://sootoday.com/national-news/ottawa-inks-initial-contract-for-new-river-class-destroyers-with-irving-10345401","outlet":"The Canadian Press, via Sault Ste. Marie News","published_at":"2025-03-08","quote":"The implementation contract is worth $8 billion for the first six years and only covers part of the tab for the first three ships, which will eventually cost $22.2 billion, to be built in Halifax."}]},{"kind":"cost","statement_date":"2026-06-12","date_precision":"day","speaker":{"type":"government","name":"National Defence"},"cost":{"low":null,"high":null,"point":60,"currency":"CAD","dollar_year":2026,"covers":"capital cost"},"headline":"About $60B for all 15 ships","sources":[{"url":"https://www.ckom.com/?p=1060566","outlet":"The Canadian Press, via CKOM","published_at":"2026-06-12","quote":"The Department of National Defence has said all 15 are expected to cost about $60-billion, but in 2022 the Parliamentary Budget Officer suggested it could be as much as $80 billion."}]}]},{"slug":"centre-block-rehabilitation","name":"Centre Block rehabilitation (Parliament Hill)","short_name":"Centre Block","sector":"other","jurisdiction":"federal","status":"construction","owner":"Government of Canada (Public Services and Procurement Canada)","url":"https://www.overruns.ca/projects/centre-block-rehabilitation","first_announced":"2021-06-17","first_price":"$4.5–5B","first_price_date":"2021-06-17","first_price_speaker":"Public Services and Procurement Canada","latest_estimate":"$4.5–5B","latest_estimate_date":"2024-06-28","latest_estimate_speaker":"Public Services and Procurement Canada","cost_basis":"project cost","multiple_after_inflation":0.88,"multiple_as_announced":1,"delay_months":0,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"The gutting and restoration of Parliament's Centre Block in Ottawa, closed since 2018, including a new underground visitor centre. Run by Public Services and Procurement Canada.","observations":[{"kind":"status","statement_date":"2018-12-01","date_precision":"year","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"new_status":"construction","headline":"Building closed for renovation","sources":[{"url":"https://cjme.com/?p=869176","outlet":"The Canadian Press, via CJME","published_at":"2024-11-14","quote":"The renovation began in 2018 and is expected to be complete in either 2030 or 2031."}]},{"kind":"cost","statement_date":"2021-06-17","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"cost":{"low":4.5,"high":5,"point":null,"currency":"CAD","dollar_year":2021,"covers":"project cost"},"headline":"First estimate: $4.5B to $5B","sources":[{"url":"https://www.theglobeandmail.com/canada/article-massive-restoration-of-parliaments-centre-block-to-cost-up-to-5/","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2021-06-17","quote":"Construction on the traditional seat of the House of Commons and Senate is expected to wrap before 2032, with a cost of between $4.5-billion and $5-billion, Public Services and Procurement Canada said Thursday in a release."}]},{"kind":"completion_target","statement_date":"2021-06-17","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"target":{"date":"2030-01-01","precision":"year","event":"completion"},"headline":"Work to continue until at least 2030","sources":[{"url":"https://www.theglobeandmail.com/canada/article-massive-restoration-of-parliaments-centre-block-to-cost-up-to-5/","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2021-06-17","quote":"The massive restoration project under way at Parliament’s Centre Block will cost up to $5-billion and continue at least until 2030, federal officials say."}]},{"kind":"cost","statement_date":"2024-06-28","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"cost":{"low":4.5,"high":5,"point":null,"currency":"CAD","dollar_year":2024,"covers":"project cost"},"headline":"Unchanged: $4.5B to $5B","sources":[{"url":"https://www.theglobeandmail.com/politics/article-renovation-of-parliaments-centre-block-on-schedule-with-expected/","outlet":"The Globe and Mail","published_at":"2024-07-02","quote":"Of the project’s forecast cost of between $4.5-billion and $5-billion, $896-million has been spent so far, says the June 28 update from the Public Services and Procurement Canada on work involving the main building on Parliament Hill."}]},{"kind":"completion_target","statement_date":"2024-11-14","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"target":{"date":"2030-01-01","precision":"year","event":"completion"},"headline":"Complete in 2030 or 2031, reopening 2032","sources":[{"url":"https://cjme.com/?p=869176","outlet":"The Canadian Press, via CJME","published_at":"2024-11-14","quote":"The renovation began in 2018 and is expected to be complete in either 2030 or 2031."}]}]},{"slug":"ch-148-cyclone","name":"CH-148 Cyclone (Maritime Helicopter Project)","short_name":"Cyclone helicopters","sector":"defence","jurisdiction":"federal","status":"operational","owner":"Government of Canada (Department of National Defence)","url":"https://www.overruns.ca/projects/ch-148-cyclone","first_announced":"2003-01-01","first_price":"$5.1B","first_price_date":"2004-07-23","first_price_speaker":"Government of Canada","latest_estimate":"$9B","latest_estimate_date":"2021-12-06","latest_estimate_speaker":"Department of National Defence","cost_basis":"acquisition and in-service support","multiple_after_inflation":1.3,"multiple_as_announced":1.76,"delay_months":78,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Twenty-eight Sikorsky maritime helicopters to replace the navy's 1960s Sea Kings. Contracted in 2004 for delivery from 2008; the first aircraft arrived in 2015.","observations":[{"kind":"announcement","statement_date":"2003-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada (Prime Minister Paul Martin)"},"headline":"Martin pegs the helicopters at $2.8B, before maintenance","note":"Shown on the timeline but not used as the cost baseline: it covered acquisition only, while the 2004 contract and every later total include in-service support. Editorial decision, 2026-10-06.","sources":[{"url":"https://amp.cbc.ca/news/canada/5-of-canada-s-biggest-military-deals-1.1137763","outlet":"CBC News","published_at":"2012-04-11","quote":"In 2003, Paul Martin pegged the program at $2.8 billion, which did not include long-term maintenance."}]},{"kind":"cost","statement_date":"2004-07-23","date_precision":"month","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":5.1,"currency":"CAD","dollar_year":2004,"covers":"acquisition and in-service support"},"headline":"Sikorsky contract for 28 Cyclones: $5.1B","sources":[{"url":"https://www.cbc.ca/news/canada/faq-how-canada-procured-new-military-helicopters-1.940250","outlet":"CBC News","published_at":"2010-10-26","quote":"The contract for 28 Cyclone helicopters was awarded to the U.S-based Sikorsky in July 2004 in a deal valued at $5.1 billion."}]},{"kind":"completion_target","statement_date":"2004-07-23","date_precision":"month","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2008-01-01","precision":"year","event":"first_delivery"},"headline":"First helicopter due 2008","sources":[{"url":"https://www.cbc.ca/news/canada/faq-how-canada-procured-new-military-helicopters-1.940250","outlet":"CBC News","published_at":"2010-10-26","quote":"The first helicopter was to be delivered in 2008, with another helicopter to be delivered every 27 months."}]},{"kind":"completion_target","statement_date":"2008-12-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada and Sikorsky"},"target":{"date":"2010-11-01","precision":"month","event":"first_delivery"},"headline":"Delivery deadline moved to November 2010","sources":[{"url":"https://www.cbc.ca/news/canada/faq-how-canada-procured-new-military-helicopters-1.940250","outlet":"CBC News","published_at":"2010-10-26","quote":"Sikorsky and the federal government negotiated a new deadline delivery of November 2010 after the original 2008 target was missed."}]},{"kind":"cost","statement_date":"2010-10-26","date_precision":"day","speaker":{"type":"watchdog","name":"Auditor General of Canada (Sheila Fraser)"},"cost":{"low":null,"high":null,"point":5.7,"currency":"CAD","dollar_year":2010,"covers":"acquisition and in-service support"},"headline":"Auditor General: about $5.7B","sources":[{"url":"https://amp.cbc.ca/news/canada/5-of-canada-s-biggest-military-deals-1.1137763","outlet":"CBC News","published_at":"2012-04-11","quote":"Former Auditor General Sheila Fraser said the cost of the program had grown to about $5.7 billion, up from an initial estimates of $5.1 billion."}]},{"kind":"cost","statement_date":"2014-06-23","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":1.9,"currency":"CAD","dollar_year":2014,"covers":"acquisition"},"headline":"Acquisition $1.9B after the 2013-14 contract amendments","sources":[{"url":"https://amp.cbc.ca/news/politics/sea-king-replacements-7-6b-cyclone-maritime-helicopters-lack-key-safety-requirement-1.2684036","outlet":"CBC News","published_at":"2014-06-23","quote":"In fact, the total budget is $7.6 billion - $5.7 billion for in-service support, including the amendments to the contract, and $1.9 billion for the acquisition of the helicopters."}]},{"kind":"cost","statement_date":"2014-06-23","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":7.6,"currency":"CAD","dollar_year":2014,"covers":"acquisition and in-service support"},"headline":"Total budget $7.6B","sources":[{"url":"https://amp.cbc.ca/news/politics/sea-king-replacements-7-6b-cyclone-maritime-helicopters-lack-key-safety-requirement-1.2684036","outlet":"CBC News","published_at":"2014-06-23","quote":"In fact, the total budget is $7.6 billion - $5.7 billion for in-service support, including the amendments to the contract, and $1.9 billion for the acquisition of the helicopters."}]},{"kind":"status","statement_date":"2015-06-19","date_precision":"day","speaker":{"type":"proponent","name":"Sikorsky"},"new_status":"operational","headline":"First six Cyclones delivered","note":"Delivered seven years after the original 2008 target. Final delivery was planned for June 2022.","sources":[{"url":"https://www.globaltrademag.com/sikorsky-delivers-six-helicopters-to-the-royal-canadian-air-force/","outlet":"Global Trade Magazine","published_at":"2015-06-24","quote":"The Royal Canadian Air Force (RCAF) has taken delivery of six Sikorsky-made CH-148 Cyclone maritime patrol helicopters."}]},{"kind":"cost","statement_date":"2021-12-06","date_precision":"day","speaker":{"type":"government","name":"Department of National Defence"},"cost":{"low":null,"high":null,"point":3.2,"currency":"CAD","dollar_year":2021,"covers":"acquisition"},"headline":"DND: acquisition $3.2B","sources":[{"url":"https://search.open.canada.ca/qpnotes/record/dnd-mdn%2CDND-2022-QP-00012","outlet":"Department of National Defence (Question Period note)","published_at":"2021-12-06","quote":"Background: Quick Facts Fleet procurement: * CH-148 Cyclone fleet: 28 aircraft procured * Acquisition cost: $3.2 billion * Cost for major in-service support until 2038: $5.8 billion."}]},{"kind":"cost","statement_date":"2021-12-06","date_precision":"day","speaker":{"type":"government","name":"Department of National Defence"},"cost":{"low":null,"high":null,"point":9,"currency":"CAD","dollar_year":2021,"covers":"acquisition and in-service support","derived":[{"field":"point","sum_of":[3.2,5.8]}]},"headline":"DND: $3.2B acquisition plus $5.8B support to 2038","sources":[{"url":"https://search.open.canada.ca/qpnotes/record/dnd-mdn%2CDND-2022-QP-00012","outlet":"Department of National Defence (Question Period note)","published_at":"2021-12-06","quote":"Background: Quick Facts Fleet procurement: * CH-148 Cyclone fleet: 28 aircraft procured * Acquisition cost: $3.2 billion * Cost for major in-service support until 2038: $5.8 billion."}]}]},{"slug":"champlain-bridge","name":"Samuel De Champlain Bridge","short_name":"Champlain Bridge","sector":"road_bridge","jurisdiction":"federal","status":"operational","owner":"Infrastructure Canada (Government of Canada)","url":"https://www.overruns.ca/projects/champlain-bridge","first_announced":"2011-10-05","first_price":"$5B","first_price_date":"2011-10-05","first_price_speaker":"Government of Canada (Transport Minister Denis Lebel)","latest_estimate":"$4.23B","latest_estimate_date":"2015-06-19","latest_estimate_speaker":"Government of Canada (Infrastructure Minister Denis Lebel)","cost_basis":"capital cost","multiple_after_inflation":0.8,"multiple_as_announced":0.85,"delay_months":6,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A cable-stayed replacement for the aging Champlain Bridge between Montreal and its South Shore, built as a public-private partnership with the Signature on the St. Lawrence consortium. Federal costs include the bridge, a Nuns' Island span and Highway 15 work.","observations":[{"kind":"cost","statement_date":"2010-01-01","date_precision":"year","speaker":{"type":"other","name":"Delcan (engineering report)"},"cost":{"low":1.3,"high":2,"point":null,"currency":"CAD","dollar_year":2010,"covers":"bridge only, replacement"},"headline":"Engineering report: at least $1.3B for a bridge","note":"From a 2010 engineering report, before Ottawa had committed to a replacement. Not an official government estimate, and narrower in scope than the 2011 figure.","sources":[{"url":"https://montreal.ctvnews.ca/replacement-for-champlain-bridge-could-include-tolls-feds-say-1.707662","outlet":"The Canadian Press, via CTV News","published_at":"2011-10-06","quote":"The same report said that a replacement bridge would cost at least $1.3 billion, while a tunnel would cost $1.9 billion, however those numbers could climb as high as $2 billion for the bridge and $3 billion for the tunnel."}]},{"kind":"cost","statement_date":"2011-10-05","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Transport Minister Denis Lebel)"},"cost":{"low":null,"high":null,"point":5,"currency":"CAD","dollar_year":2011,"covers":"capital cost"},"headline":"Replacement announced at about $5B","note":"Reported on the day Ottawa announced it would replace the bridge. Global also noted that a new bridge had previously been pegged at around $1.3B.","sources":[{"url":"https://globalnews.ca/news/162719/feds-announce-plan-to-replace-montreals-champlain-bridge-within-10-years","outlet":"The Canadian Press, via Global News","published_at":"2011-10-05","quote":"Building a new span to Montreal’s south shore could take as long as 10 years and cost $5 billion, but Transport Minister Denis Lebel suggested it would also create 30,000 jobs and be paid for by a toll system."}]},{"kind":"cost","statement_date":"2015-06-19","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Infrastructure Minister Denis Lebel)"},"cost":{"low":null,"high":null,"point":4.23,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"Project contract announced at $4.23B","note":"Covers the new bridge, a new Nuns' Island span and widening of Highway 15, as described by CBC.","sources":[{"url":"https://amp.cbc.ca/news/canada/montreal/new-champlain-bridge-to-cost-4-23b-1.3120454","outlet":"CBC News","published_at":"2015-06-19","quote":"Federal Infrastructure Minister Denis Lebel announced Friday afternoon that the new Champlain Bridge will cost $4.23 billion."}]},{"kind":"completion_target","statement_date":"2015-06-19","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Infrastructure Minister Denis Lebel)"},"target":{"date":"2018-12-01","precision":"year","event":"completion"},"headline":"Bridge to be built by 2018","note":"The project agreement later cited by officials called for opening in December 2018.","sources":[{"url":"https://amp.cbc.ca/news/canada/montreal/new-champlain-bridge-to-cost-4-23b-1.3120454","outlet":"CBC News","published_at":"2015-06-19","quote":"New Champlain Bridge will be built by 2018, Lebel says"}]},{"kind":"completion_target","statement_date":"2018-04-13","date_precision":"day","speaker":{"type":"government","name":"Government of Canada and Signature on the St. Lawrence"},"target":{"date":"2018-12-21","precision":"day","event":"first_service"},"headline":"Opening reset to Dec. 21, 2018","note":"Part of a settlement between Ottawa and the consortium.","sources":[{"url":"https://www.cbc.ca/news/canada/montreal/champlain-bridge-open-dec-1.4619218","outlet":"CBC News","published_at":"2018-04-13","quote":"The new Champlain Bridge is expected to be ready for Dec. 21, 2018."}]},{"kind":"status","statement_date":"2019-06-24","date_precision":"day","speaker":{"type":"media_estimate","name":"The Canadian Press"},"new_status":"operational","headline":"Opened to traffic in June 2019","note":"Open to traffic in both directions on July 1, 2019, per federal question period notes.","sources":[{"url":"https://nationalobserver.com/2019/06/24/news/montreals-new-44-billion-champlain-bridge-opens-first-traffic","outlet":"The Canadian Press, via Canada's National Observer","published_at":"2019-06-25","quote":"Montreal's expensive new Samuel De Champlain Bridge opened to traffic for the first time this morning, about six months behind schedule."}]},{"kind":"cost","statement_date":"2019-06-26","date_precision":"day","speaker":{"type":"media_estimate","name":"The Canadian Press"},"cost":{"low":null,"high":null,"point":4.435,"currency":"CAD","dollar_year":2019,"covers":"capital cost","derived":[{"field":"point","sum_of":[4.2,0.235]}]},"headline":"About $4.4B after $235M added","note":"Press figure. Federal question period notes put the project agreement at $4.212B including the extra $235M, over a 34-year term including operations, so the final cost is not settled in the sources found.","sources":[{"url":"https://cfjctoday.com/2019/06/26/montreals-costly-new-champlain-bridge-opens-to-northbound-traffic/","outlet":"The Canadian Press, via CFJC Today","published_at":"2019-06-26","quote":"It was originally scheduled to open last December, but various delays pushed back the opening and added another $235 million to the original $4.2 billion price tag."}]}]},{"slug":"churchill-falls-gull-island","name":"Churchill Falls expansion and Gull Island hydro","short_name":"Churchill Falls and Gull Island","sector":"hydro","jurisdiction":"multi","status":"planning","owner":"Hydro-Québec and Newfoundland and Labrador Hydro (provincial Crown utilities), with federal financing","url":"https://www.overruns.ca/projects/churchill-falls-gull-island","first_announced":"2024-12-12","first_price":"$33B+","first_price_date":"2024-12-12","first_price_speaker":"Government of Newfoundland and Labrador","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"hydro construction (Gull Island and Churchill Falls expansion)","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":null,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"New hydro generation on Labrador's Churchill River under a Hydro-Québec and Newfoundland and Labrador Hydro deal that replaces the 1969 power contract: a Gull Island station, Churchill Falls upgrades, plus wind and transmission. Not yet binding.","observations":[{"kind":"cost","statement_date":"2024-12-12","date_precision":"day","speaker":{"type":"government","name":"Government of Newfoundland and Labrador"},"cost":{"low":33,"high":null,"point":null,"currency":"CAD","dollar_year":2024,"covers":"hydro construction (Gull Island and Churchill Falls expansion)"},"headline":"MOU: at least $33B of construction","sources":[{"url":"https://www.gov.nl.ca/releases/2024/exec/1212n02/","outlet":"Government of Newfoundland and Labrador","published_at":"2024-12-12","quote":"The value of these combined construction projects is at least $33 Billion and will provide thousands of jobs over a generation."}]},{"kind":"status","statement_date":"2024-12-12","date_precision":"day","speaker":{"type":"proponent","name":"Hydro-Québec"},"new_status":"planning","headline":"Non-binding MOU signed","sources":[{"url":"https://globalnews.ca/news/10914489/churchill-falls-new-deal-quebec-newfoundland-labrador","outlet":"Global News","published_at":"2024-12-12","quote":"Hydro-Québec described the preliminary deal as “non-binding and will serve to guide future discussions” in a statement, adding both provinces will benefit from it, a statement Legault echoed when speaking to reporters."}]},{"kind":"scope_change","statement_date":"2026-08-17","date_precision":"day","speaker":{"type":"government","name":"Governments of Canada, Quebec and Newfoundland and Labrador"},"scope":{"description":"The 2024 MOU was renegotiated; the package now adds a Labrador onshore wind project and new transmission lines alongside Gull Island and the Churchill Falls upgrades."},"headline":"Deal renegotiated, wind and transmission added","sources":[{"url":"https://environmentjournal.ca/?p=24725","outlet":"Environment Journal","published_at":"2026-08-19","quote":"Together, these projects represent the largest clean energy investment in North American history, at nearly $70 billion."}]},{"kind":"cost","statement_date":"2026-08-17","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":70,"currency":"CAD","dollar_year":2026,"covers":"full package including wind and transmission"},"headline":"Nearly $70B including wind and transmission","note":"Covers more than the 2024 figure (wind and transmission are added), so the two are not compared directly.","sources":[{"url":"https://environmentjournal.ca/?p=24725","outlet":"Environment Journal","published_at":"2026-08-19","quote":"Together, these projects represent the largest clean energy investment in North American history, at nearly $70 billion."}]}]},{"slug":"contrecoeur-container-terminal","name":"Contrecœur Container Terminal","short_name":"Contrecœur terminal","sector":"other","jurisdiction":"QC","status":"construction","owner":"Montreal Port Authority (federal port authority); financing from the Canada Infrastructure Bank, Transport Canada and Québec","url":"https://www.overruns.ca/projects/contrecoeur-container-terminal","first_announced":"2019-08-14","first_price":"$750M","first_price_date":"2019-08-14","first_price_speaker":"Montreal Port Authority (with the Canada Infrastructure Bank)","latest_estimate":"$2.3B","latest_estimate_date":"2025-09-11","latest_estimate_speaker":"Minister Dominic LeBlanc","cost_basis":"capital cost","multiple_after_inflation":2.54,"multiple_as_announced":3.07,"delay_months":84,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A new container terminal for the Port of Montréal at Contrecœur, about 40 km downstream, on federal land managed by the Montreal Port Authority. In-water works began in October 2025; commercial operations are targeted for 2030.","observations":[{"kind":"cost","statement_date":"2019-08-14","date_precision":"day","speaker":{"type":"proponent","name":"Montreal Port Authority (with the Canada Infrastructure Bank)"},"cost":{"low":null,"high":null,"point":0.75,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"$750M","note":"Announced with a $300M Canada Infrastructure Bank loan. The port has since said its 2019 ceiling was $950M.","sources":[{"url":"https://maritimemag.com/canada-infrastructure-bank-commits-300-million-to-contrecoeur-project/","outlet":"Maritime Magazine","published_at":"2019-08-14","quote":"The project is valued at $750 million."}]},{"kind":"completion_target","statement_date":"2019-08-14","date_precision":"day","speaker":{"type":"proponent","name":"Montreal Port Authority"},"target":{"date":"2023-01-01","precision":"year","event":"completion"},"headline":"Terminal complete by 2023","sources":[{"url":"https://maritimemag.com/canada-infrastructure-bank-commits-300-million-to-contrecoeur-project/","outlet":"Maritime Magazine","published_at":"2019-08-14","quote":"Once final regulatory approvals are made and a full financing package (involving the port, government and industry stakeholders) is assembled, the Montreal Port Authority would set the wheels in motion for new terminal completion by 2023,"}]},{"kind":"status","statement_date":"2021-03-02","date_precision":"day","speaker":{"type":"government","name":"Minister of Environment and Climate Change (Jonathan Wilkinson)"},"new_status":"approved","headline":"Federal environmental approval","sources":[{"url":"https://amp.cbc.ca/news/canada/montreal/montreal-port-authority-contrec%C5%93ur-terminal-1.5932913","outlet":"CBC News","published_at":"2021-03-02","quote":"Wilkinson's approval was the last step of many in getting the project authorized, and now the port authority is ready to make a call for tenders with an aim to get the facility operational by 2024."}]},{"kind":"completion_target","statement_date":"2021-03-02","date_precision":"day","speaker":{"type":"proponent","name":"Montreal Port Authority"},"target":{"date":"2024-01-01","precision":"year","event":"completion"},"headline":"Operational by 2024","sources":[{"url":"https://amp.cbc.ca/news/canada/montreal/montreal-port-authority-contrec%C5%93ur-terminal-1.5932913","outlet":"CBC News","published_at":"2021-03-02","quote":"Wilkinson's approval was the last step of many in getting the project authorized, and now the port authority is ready to make a call for tenders with an aim to get the facility operational by 2024."}]},{"kind":"cost","statement_date":"2021-07-09","date_precision":"day","speaker":{"type":"proponent","name":"Montreal Port Authority"},"cost":{"low":0.75,"high":0.95,"point":null,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"$750M-950M","sources":[{"url":"https://ici.radio-canada.ca/nouvelle/1807841/terminal-contecoeur-port-montreal-appel-offres-international","outlet":"Radio-Canada","published_at":"2021-07-09","quote":"Le coût du nouveau terminal, estimé entre 750 et 950 millions de dollars, sera assumé en partie par la Banque de l’infrastructure du Canada, qui versera 300 millions de dollars, et par le gouvernement du Québec qui a promis 55 millions."}]},{"kind":"completion_target","statement_date":"2021-07-09","date_precision":"day","speaker":{"type":"proponent","name":"Montreal Port Authority"},"target":{"date":"2025-10-01","precision":"quarter","event":"completion"},"headline":"In service by end of 2025","sources":[{"url":"https://ici.radio-canada.ca/nouvelle/1807841/terminal-contecoeur-port-montreal-appel-offres-international","outlet":"Radio-Canada","published_at":"2021-07-09","quote":"Au moins trois consortiums seraient en lice pour décrocher la construction du nouveau terminal, dont la mise en service est prévue pour la fin de 2025."}]},{"kind":"announcement","statement_date":"2023-04-27","date_precision":"day","speaker":{"type":"proponent","name":"Montreal Port Authority (Martin Imbleau, CEO)"},"headline":"CEO: the 2019 estimate of $950M no longer holds","note":"He declined to confirm the $1.4B reported by The Globe and Mail.","sources":[{"url":"https://ici.radio-canada.ca/nouvelle/1974864/port-montreal-contrecoeur-financement-federal","outlet":"Radio-Canada","published_at":"2023-04-27","quote":"En entrevue à l'émission Zone économie, le PDG du Port de Montréal, Martin Imbleau, a affirmé que l'estimation faite en 2019, soit un investissement de 950 millions de dollars, ne tenait plus."}]},{"kind":"cost","statement_date":"2023-04-27","date_precision":"day","speaker":{"type":"media_estimate","name":"The Globe and Mail (unnamed sources)"},"cost":{"low":null,"high":null,"point":1.4,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"Reported: about $1.4B","note":"From unnamed sources, not the port authority, so not used as the official figure.","sources":[{"url":"https://www.cbc.ca/news/canada/montreal/port-of-montreal-contrecoeur-expansion-costs-balloon-1.6825070","outlet":"The Canadian Press, via CBC News","published_at":"2023-04-27","quote":"The cost of the expansion of the Port of Montreal with a new terminal at Contrecoeur has risen from a $950-million ceiling to about $1.4 billion as a result of inflation, sources say."},{"url":"https://www.theglobeandmail.com/business/article-port-of-montreal-contrecoeur-terminal/","outlet":"The Globe and Mail","published_at":"2023-10-10","quote":"Lawrence River have ballooned to $1.4-billion, roughly 50 per cent more than the maximum $950-million calculated in 2019 before the COVID-19 crisis."}]},{"kind":"milestone","statement_date":"2023-10-10","date_precision":"day","speaker":{"type":"government","name":"Transport Canada"},"milestone":{"title":"Up to $150M in federal funding","achieved":true},"headline":"Ottawa adds up to $150M","sources":[{"url":"https://www.theglobeandmail.com/business/article-port-of-montreal-contrecoeur-terminal/","outlet":"The Globe and Mail","published_at":"2023-10-10","quote":"The Port of Montreal has secured up to $150-million in federal funding for its container terminal expansion project in Contrecoeur, a key piece of transportation infrastructure needed to service markets in Quebec, Ontario and the U.S."}]},{"kind":"cost","statement_date":"2025-02-17","date_precision":"day","speaker":{"type":"government","name":"Premier François Legault (Québec)"},"cost":{"low":null,"high":null,"point":1.5,"currency":"CAD","dollar_year":2025,"covers":"capital cost"},"headline":"Québec: 'a $1.5-billion project'","note":"Other outlets reported $1.6B the same day.","sources":[{"url":"https://ici.radio-canada.ca/nouvelle/2141428/expansion-port-montreal-contrecoeur-quebec","outlet":"Radio-Canada","published_at":"2025-02-17","quote":"Mais c'est un projet de 1,5 milliard $ où le gouvernement du Québec met 130 millions $, donc..."}]},{"kind":"cost","statement_date":"2025-09-11","date_precision":"day","speaker":{"type":"government","name":"Minister Dominic LeBlanc"},"cost":{"low":null,"high":null,"point":2.3,"currency":"CAD","dollar_year":2025,"covers":"capital cost"},"headline":"Ottawa: $2.3B","note":"The port authority wouldn't confirm it, but said electrification had been added.","sources":[{"url":"https://www.ttnews.com/articles/port-montreal-cost-soars","outlet":"Bloomberg, via Transport Topics","published_at":"2025-09-11","quote":"The cost of a new Port of Montreal terminal that Canadian Prime Minister Mark Carney says is in the national interest has soared to C$2.3 billion ($1.7 billion), according to a Cabinet minister."},{"url":"https://www.noovo.info/nouvelle/le-cout-de-lexpansion-du-port-de-montreal-a-contrecoeur-serait-maintenant-de-2-3g.html","outlet":"Noovo Info","published_at":"2025-09-11","quote":"Jeudi, en annonçant que ce projet était maintenant inclus dans la liste des projets soutenus par le Bureau des grands projets, liste présentée à Edmonton par le premier ministre Mark Carney, le ministre Dominic LeBlanc a parlé à deux reprises d’un projet de 2,3 milliards $, soit une augmentation de 700 millions $ ou près de 44 %."}]},{"kind":"completion_target","statement_date":"2025-09-11","date_precision":"day","speaker":{"type":"government","name":"Minister Dominic LeBlanc"},"target":{"date":"2030-01-01","precision":"year","event":"completion"},"headline":"Finished by 2030","sources":[{"url":"https://www.noovo.info/nouvelle/le-cout-de-lexpansion-du-port-de-montreal-a-contrecoeur-serait-maintenant-de-2-3g.html","outlet":"Noovo Info","published_at":"2025-09-11","quote":"On reconnaît qu'il y a un élément de financement public pour combler les montants nécessaires pour arriver à 2,3 milliards $ pour finir le projet d'ici 2030."}]},{"kind":"status","statement_date":"2025-10-01","date_precision":"month","speaker":{"type":"proponent","name":"Montreal Port Authority"},"new_status":"construction","headline":"In-water construction begins","sources":[{"url":"https://cib-bic.ca/en/medias/articles/landmark-1.16-billion-loan-to-boost-trade-capacity-jobs-and-economic-growth-through-one-of-canadas-largest-port-expansions","outlet":"Canada Infrastructure Bank","published_at":"2026-04-06","quote":"Construction of critical in-water works including dredging, quay wall construction and other infrastructure required for vessel access and operations began in October 2025 and is being delivered by a joint venture between Aecon and Pomerleau."}]},{"kind":"milestone","statement_date":"2026-04-06","date_precision":"day","speaker":{"type":"government","name":"Canada Infrastructure Bank"},"milestone":{"title":"Canada Infrastructure Bank loan of $1.16B","achieved":true},"headline":"$1.16B federal loan","sources":[{"url":"https://cib-bic.ca/en/medias/articles/landmark-1.16-billion-loan-to-boost-trade-capacity-jobs-and-economic-growth-through-one-of-canadas-largest-port-expansions","outlet":"Canada Infrastructure Bank","published_at":"2026-04-06","quote":"CONTRECŒUR – Canada’s largest east coast port expansion moves forward as the Canada Infrastructure Bank (CIB) is supporting the new Contrecoeur container terminal by loaning $1.16 billion to the Montreal Port Authority (MPA)."}]},{"kind":"completion_target","statement_date":"2026-04-06","date_precision":"day","speaker":{"type":"government","name":"Canada Infrastructure Bank"},"target":{"date":"2030-01-01","precision":"year","event":"completion"},"headline":"Commercial operations targeted for 2030","sources":[{"url":"https://cib-bic.ca/en/medias/articles/landmark-1.16-billion-loan-to-boost-trade-capacity-jobs-and-economic-growth-through-one-of-canadas-largest-port-expansions","outlet":"Canada Infrastructure Bank","published_at":"2026-04-06","quote":"Construction is expected to begin in 2027 on building out terminal and logistics infrastructure, with commercial operations targeted for 2030."}]}]},{"slug":"darlington-new-nuclear","name":"Darlington New Nuclear Project (small modular reactors)","short_name":"Darlington SMRs","sector":"energy","jurisdiction":"ON","status":"construction","owner":"Ontario Power Generation (owned by the Province of Ontario); equity from the Canada Growth Fund and Building Ontario Fund","url":"https://www.overruns.ca/projects/darlington-new-nuclear","first_announced":"2021-12-02","first_price":"$20.9B","first_price_date":"2025-05-08","first_price_speaker":"Government of Ontario / Ontario Power Generation","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":24,"delay_is_minimum":true,"scope_changed":false,"last_reviewed":"2026-11-19","last_monthly_review":"2026-11-05","summary":"Four GE Vernova Hitachi BWRX-300 small modular reactors beside the Darlington station in Clarington, Ont., built by Ontario Power Generation, the province's wholly owned utility. Only the first unit has final approval.","observations":[{"kind":"announcement","statement_date":"2021-12-02","date_precision":"day","speaker":{"type":"proponent","name":"Ontario Power Generation"},"headline":"OPG picks the BWRX-300 for Darlington","note":"No cost given.","sources":[{"url":"https://world-nuclear-news.org/Articles/OPG-chooses-BWRX-300-SMR-for-Darlington-new-build","outlet":"World Nuclear News","published_at":"2021-12-02","quote":"Ontario Power Generation has selected the BWRX-300 small modular reactor for the Darlington new nuclear site, and will work with GE Hitachi Nuclear Energy to deploy the reactor."}]},{"kind":"completion_target","statement_date":"2021-12-02","date_precision":"day","speaker":{"type":"proponent","name":"Ontario Power Generation"},"target":{"date":"2028-01-01","precision":"year","event":"first_service"},"headline":"First reactor 'as early as 2028'","sources":[{"url":"https://world-nuclear-news.org/Articles/OPG-chooses-BWRX-300-SMR-for-Darlington-new-build","outlet":"World Nuclear News","published_at":"2021-12-02","quote":"Canada's first commercial, grid-scale, SMR could be completed as early as 2028."}]},{"kind":"cost","statement_date":"2025-05-08","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario / Ontario Power Generation"},"cost":{"low":null,"high":null,"point":20.9,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"$20.9B for four reactors","note":"In 2024 dollars. Only the first reactor has final approval.","sources":[{"url":"https://www.theglobeandmail.com/business/article-ontarios-darlington-smr-project-to-cost-nearly-21-billion/","outlet":"The Globe and Mail","published_at":"2025-05-08","quote":"All told, the 1,200-megawatt plant‘s estimated cost is $20.9-billion, expressed in 2024 dollars."},{"url":"https://www.cbc.ca/1.7529338","outlet":"CBC News","published_at":"2025-05-08","quote":"It would be the first of four such reactors that OPG aims to build on the site, at a total project cost of $20.9 billion, in an effort to meet what's forecast to be a steep rise in demand for electricity in the province."}]},{"kind":"cost","statement_date":"2025-05-08","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario / Ontario Power Generation"},"cost":{"low":null,"high":null,"point":7.7,"currency":"CAD","dollar_year":2024,"covers":"capital cost (unit 1 incl. shared infrastructure)"},"headline":"Unit 1: $7.7B including shared infrastructure","sources":[{"url":"https://www.cbc.ca/1.7529338","outlet":"CBC News","published_at":"2025-05-08","quote":"The estimated construction cost of the initial reactor is $7.7 billion, which includes $1.6 billion of infrastructure to be shared across the project."}]},{"kind":"status","statement_date":"2025-05-08","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario"},"new_status":"construction","headline":"Province approves construction of the first unit","sources":[{"url":"https://www.cbc.ca/1.7529338","outlet":"CBC News","published_at":"2025-05-08","quote":"Premier Doug Ford's government has given Ontario Power Generation the green light to start construction on Canada's first small modular reactor, a new nuclear energy technology to be built next door to the Darlington power plant."}]},{"kind":"completion_target","statement_date":"2025-05-08","date_precision":"day","speaker":{"type":"proponent","name":"Ontario Power Generation"},"target":{"date":"2030-01-01","precision":"year","event":"first_service"},"headline":"First unit on the grid in 2030","sources":[{"url":"https://www.cbc.ca/1.7529338","outlet":"CBC News","published_at":"2025-05-08","quote":"The timeline is to finish construction of the first reactor by the end of 2029, and connect it to the grid in 2030."},{"url":"https://www.theglobeandmail.com/business/article-ontarios-darlington-smr-project-to-cost-nearly-21-billion/","outlet":"The Globe and Mail","published_at":"2025-05-08","quote":"The first reactor was to have been completed in 2028, but OPG has pushed that back by one year."}]},{"kind":"milestone","statement_date":"2025-10-24","date_precision":"day","speaker":{"type":"government","name":"Canada Growth Fund and Building Ontario Fund"},"milestone":{"title":"Canada Growth Fund and Building Ontario Fund commit $3B in equity","achieved":true},"headline":"$3B in federal and provincial equity","sources":[{"url":"https://www.world-nuclear-news.org/articles/opg-secures-government-equity-financing-for-smr-project","outlet":"World Nuclear News","published_at":"2025-10-24","quote":"Canada Growth Fund Inc - a CAD15 billion arm's-length investment vehicle designed to attract private capital to build Canada's clean economy - has committed to invest up to CAD2 billion in the project, while Building Ontario Fund - a Crown agency with a mandate to catalyse investment in revenue-generating infrastructure projects across Ontario, backed by CAD8 billion in funding from the province - will invest CAD1 billion."}]},{"kind":"milestone","statement_date":"2026-11-10","date_precision":"day","speaker":{"type":"proponent","name":"Ontario Power Generation"},"withdraws_target":{"event":"first_service"},"milestone":{"title":"Unit 1 will miss the October 2030 target and the $7.7B estimate; new cost and schedule under assessment","achieved":false},"headline":"OPG: Unit 1 will miss its 2030 date and $7.7B budget","note":"OPG's Q3 2026 results (Nov 10) gave no new cost or date. It expects its assessment to be substantially complete by mid-2027.","sources":[{"url":"https://www.theglobeandmail.com/business/article-ottawa-darlington-small-modular-reactor-delay-rising-cost/","outlet":"The Globe and Mail","published_at":"2026-11-13","quote":"In quarterly financial statements released Tuesday, OPG said the first reactor unit would not be completed within its previously disclosed $7.7-billion budget."},{"url":"https://www.theglobeandmail.com/business/article-ottawa-darlington-small-modular-reactor-delay-rising-cost/","outlet":"The Globe and Mail","published_at":"2026-11-13","quote":"OPG had previously targeted an in-service date of October 2030. The delay could ultimately prove shorter than a year, depending on the outcome of an assessment that is expected to be completed by mid-2027."}]}]},{"slug":"darlington-refurbishment","name":"Darlington Nuclear Refurbishment","short_name":"Darlington refurbishment","sector":"energy","jurisdiction":"ON","status":"complete","owner":"Ontario Power Generation (Province of Ontario)","url":"https://www.overruns.ca/projects/darlington-refurbishment","first_announced":"2016-01-11","first_price":"$12.8B","first_price_date":"2016-01-11","first_price_speaker":"Ontario Power Generation","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":0,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"The mid-life overhaul of all four CANDU reactors at OPG's Darlington station in Clarington, Ontario, extending their life to at least 2055. One of the few megaprojects here delivered on its budget.","observations":[{"kind":"cost","statement_date":"2016-01-11","date_precision":"year","speaker":{"type":"proponent","name":"Ontario Power Generation"},"cost":{"low":null,"high":null,"point":12.8,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"Budget $12.8B","note":"OPG's budget at the start of execution. Earlier planning-stage figures are not yet sourced.","sources":[{"url":"https://www.ans.org/news/2026-02-03/article-7729/opg-completes-darlington-refurbishment-construction/","outlet":"Nuclear News (American Nuclear Society)","published_at":"2026-02-03","quote":"The 10-year megaproject, budgeted at C$12.8 billion (about $9.4 billion), was also 10 years in the planning."}]},{"kind":"completion_target","statement_date":"2016-01-11","date_precision":"year","speaker":{"type":"proponent","name":"Ontario Power Generation"},"target":{"date":"2026-01-01","precision":"year","event":"completion"},"headline":"Execution 2016 to 2026","sources":[{"url":"https://www.renewcanada.net/the-projects/darlington-nuclear-refurbishment/","outlet":"ReNew Canada","published_at":"2020-01-22","quote":"About The Project The Darlington Nuclear Refurbishment Project was managed in three distinct phases: Initiation Phase (2007Ð2009); Definition Phase (2010-2015); and Execution Phase (2016-2026)."}]},{"kind":"status","statement_date":"2016-10-15","date_precision":"month","speaker":{"type":"proponent","name":"Ontario Power Generation"},"new_status":"construction","headline":"Unit 2 taken offline, work begins","sources":[{"url":"https://www.ans.org/news/2026-02-03/article-7729/opg-completes-darlington-refurbishment-construction/","outlet":"Nuclear News (American Nuclear Society)","published_at":"2026-02-03","quote":"Work commenced in earnest in October 2016, when Unit 2 was taken off line (Nuclear News, December 2016, p. 45).Unit 2, the plant's first reactor to undergo refurbishment, returned to service in June 2020."}]},{"kind":"status","statement_date":"2026-02-02","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario"},"new_status":"complete","headline":"Construction complete, ahead of schedule and under budget","note":"The province said the project finished four months early and $150M under the $12.8B budget. A final cost figure has not been published as a single number.","sources":[{"url":"https://www.nucnet.org/news/darlington-nuclear-refurbishment-construction-completed-ahead-of-schedule-and-cad150-million-under-budget-2-2-2026","outlet":"NucNet","published_at":"2026-02-03","quote":"The construction phase of refurbishment of the fourth Candu reactor at the Darlington nuclear power station in Ontario, Canada, has been completed with the overall project four months ahead of schedule and CAD150m (€92m, $109m) under the CAD12.8bn budget."}]}]},{"slug":"deep-geological-repository","name":"Deep Geological Repository for used nuclear fuel","short_name":"Nuclear waste repository","sector":"energy","jurisdiction":"ON","status":"planning","owner":"Nuclear Waste Management Organization (funded by nuclear fuel owners: OPG, Hydro-Québec, NB Power, AECL)","url":"https://www.overruns.ca/projects/deep-geological-repository","first_announced":"2003-01-01","first_price":"$16.9B","first_price_date":"2003-01-01","first_price_speaker":"CTECH and Cogema Logistics, with Ontario Power Generation (for the nuclear fuel owners)","latest_estimate":"$26B","latest_estimate_date":"2021-10-05","latest_estimate_speaker":"Nuclear Waste Management Organization","cost_basis":"lifecycle","multiple_after_inflation":1.31,"multiple_as_announced":1.54,"delay_months":null,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"An underground repository near Ignace and Wabigoon Lake Ojibway Nation in northwestern Ontario for all of Canada's used nuclear fuel, run by the Nuclear Waste Management Organization and paid for by the nuclear utilities, mostly public (Ontario Power Generation, Hydro-Québec, NB Power, Atomic Energy of Canada).","observations":[{"kind":"cost","statement_date":"2003-01-01","date_precision":"year","speaker":{"type":"proponent","name":"CTECH and Cogema Logistics, with Ontario Power Generation (for the nuclear fuel owners)"},"cost":{"low":null,"high":null,"point":16.9,"currency":"CAD","dollar_year":2010,"covers":"lifecycle"},"headline":"$16.9B over the program's life","note":"NWMO's 2003 estimate, restated in 2010 dollars. Covers building, running and transport over about 150 years, for 3.6 million fuel bundles.","sources":[{"url":"https://www.nwmo.ca/-/media/Reports-MASTER/Funding-and-project-costs/1924_apm-rep-00440-0011_apmcostestimatesummaryreport_r0h.ashx?rev=d9234c4236684068a6047b70da07ffe7&sc_lang=en","outlet":"Nuclear Waste Management Organization, APM cost estimate summary report APM-REP-00440-0011","published_at":"2011-10-01","quote":"The previous cost estimate for an APM deep geological repository and used fuel transportation system for 3.6 million used CANDU fuel bundles was $16.9 billion (2010$), with a present value of $6.9 billion (2010$)."}]},{"kind":"cost","statement_date":"2011-10-01","date_precision":"month","speaker":{"type":"proponent","name":"Nuclear Waste Management Organization"},"cost":{"low":null,"high":null,"point":17.9,"currency":"CAD","dollar_year":2010,"covers":"lifecycle"},"headline":"$17.9B lifecycle (2010 dollars)","sources":[{"url":"https://www.nwmo.ca/-/media/Reports-MASTER/Funding-and-project-costs/1924_apm-rep-00440-0011_apmcostestimatesummaryreport_r0h.ashx?rev=d9234c4236684068a6047b70da07ffe7&sc_lang=en","outlet":"Nuclear Waste Management Organization, APM cost estimate summary report APM-REP-00440-0011","published_at":"2011-10-01","quote":"The 2011 reference APM cost estimate for 3.6 million used CANDU fuel bundles is $17.9 billion (2010$), with a present value of $7.0 billion (2010$)."}]},{"kind":"scope_change","statement_date":"2021-10-05","date_precision":"day","speaker":{"type":"proponent","name":"Nuclear Waste Management Organization"},"scope":{"description":"Reference inventory raised from 3.6 million to about 5.5 million used fuel bundles."},"headline":"Planned inventory raised to 5.5 million fuel bundles","sources":[{"url":"https://annualreport.nwmo.ca/2021/?p=110","outlet":"Nuclear Waste Management Organization, Annual Report 2021","published_at":"2021-10-05","quote":"For planning purposes, our 2021 cost estimate is based on an expected volume of about 5.5 million fuel bundles, the anticipated volume at the end of the planned operation of Canada’s existing nuclear reactors."}]},{"kind":"cost","statement_date":"2021-10-05","date_precision":"day","speaker":{"type":"proponent","name":"Nuclear Waste Management Organization"},"cost":{"low":null,"high":null,"point":26,"currency":"CAD","dollar_year":2020,"covers":"lifecycle"},"headline":"$26B over the program's life, for 5.5 million bundles","note":"In 2020 dollars. NWMO says most of the increase comes from the larger inventory.","sources":[{"url":"https://annualreport.nwmo.ca/2021/?p=110","outlet":"Nuclear Waste Management Organization, Annual Report 2021","published_at":"2021-10-05","quote":"Based on this expected volume, the total lifecycle cost of the project – from the beginning of site selection in 2010 to the completion of the project – is approximately $26 billion (in 2020 dollars)."}]},{"kind":"cost","statement_date":"2024-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Nuclear Waste Management Organization"},"cost":{"low":null,"high":null,"point":4.5,"currency":"CAD","dollar_year":2020,"covers":"capital cost"},"headline":"Construction: $4.5B (2020 dollars)","note":"Construction only, in 2020 dollars.","sources":[{"url":"https://implementationplan.nwmo.ca/2024_28/cost-and-funding/","outlet":"Nuclear Waste Management Organization, Implementing Adaptive Phased Management 2024-28","published_at":"2024-01-01","quote":"This figure covers the initial investment of $4.5 billion (in 2020 dollars) in construction costs over a 10-year period, as well as many decades of lifecycle activity, stretching well into the next century."}]},{"kind":"completion_target","statement_date":"2024-07-10","date_precision":"day","speaker":{"type":"proponent","name":"Nuclear Waste Management Organization"},"target":{"date":"2033-01-01","precision":"year","event":"construction_start"},"headline":"Construction from 2033; operating early 2040s","sources":[{"url":"https://www.cbc.ca/1.7259610","outlet":"CBC News","published_at":"2024-07-10","quote":"Whichever municipality ends up being chosen, the site won't be operational for some time; construction is expected to start in 2033, and the site would be up and running by the early 2040s."}]},{"kind":"milestone","statement_date":"2024-11-28","date_precision":"day","speaker":{"type":"proponent","name":"Nuclear Waste Management Organization"},"milestone":{"title":"Site selected","achieved":true},"headline":"Site chosen: Wabigoon Lake Ojibway Nation-Ignace area","sources":[{"url":"https://www.cbc.ca/1.7395660","outlet":"CBC News","published_at":"2024-11-28","quote":"Northwestern Ontario has been chosen for Canada's first deep geological repository, a multibillion-dollar project that aims to eventually store the country's nuclear waste."}]},{"kind":"completion_target","statement_date":"2025-05-21","date_precision":"day","speaker":{"type":"proponent","name":"Nuclear Waste Management Organization"},"target":{"date":"2045-01-01","precision":"year","event":"first_service"},"headline":"Operations start 2045","sources":[{"url":"https://www.enr.com/articles/60779-wsp-kiewit-hatch-to-build-canadas-32b-spent-fuel-repository","outlet":"Engineering News-Record","published_at":"2025-05-21","quote":"Design is set to complete by 2028, with construction to begin by 2033 after design and environmental impact reviews by Canadian and indigenous regulators, and operation startup set for 2045."}]}]},{"slug":"eglinton-crosstown-lrt","name":"Eglinton Crosstown LRT (Line 5 Eglinton)","short_name":"Eglinton Crosstown","sector":"transit","jurisdiction":"ON","status":"operational","owner":"Metrolinx (Province of Ontario)","url":"https://www.overruns.ca/projects/eglinton-crosstown-lrt","first_announced":"2007-03-01","first_price":"$2.2B","first_price_date":"2007-03-01","first_price_speaker":"Toronto Transit Commission and City of Toronto (Transit City plan)","latest_estimate":"$5.3B","latest_estimate_date":"2015-11-03","latest_estimate_speaker":"Government of Ontario (Transportation Minister Steven Del Duca)","cost_basis":"capital cost","multiple_after_inflation":2.12,"multiple_as_announced":2.41,"delay_months":110,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 19 km light rail line along Eglinton Avenue in Toronto, about 10 km of it underground, from Mount Dennis to Kennedy. Built by Metrolinx under a public-private partnership and run by the TTC as Line 5.","observations":[{"kind":"cost","statement_date":"2007-03-01","date_precision":"month","speaker":{"type":"proponent","name":"Toronto Transit Commission and City of Toronto (Transit City plan)"},"cost":{"low":null,"high":null,"point":2.2,"currency":"CAD","dollar_year":2007,"covers":"capital cost"},"headline":"Transit City plan: $2.2B","note":"First figure for the Eglinton line, then planned from Kingston Road to Pearson Airport. The Globe reports it was not fully developed and left out items such as vehicle storage.","sources":[{"url":"https://theglobeandmail.com/canada/article-eglinton-crosstown-lrt-railway-project-wrong-toronto","outlet":"The Globe and Mail","published_at":"2025-10-30","quote":"March, 2007 Transit City plans unveiled Mayor David Miller and the Toronto Transit Commission reveal their “Transit City” plan for new light-rail lines, including a partly tunnelled line along Eglinton Avenue, from Kingston Road in the east to Pearson Airport in the west, with an initial estimated cost of just $2.2-billion."}]},{"kind":"cost","statement_date":"2009-04-01","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario (Premier Dalton McGuinty)"},"cost":{"low":null,"high":null,"point":4.6,"currency":"CAD","dollar_year":2009,"covers":"capital cost"},"headline":"Province funds the line at $4.6B","note":"For a 31 km line from Kennedy to Pearson Airport.","sources":[{"url":"https://spacing.ca/toronto/2009/04/01/transit-city-to-get-major-funding-boost-from-province/","outlet":"Spacing Toronto (citing The Globe and Mail)","published_at":"2009-04-01","quote":"The Eglinton rapid transit line will be the most expensive among the projects, costing about $4.6-billion."},{"url":"https://www.cbc.ca/news/canada/toronto/eglinton-transit-city-line-may-survive-1.1067851","outlet":"CBC News","published_at":"2011-01-04","quote":"The $4.6-billion Eglinton Crosstown LRT line, as it is currently envisioned, stretches from the Scarborough Town Centre in the east to Pearson International Airport westward."}]},{"kind":"completion_target","statement_date":"2009-04-01","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario"},"target":{"date":"2016-01-01","precision":"year","event":"first_service"},"headline":"Completion expected in 2016","sources":[{"url":"https://theglobeandmail.com/canada/article-eglinton-crosstown-lrt-railway-project-wrong-toronto","outlet":"The Globe and Mail","published_at":"2025-10-30","quote":"The plan includes a 31-kilometre partly tunnelled Eglinton line running from Kennedy Road in the east all the way to Pearson International Airport in the west, with a price tag of $4.6-billion and an “expected completion date” of 2016."}]},{"kind":"scope_change","statement_date":"2010-03-25","date_precision":"month","speaker":{"type":"government","name":"Government of Ontario"},"scope":{"description":"Provincial funding cut in the 2010 budget shortened the line to 19 km, Mount Dennis area to Kennedy, dropping the section to Pearson Airport."},"headline":"Line cut to 19 km","sources":[{"url":"https://theglobeandmail.com/canada/article-eglinton-crosstown-lrt-railway-project-wrong-toronto","outlet":"The Globe and Mail","published_at":"2025-10-30","quote":"Later that year, the TTC and Metrolinx would agree on today’s shortened, 19-kilometre Eglinton line, pledging to have it done by 2020."}]},{"kind":"completion_target","statement_date":"2010-03-25","date_precision":"month","speaker":{"type":"proponent","name":"Metrolinx and Toronto Transit Commission"},"target":{"date":"2020-01-01","precision":"year","event":"first_service"},"headline":"Shortened line due by 2020","sources":[{"url":"https://theglobeandmail.com/canada/article-eglinton-crosstown-lrt-railway-project-wrong-toronto","outlet":"The Globe and Mail","published_at":"2025-10-30","quote":"The now 19-kilometre Eglinton line was to be completed by 2019-2020."},{"url":"https://www.cbc.ca/lite/story/9.7077697","outlet":"CBC News","published_at":"2026-02-08","quote":"Though the network was eliminated, the Eglinton project persisted with a ground-breaking ceremony held at Mount Dennis in 2011, with promises for a completed line by late 2020."}]},{"kind":"cost","statement_date":"2015-11-03","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario (Transportation Minister Steven Del Duca)"},"cost":{"low":null,"high":null,"point":5.3,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"Contract signed, $5.3B of it capital","note":"Capital share of the $9.1B, 30-year contract with Crosslinx Transit Solutions. The rest covers financing, maintenance and lifecycle.","sources":[{"url":"https://www.thestar.com/news/gta/transportation/2015/11/03/91b-crosstown-lrt-mega-contract-comes-in-under-estimates.html","outlet":"Toronto Star","published_at":"2015-11-03","quote":"Of the $9.1 billion, $5.3 billion is capital."},{"url":"https://www.cbc.ca/lite/story/1.5466847","outlet":"CBC News","published_at":"2020-02-18","quote":"In a statement released Tuesday, Metrolinx president and CEO Phil Verster attributed much of the delay to the group of private companies building the $5.3-billion project in partnership with the province, Crosslinx Transit Solutions (CTS)."}]},{"kind":"completion_target","statement_date":"2015-11-03","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario"},"target":{"date":"2021-01-01","precision":"year","event":"first_service"},"headline":"Opening slips to 2021","sources":[{"url":"https://www.theglobeandmail.com/news/toronto/ontario-government-shaves-2-billion-off-eglinton-crosstown-lrt-price-tag/article27085427/","outlet":"The Globe and Mail","published_at":"2015-11-03","quote":"It survived the anti-LRT mood of the last city council and is due to enter service in 2021, a year behind schedule."}]},{"kind":"cost","statement_date":"2018-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Metrolinx"},"cost":{"low":null,"high":null,"point":11.78,"currency":"CAD","dollar_year":2018,"covers":"total including financing and 30-year maintenance"},"headline":"Budget $11.78B with 30 years of upkeep","note":"Not comparable with the capital-only figures: includes financing and 30 years of maintenance.","sources":[{"url":"https://www.cbc.ca/lite/story/1.6675131","outlet":"CBC News","published_at":"2022-12-08","quote":"The budget for the project was $11.78 billion in 2018, which included the design, construction, financing and 30-year maintenance of the light rail transit (LRT) system."}]},{"kind":"completion_target","statement_date":"2021-12-01","date_precision":"month","speaker":{"type":"proponent","name":"Metrolinx"},"target":{"date":"2023-01-01","precision":"year","event":"first_service"},"headline":"Service pushed to 2023","note":"Set after a legal settlement with the builder. Metrolinx later stopped giving target dates until testing was done.","sources":[{"url":"https://www.thestar.com/news/gta/2022/12/08/no-credible-plan-for-completion-of-eglinton-lrt-says-metrolinx.html","outlet":"Toronto Star","published_at":"2022-12-08","quote":"In December 2021, Metrolinx said the transit line would be complete by September 2022 and ready for service in 2023"}]},{"kind":"cost","statement_date":"2022-12-08","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx (internal documents)"},"cost":{"low":null,"high":null,"point":12.81,"currency":"CAD","dollar_year":2022,"covers":"total including financing and 30-year maintenance"},"headline":"Approved budget reaches $12.81B","sources":[{"url":"https://www.cbc.ca/lite/story/1.6675131","outlet":"CBC News","published_at":"2022-12-08","quote":"They detail the status of the project and show the current approved budget to be $12.81 billion."}]},{"kind":"cost","statement_date":"2025-10-30","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"cost":{"low":null,"high":null,"point":13.08,"currency":"CAD","dollar_year":2025,"covers":"total including financing and 30-year maintenance"},"headline":"$13.08B including 30 years of maintenance","sources":[{"url":"https://theglobeandmail.com/canada/article-eglinton-crosstown-lrt-railway-project-wrong-toronto","outlet":"The Globe and Mail","published_at":"2025-10-30","quote":"The bill for this partially tunnelled, 19-kilometre light-rail line is currently pegged at $13.08-billion, including 30 years of maintenance – around $8-billion more than estimated back when construction began."},{"url":"https://www.cbc.ca/lite/story/9.7077697","outlet":"CBC News","published_at":"2026-02-08","quote":"As of last fall, the project had amassed a price tag of over $13 billion, according to a report from Metrolinx, an increase from the $11.78 billion projected in 2018."}]},{"kind":"status","statement_date":"2026-02-08","date_precision":"day","speaker":{"type":"proponent","name":"Toronto Transit Commission"},"new_status":"operational","headline":"Opens as TTC Line 5","note":"Opened about six years after the 2020 target, with reduced hours at first.","sources":[{"url":"https://www.cbc.ca/lite/story/9.7077697","outlet":"CBC News","published_at":"2026-02-08","quote":"People ride the Eglinton Crosstown LRT on its first day of service in Toronto on Feb. 8, 2026."}]}]},{"slug":"finch-west-lrt","name":"Finch West LRT (Line 6 Finch West)","short_name":"Finch West LRT","sector":"transit","jurisdiction":"ON","status":"operational","owner":"Metrolinx (Province of Ontario)","url":"https://www.overruns.ca/projects/finch-west-lrt","first_announced":"2015-09-10","first_price":"$1.2B","first_price_date":"2015-09-10","first_price_speaker":"Metrolinx and Infrastructure Ontario (procurement launch)","latest_estimate":"$1.2B","latest_estimate_date":"2017-06-26","latest_estimate_speaker":"Government of Ontario (Transportation Minister Steven Del Duca)","cost_basis":"capital cost","multiple_after_inflation":0.97,"multiple_as_announced":1,"delay_months":24,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"An 11 km light rail line along Finch Avenue West in Toronto from Finch West station to Humber College, built by Metrolinx with the Mosaic Transit Group and run by the TTC as Line 6.","observations":[{"kind":"cost","statement_date":"2015-09-10","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx and Infrastructure Ontario (procurement launch)"},"cost":{"low":null,"high":null,"point":1.2,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"Estimated at $1.2B at procurement","note":"Earliest figure found, from the launch of the build tender. It is the capital cost to build the line.","sources":[{"url":"https://www.railwaypro.com/wp/toronto-tender-launched-for-light-rail-project/","outlet":"Railway PRO","published_at":"2015-09-10","quote":"The cost is estimated at CA$1.2bn (EUR 820 million)."}]},{"kind":"cost","statement_date":"2017-06-26","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario (Transportation Minister Steven Del Duca)"},"cost":{"low":null,"high":null,"point":1.2,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"Province repeats $1.2B as Ottawa adds $333M","sources":[{"url":"https://www.rtands.com/?p=9769","outlet":"Railway Track & Structures","published_at":"2017-06-26","quote":"The Finch West LRT project is estimated to cost CA$1.2 billion (US$906 million) and will consist of 6.8 miles of light-rail line along Finch Ave."}]},{"kind":"cost","statement_date":"2018-05-07","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx and Infrastructure Ontario"},"cost":{"low":null,"high":null,"point":2.5,"currency":"CAD","dollar_year":2018,"covers":"total including construction contract and 30-year maintenance"},"headline":"Contract signed at $2.5B","note":"The contract is for design, build, finance and maintenance, so it is not comparable with the $1.2B capital figure.","sources":[{"url":"https://www.renewcanada.net/contract-awarded-for-finch-west-lrt-project/","outlet":"ReNew Canada","published_at":"2018-05-07","quote":"has signed a contract valued at $2.5 billion to design, build, finance, and maintain"},{"url":"https://www.progressiverailroading.com/passenger_rail/news/Sound-Transit-Metrolinx-open-new-light-rail-lines--75948","outlet":"Progressive Railroading, citing The Canadian Press","published_at":"2025-12-10","quote":"The line's total cost, including the construction contract to Mosaic Transit Group and a 30-year maintenance contract to Bombardier Transportation, was originally estimated at C$2.5 billion."}]},{"kind":"completion_target","statement_date":"2018-05-07","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx and Infrastructure Ontario"},"target":{"date":"2023-01-01","precision":"year","event":"first_service"},"headline":"Mosaic to deliver the LRT by 2023","sources":[{"url":"https://www.renewcanada.net/contract-awarded-for-finch-west-lrt-project/","outlet":"ReNew Canada","published_at":"2018-05-07","quote":"Mosaic’s successful proposal will deliver the LRT by 2023."}]},{"kind":"cost","statement_date":"2025-12-07","date_precision":"day","speaker":{"type":"other","name":"Report cited by CTV News and The Canadian Press"},"cost":{"low":null,"high":null,"point":3.7,"currency":"CAD","dollar_year":2025,"covers":"total including lifecycle, operating and maintenance"},"headline":"Total cost $3.7B including maintenance","note":"Includes lifecycle, operating and maintenance costs, so it is not comparable with the $1.2B construction figure or the $2.5B contract.","sources":[{"url":"https://www.ctvnews.ca/toronto/article/finch-west-lrt-officially-opens-with-free-rides-as-ttc-launches-first-new-transit-line-since-2002/","outlet":"CTV News","published_at":"2025-12-07","quote":"A report earlier this fall pegged the total cost of the line at $3.7 billion, including lifecycle, operating and maintenance expenses."},{"url":"https://www.progressiverailroading.com/passenger_rail/news/Sound-Transit-Metrolinx-open-new-light-rail-lines--75948","outlet":"Progressive Railroading, citing The Canadian Press","published_at":"2025-12-10","quote":"However, the final cost came in at C$3.7 billion, according to the report."}]},{"kind":"status","statement_date":"2025-12-07","date_precision":"day","speaker":{"type":"proponent","name":"Toronto Transit Commission"},"new_status":"operational","headline":"Opens as TTC Line 6","note":"Opened with free rides. The TTC says it runs under soft-opening conditions until spring 2026.","sources":[{"url":"https://www.ctvnews.ca/toronto/article/finch-west-lrt-officially-opens-with-free-rides-as-ttc-launches-first-new-transit-line-since-2002/","outlet":"CTV News","published_at":"2025-12-07","quote":"Finch West LRT opens with free rides today"},{"url":"https://www.ctvnews.ca/toronto/article/finch-west-lrt-officially-opens-with-free-rides-as-ttc-launches-first-new-transit-line-since-2002/","outlet":"CTV News","published_at":"2025-12-07","quote":"The TTC says Line 6 will run under “soft opening” conditions until spring 2026."}]}]},{"slug":"future-fighter-capability-project","name":"Future Fighter Capability Project (CF-18 replacement)","short_name":"F-35 fighters","sector":"defence","jurisdiction":"federal","status":"procurement","owner":"Government of Canada (National Defence; Public Services and Procurement Canada)","url":"https://www.overruns.ca/projects/future-fighter-capability-project","first_announced":"2010-07-16","first_price":"$9B","first_price_date":"2010-07-16","first_price_speaker":"Government of Canada (Defence Minister Peter MacKay)","latest_estimate":"$27.7B","latest_estimate_date":"2025-06-10","latest_estimate_speaker":"National Defence (estimate reported by the Auditor General)","cost_basis":"acquisition","multiple_after_inflation":2.23,"multiple_as_announced":3.08,"delay_months":144,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Replacing the RCAF's CF-18 Hornets. Announced in 2010 as a sole-source buy of 65 F-35s, reset in 2012, relaunched in 2017 as an open competition for 88 jets, and won by the F-35 in 2022. The full purchase has been under review since March 2025.","observations":[{"kind":"cost","statement_date":"2010-07-16","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Defence Minister Peter MacKay)"},"cost":{"low":null,"high":null,"point":9,"currency":"CAD","dollar_year":2010,"covers":"acquisition"},"headline":"$9B for 65 F-35s","note":"Purchase only. Operating and maintenance costs were not included.","sources":[{"url":"https://ainonline.com/aviation-news/defense/2010-07-18/canada-commits-jsf-future-deal-65","outlet":"Aviation International News","published_at":"2010-07-18","quote":"The $9 billion commitment covers 65 JSFs."},{"url":"https://www.cbc.ca/news/politics/f-35-jets-cost-to-soar-to-29b-watchdog-1.983367","outlet":"CBC News","published_at":"2011-03-10","quote":"It says it has committed $9-billion to buy the 65 planes and they will cost around $70 million each."}]},{"kind":"completion_target","statement_date":"2010-07-16","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2016-01-01","precision":"year","event":"first_delivery"},"headline":"First jet delivered in 2016","sources":[{"url":"https://ainonline.com/aviation-news/defense/2010-07-18/canada-commits-jsf-future-deal-65","outlet":"Aviation International News","published_at":"2010-07-18","quote":"The first is due for delivery in 2016 to begin replacement of the CF-18 Hornet fleet."}]},{"kind":"cost","statement_date":"2011-03-10","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer (Kevin Page)"},"cost":{"low":null,"high":null,"point":9.7,"currency":"CAD","dollar_year":2011,"covers":"acquisition"},"headline":"Budget officer: $9.7B to buy","sources":[{"url":"https://www.cbc.ca/news/politics/f-35-jets-cost-to-soar-to-29b-watchdog-1.983367","outlet":"CBC News","published_at":"2011-03-10","quote":"Page estimates the acquisition cost for the fleet at $9.7 billion and the ongoing sustainment cost for it at $19.6 billion."}]},{"kind":"cost","statement_date":"2011-03-10","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer (Kevin Page)"},"cost":{"low":null,"high":null,"point":29.3,"currency":"CAD","dollar_year":2011,"covers":"lifecycle"},"headline":"Budget officer: $29.3B over 30 years","sources":[{"url":"https://www.cbc.ca/news/politics/f-35-jets-cost-to-soar-to-29b-watchdog-1.983367","outlet":"CBC News","published_at":"2011-03-10","quote":"Parliamentary Budget Officer Kevin Page said in a report Thursday that his $29.3 billion estimate covers the purchase price and sustainment costs for the fleet over 30 years."}]},{"kind":"cost","statement_date":"2012-04-03","date_precision":"day","speaker":{"type":"watchdog","name":"Auditor General of Canada (Michael Ferguson)"},"cost":{"low":null,"high":null,"point":25,"currency":"CAD","dollar_year":2012,"covers":"lifecycle"},"headline":"Auditor general: Defence's own 20-year figure was $25B","sources":[{"url":"https://www.cbc.ca/news/politics/f-35-fighter-jet-cost-questions-date-back-to-2010-1.1203376","outlet":"CBC News","published_at":"2012-04-12","quote":"Ferguson says the department's own estimate puts personnel, operating and maintenance costs at $16 billion, for a total 20-year cost of $25 billion for the F-35s."}]},{"kind":"cost","statement_date":"2012-12-12","date_precision":"day","speaker":{"type":"government","name":"Department of National Defence"},"cost":{"low":null,"high":null,"point":44,"currency":"CAD","dollar_year":2012,"covers":"lifecycle"},"headline":"Defence: about $44B over 42 years","sources":[{"url":"https://amp.cbc.ca/lite/story/1.1203373","outlet":"CBC News","published_at":"2012-12-12","quote":"Wednesday, a Department of National Defence report assessed the new longer costs at about $44 billion."}]},{"kind":"cost","statement_date":"2012-12-12","date_precision":"day","speaker":{"type":"other","name":"KPMG (independent review commissioned by the government)"},"cost":{"low":null,"high":null,"point":45.8,"currency":"CAD","dollar_year":2012,"covers":"lifecycle"},"headline":"KPMG: $45.8B over 42 years","sources":[{"url":"https://amp.cbc.ca/lite/story/1.1203373","outlet":"CBC News","published_at":"2012-12-12","quote":"It also tacked on another billion dollars in costs to account for aircraft losses over the years, setting the final cost for 65 aircraft, maintenance, operating costs and sustainment at $45.8 billon."}]},{"kind":"status","statement_date":"2012-12-12","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"new_status":"paused","headline":"Plan 'reset': no decision until a full options review","sources":[{"url":"https://amp.cbc.ca/lite/story/1.1203373","outlet":"CBC News","published_at":"2012-12-12","quote":"The federal government says it won't make a final decision on which fighter jet to buy until it completes every step of the complex process it laid out last spring following a blistering report from the auditor general about the escalating costs attached to the F-35."}]},{"kind":"scope_change","statement_date":"2017-12-12","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"scope":{"description":"Fleet raised from 65 to 88 jets and bought through an open competition, with 18 used Australian F-18s as an interim fleet."},"headline":"Open competition for 88 jets","sources":[{"url":"https://globalnews.ca/news/3912118/fighter-jet-competition-boeing-trade-challenge/","outlet":"Global News","published_at":"2017-12-12","quote":"The Canadian government is launching a competition to buy a new fleet of 88 fighter jets and officials confirmed Tuesday they will also be buying an interim fleet of 18 jets from Australia rather than Boeing."}]},{"kind":"cost","statement_date":"2017-12-12","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (officials)"},"cost":{"low":15,"high":19,"point":null,"currency":"CAD","dollar_year":2017,"covers":"acquisition"},"headline":"$15-19B set aside for 88 jets","sources":[{"url":"https://globalnews.ca/news/3912118/fighter-jet-competition-boeing-trade-challenge/","outlet":"Global News","published_at":"2017-12-12","quote":"Officials said Tuesday the cost is being estimated at roughly half a billion dollars for the interim replacement, while roughly $15 billion to $19 billion will be set aside for the full competition."}]},{"kind":"completion_target","statement_date":"2017-12-12","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2025-01-01","precision":"year","event":"first_delivery"},"headline":"First new jet by 2025","sources":[{"url":"https://globalnews.ca/news/3912118/fighter-jet-competition-boeing-trade-challenge/","outlet":"Global News","published_at":"2017-12-12","quote":"A contract award is expected in 2022 and the government says it expects to have the first aircraft resulting from the award of the contract in its possession by 2025."}]},{"kind":"milestone","statement_date":"2022-03-28","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"milestone":{"title":"F-35 chosen as preferred bidder; negotiations begin","achieved":true},"headline":"F-35 wins the competition","sources":[{"url":"https://www.cbc.ca/news/politics/f-35-negotiations-1.6399978","outlet":"CBC News","published_at":"2022-03-28","quote":"The Canadian government has chosen the F-35 as its preferred replacement for the air force's four-decade-old CF-18 fighters and will open negotiations with the stealth jet's manufacturer, Lockheed Martin."}]},{"kind":"completion_target","statement_date":"2022-12-21","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2032-01-01","precision":"year","event":"final_delivery"},"headline":"Replacement complete by 2032","sources":[{"url":"https://www.cbc.ca/news/politics/defence-department-approval-f35-1.6693455","outlet":"The Canadian Press, via CBC News","published_at":"2022-12-21","quote":"While the federal government has said it plans to buy 88 new fighter jets to replace its aging CF-18s between 2026 and 2032, the sources said Canada will be purchasing F-35s in blocks over the next few years."}]},{"kind":"cost","statement_date":"2023-01-09","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Defence Minister Anita Anand)"},"cost":{"low":null,"high":null,"point":19,"currency":"CAD","dollar_year":2023,"covers":"acquisition"},"headline":"Contract signed; budget $19B","sources":[{"url":"https://www.cbc.ca/1.6707769","outlet":"CBC News","published_at":"2023-01-09","quote":"The project's budget of $19 billion remains the same as originally forecast by the Liberal government when it signalled the purchase last year."}]},{"kind":"completion_target","statement_date":"2023-01-09","date_precision":"day","speaker":{"type":"government","name":"National Defence (senior officials, technical briefing)"},"target":{"date":"2026-01-01","precision":"year","event":"first_delivery"},"headline":"First delivery slips to 2026","sources":[{"url":"https://www.cbc.ca/1.6707769","outlet":"CBC News","published_at":"2023-01-09","quote":"won't see its first delivery until 2026 and the first F-35 squadrons will not be operational until 2029, senior defence officials said during a technical briefing before the minister's announcement."}]},{"kind":"cost","statement_date":"2023-11-02","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer (Yves Giroux)"},"cost":{"low":null,"high":null,"point":19.8,"currency":"CAD","dollar_year":2023,"covers":"acquisition"},"headline":"Budget officer: $19.8B acquisition phase","sources":[{"url":"https://www.cbc.ca/news/politics/f35-pbo-74-billion-1.7016178","outlet":"CBC News","published_at":"2023-11-02","quote":"\"The total cost of the acquisition phase, including not just the purchase cost of the fighter jets but all acquisition phase activities, is projected to be $19.8 billion, according to our analysis,\""}]},{"kind":"cost","statement_date":"2023-11-02","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer (Yves Giroux)"},"cost":{"low":null,"high":73.9,"point":null,"currency":"CAD","dollar_year":2023,"covers":"lifecycle"},"headline":"Budget officer: up to $73.9B over the fleet's life","sources":[{"url":"https://www.cbc.ca/news/politics/f35-pbo-74-billion-1.7016178","outlet":"CBC News","published_at":"2023-11-02","quote":"Owning and operating a fleet of F-35 fighter jets over the next four and a half decades is expected to cost Canadian taxpayers as much as $73.9 billion, the Parliamentary Budget Officer said Thursday in a new report."}]},{"kind":"milestone","statement_date":"2025-03-14","date_precision":"day","speaker":{"type":"government","name":"Defence Minister Bill Blair"},"milestone":{"title":"Government reviews the F-35 purchase and talks to rival makers","achieved":true},"headline":"Ottawa reopens the F-35 decision","sources":[{"url":"https://www.cbc.ca/lite/story/1.7484477","outlet":"CBC News","published_at":"2025-03-14","quote":"Canada is actively looking at potential alternatives to the U.S.-built F-35 stealth fighter and will hold conversations with rival aircraft makers, Defence Minister Bill Blair said late Friday, just hours after being reappointed to the post as part of Prime Minister Mark Carney's new cabinet."}]},{"kind":"cost","statement_date":"2025-06-10","date_precision":"day","speaker":{"type":"government","name":"National Defence (estimate reported by the Auditor General)"},"cost":{"low":null,"high":null,"point":27.7,"currency":"CAD","dollar_year":2024,"covers":"acquisition"},"headline":"National Defence's own estimate: $27.7B","note":"Revealed in the Auditor General's audit. Bases, weapons and other items add at least $5.5B more.","sources":[{"url":"https://www.cbc.ca/news/politics/f-35-fighter0-jets-arrive-can-contractor-1.7556943","outlet":"CBC News","published_at":"2025-06-10","quote":"According to the report, the cost of the F-35 program has risen to $27.7 billion — up from the $19 billion National Defence announced in 2023."},{"url":"https://nationalnewswatch.com/2025/06/10/auditor-general-finds-f-35-costs-soar-amid-project-delays-pilot-shortages","outlet":"The Canadian Press, via National Newswatch","published_at":"2025-06-10","quote":"Just two years later, the number has climbed to $27.7 billion."},{"url":"https://www.canada.ca/en/auditor-general/media-room/osh-20251007-e-44734.html","outlet":"Office of the Auditor General of Canada","published_at":"2025-10-07","quote":"The audit found that this figure was based on outdated information and that by 2024, the projected costs had increased to $27.7 billion—almost 50% more than the original estimate."}]},{"kind":"completion_target","statement_date":"2025-06-10","date_precision":"day","speaker":{"type":"watchdog","name":"Auditor General of Canada"},"target":{"date":"2028-01-01","precision":"year","event":"first_delivery"},"headline":"First jets in Canada in 2028","note":"The first jets go to Arizona for pilot training in 2026.","sources":[{"url":"https://www.canada.ca/en/auditor-general/media-room/osh-20251007-e-44734.html","outlet":"Office of the Auditor General of Canada","published_at":"2025-10-07","quote":"Based on the current plan, Canada’s first CF‑35s will be sent to Luke Air Force Base in Arizona in 2026 to support pilot training, while the first aircraft will arrive in Canada in 2028."}]},{"kind":"milestone","statement_date":"2026-04-27","date_precision":"day","speaker":{"type":"government","name":"Defence Minister David McGuinty"},"milestone":{"title":"Review of the F-35 purchase still under way, no timeline","achieved":false},"headline":"Review continues with no end date","sources":[{"url":"https://www.aerotime.aero/articles/canada-f-35-review-no-end-date","outlet":"AeroTime","published_at":"2026-04-28","quote":"Canada’s defense minister has confirmed that Ottawa’s review of its plan to purchase 88 Lockheed Martin F-35 fighter jets is still ongoing, with no timeline given for a final decision."}]},{"kind":"milestone","statement_date":"2026-10-22","date_precision":"day","speaker":{"type":"government","name":"Royal Canadian Air Force"},"milestone":{"title":"First two F-35As arrive at Luke Air Force Base, Arizona, for pilot training","achieved":true},"headline":"First two F-35s delivered in Arizona, full order still under review","note":"The jets are at Luke Air Force Base for training, not in Canada. The review of the full 88-aircraft order continues.","sources":[{"url":"https://theaviationist.com/2026/10/26/canada-receives-first-two-cf-35a-fighters/","outlet":"The Aviationist","published_at":"2026-10-26","quote":"The aircraft arrived at Luke Air Force Base, Arizona, on Oct. 22, 2026, where they will support the initial phase of the country's F-35 program."}]}]},{"slug":"gatineau-tramway","name":"Gatineau tramway (western Gatineau rapid transit)","short_name":"Gatineau tramway","sector":"transit","jurisdiction":"QC","status":"planning","owner":"Société de transport de l'Outaouais (Government of Quebec and Government of Canada funding)","url":"https://www.overruns.ca/projects/gatineau-tramway","first_announced":"2018-06-01","first_price":"$2.1B","first_price_date":"2018-06-01","first_price_speaker":"City of Gatineau and STO","latest_estimate":"up to $4.4B","latest_estimate_date":"2023-09-07","latest_estimate_speaker":"Société de transport de l'Outaouais","cost_basis":"capital cost (whole western network)","multiple_after_inflation":1.78,"multiple_as_announced":2.1,"delay_months":72,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A planned tram line linking Gatineau's Aylmer and Plateau districts to downtown Gatineau and Ottawa, run by the Société de transport de l'Outaouais.","observations":[{"kind":"cost","statement_date":"2018-06-01","date_precision":"year","speaker":{"type":"government","name":"City of Gatineau and STO"},"cost":{"low":null,"high":null,"point":2.1,"currency":"CAD","dollar_year":2018,"covers":"capital cost (whole western network)"},"headline":"First plan: $2.1B","note":"The STO called the 2018 estimate very preliminary.","sources":[{"url":"https://www.cbc.ca/news/canada/ottawa/sto-tram-portage-bridge-lyon-station-1.5571719","outlet":"CBC News","published_at":"2020-05-15","quote":"Back in 2018, Gatineau officials unveiled an ambitious vision for a 26-kilometre, $2.1-billion light rail line that would bring residents from the growing Aylmer and Plateau areas to downtown by 2028, as well as connect with Ottawa's LRT."}]},{"kind":"completion_target","statement_date":"2018-06-01","date_precision":"year","speaker":{"type":"government","name":"City of Gatineau and STO"},"target":{"date":"2028-01-01","precision":"year","event":"first_service"},"headline":"Service by 2028","sources":[{"url":"https://www.cbc.ca/news/canada/ottawa/sto-tram-portage-bridge-lyon-station-1.5571719","outlet":"CBC News","published_at":"2020-05-15","quote":"Back in 2018, Gatineau officials unveiled an ambitious vision for a 26-kilometre, $2.1-billion light rail line that would bring residents from the growing Aylmer and Plateau areas to downtown by 2028, as well as connect with Ottawa's LRT."}]},{"kind":"completion_target","statement_date":"2023-03-29","date_precision":"day","speaker":{"type":"proponent","name":"Société de transport de l'Outaouais"},"target":{"date":"2032-01-01","precision":"year","event":"first_service"},"headline":"Now 2032","sources":[{"url":"https://ottawa.ctvnews.ca/federal-and-quebec-governments-reach-agreement-in-principle-to-fund-gatineau-tram-project-mayor-1.6334439","outlet":"CTV News Ottawa","published_at":"2023-03-29","quote":"The project is expected to be complete by 2032."}]},{"kind":"status","statement_date":"2023-03-29","date_precision":"day","speaker":{"type":"proponent","name":"Société de transport de l'Outaouais"},"new_status":"planning","headline":"In planning","sources":[{"url":"https://ottawa.ctvnews.ca/federal-and-quebec-governments-reach-agreement-in-principle-to-fund-gatineau-tram-project-mayor-1.6334439","outlet":"CTV News Ottawa","published_at":"2023-03-29","quote":"The multi-billion dollar tram project is currently in its planning phase, according to a timeline provided by the STO, which includes securing funding and conducting studies."}]},{"kind":"cost","statement_date":"2023-09-07","date_precision":"day","speaker":{"type":"proponent","name":"Société de transport de l'Outaouais"},"cost":{"low":null,"high":4.4,"point":null,"currency":"CAD","dollar_year":2023,"covers":"capital cost (whole western network)"},"headline":"Up to $4.4B","sources":[{"url":"https://www.noovo.info/nouvelle/le-tramway-se-voudrait-toujours-la-meilleure-option-pour-gatineau.html","outlet":"Noovo Info","published_at":"2023-09-07","quote":"La nouvelle date cible est fixée à 2034 et le coût pourrait atteindre jusqu'à 4,4 milliards $."}]},{"kind":"completion_target","statement_date":"2023-09-07","date_precision":"day","speaker":{"type":"proponent","name":"Société de transport de l'Outaouais"},"target":{"date":"2034-01-01","precision":"year","event":"first_service"},"headline":"Now 2034","sources":[{"url":"https://www.noovo.info/nouvelle/le-tramway-se-voudrait-toujours-la-meilleure-option-pour-gatineau.html","outlet":"Noovo Info","published_at":"2023-09-07","quote":"La nouvelle date cible est fixée à 2034 et le coût pourrait atteindre jusqu'à 4,4 milliards $."}]},{"kind":"cost","statement_date":"2026-06-18","date_precision":"day","speaker":{"type":"government","name":"Mobilité Infra Québec"},"cost":{"low":null,"high":null,"point":8,"currency":"CAD","dollar_year":2026,"covers":"capital cost (about 24 km route, preliminary)"},"headline":"Quebec agency: about $8B for a 24 km line","note":"Preliminary figure from Mobilité Infra Québec, which took over the project from the STO in February 2026. It covers a 24 km route; the 2018 and 2023 figures covered a 26 km western network, so the scopes are not identical. Final recommendations are due 30 November 2026.","sources":[{"url":"https://www.quebec.ca/nouvelles/actualites/details/mise-au-point-sur-lavancement-du-projet-tramgo-71283","outlet":"Gouvernement du Québec (Mobilité Infra Québec)","published_at":"2026-06-18","quote":"Sur cette base préliminaire, un tracé d'environ 24 km représenterait un investissement de l'ordre de 8 milliards de dollars."}]}]},{"slug":"george-massey-crossing","name":"George Massey Crossing (Massey Tunnel replacement)","short_name":"Massey Tunnel replacement","sector":"road_bridge","jurisdiction":"BC","status":"procurement","owner":"Province of British Columbia, with federal funding","url":"https://www.overruns.ca/projects/george-massey-crossing","first_announced":"2017-07-18","first_price":"$3.5B","first_price_date":"2017-07-18","first_price_speaker":"Province of British Columbia","latest_estimate":"$8.5B","latest_estimate_date":"2026-07-06","latest_estimate_speaker":"Province of British Columbia (Transportation Minister Mike Farnworth)","cost_basis":"capital cost","multiple_after_inflation":1.88,"multiple_as_announced":2.43,"delay_months":9,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A replacement for the 1959 George Massey Tunnel under the Fraser River between Richmond and Delta. First planned as a 10-lane bridge, cancelled in 2017, and replaced by an eight-lane immersed tunnel.","observations":[{"kind":"cost","statement_date":"2017-07-18","date_precision":"year","speaker":{"type":"government","name":"Province of British Columbia"},"cost":{"low":null,"high":null,"point":3.5,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"10-lane bridge: $3.5B","note":"The figure for the BC Liberal government's bridge, approved in 2012 and cancelled in 2017. Its own first cost figure is not yet sourced.","sources":[{"url":"https://globalnews.ca/news/9112754/massey-crossing-replacement-delay","outlet":"Global News","published_at":"2022-09-07","quote":"The government had secured environmental approvals and already spent about $100 million on preparatory work for the $3.5-billion project when the NDP came to power in 2017 and cancelled it."}]},{"kind":"scope_change","statement_date":"2017-09-01","date_precision":"year","speaker":{"type":"government","name":"Province of British Columbia"},"scope":{"description":"The 10-lane bridge was cancelled; in 2020 the province chose an eight-lane immersed tunnel instead."},"headline":"Bridge cancelled, tunnel chosen","sources":[{"url":"https://globalnews.ca/news/9112754/massey-crossing-replacement-delay","outlet":"Global News","published_at":"2022-09-07","quote":"The government had secured environmental approvals and already spent about $100 million on preparatory work for the $3.5-billion project when the NDP came to power in 2017 and cancelled it."}]},{"kind":"cost","statement_date":"2022-03-18","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"cost":{"low":null,"high":null,"point":4.15,"currency":"CAD","dollar_year":2022,"covers":"capital cost"},"headline":"Tunnel: $4.15B","sources":[{"url":"https://www.cbc.ca/1.6389938","outlet":"CBC News","published_at":"2022-03-18","quote":"The B.C. government says it's chosen a main contractor for part of the major $4.15-billion project to replace the 62-year-old George Massey Tunnel and build an interchange."}]},{"kind":"completion_target","statement_date":"2022-03-18","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"target":{"date":"2030-01-01","precision":"year","event":"first_service"},"headline":"Tunnel to open in 2030","sources":[{"url":"https://www.cbc.ca/1.6389938","outlet":"CBC News","published_at":"2022-03-18","quote":"The new tunnel is expected to open to traffic in 2030, the NDP government said."}]},{"kind":"status","statement_date":"2022-03-18","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"new_status":"procurement","headline":"First contractor chosen","note":"As of July 2026 main construction was projected to start in 2027.","sources":[{"url":"https://www.cbc.ca/1.6389938","outlet":"CBC News","published_at":"2022-03-18","quote":"The B.C. government says it's chosen a main contractor for part of the major $4.15-billion project to replace the 62-year-old George Massey Tunnel and build an interchange."}]},{"kind":"cost","statement_date":"2026-07-06","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia (Transportation Minister Mike Farnworth)"},"cost":{"low":null,"high":null,"point":8.5,"currency":"CAD","dollar_year":2026,"covers":"capital cost"},"headline":"Budget more than doubles to $8.5B","sources":[{"url":"https://globalnews.ca/news/11955891/cost-work-replace-george-massey-tunnel-increases-billions/","outlet":"Global News","published_at":"2026-07-06","quote":"The budget for the project to replace the George Massey Tunnel has more than doubled to $8.5 billion."}]},{"kind":"completion_target","statement_date":"2026-07-06","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"target":{"date":"2031-09-01","precision":"month","event":"first_service"},"headline":"Completion now September 2031","sources":[{"url":"https://globalnews.ca/news/11955891/cost-work-replace-george-massey-tunnel-increases-billions/","outlet":"Global News","published_at":"2026-07-06","quote":"The completion date for the project has also been pushed back from December 2030 to September 2031."}]}]},{"slug":"gordie-howe-bridge","name":"Gordie Howe International Bridge","short_name":"Gordie Howe Bridge","sector":"road_bridge","jurisdiction":"federal","status":"operational","owner":"Windsor-Detroit Bridge Authority (federal Crown corporation)","url":"https://www.overruns.ca/projects/gordie-howe-bridge","first_announced":"2018-09-27","first_price":"$5.7B","first_price_date":"2018-09-27","first_price_speaker":"Windsor-Detroit Bridge Authority","latest_estimate":"$6.4B","latest_estimate_date":"2024-01-04","latest_estimate_speaker":"Windsor-Detroit Bridge Authority","cost_basis":"design-build contract plus operations and maintenance","multiple_after_inflation":0.93,"multiple_as_announced":1.12,"delay_months":19,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A six-lane cable-stayed bridge and two ports of entry linking Windsor, Ontario and Detroit, Michigan, delivered by the Windsor-Detroit Bridge Authority. Canada is paying the full upfront cost and expects to recover it through tolls.","observations":[{"kind":"cost","statement_date":"2018-09-27","date_precision":"day","speaker":{"type":"proponent","name":"Windsor-Detroit Bridge Authority"},"cost":{"low":null,"high":null,"point":5.7,"currency":"CAD","dollar_year":2018,"covers":"design-build contract plus operations and maintenance"},"headline":"Fixed-price contract at $5.7B","note":"Set at financial close. Includes the design-build phase and the operation, maintenance and rehabilitation phase, so it is the first figure that is comparable with later totals.","sources":[{"url":"https://gordiehoweinternationalbridge.com/financial-close-reached-on-gordie-howe-international-bridge-project/","outlet":"Gordie Howe International Bridge (WDBA)","published_at":"2018-09-27","quote":"The fixed-priced contract is valued at $5.7 billion (nominal value), which includes the design-build (DB) phase and the operation, maintenance, rehabilitation (OMR) phase."}]},{"kind":"completion_target","statement_date":"2018-09-27","date_precision":"day","speaker":{"type":"proponent","name":"Windsor-Detroit Bridge Authority"},"target":{"date":"2024-12-31","precision":"day","event":"first_service"},"headline":"Bridge in service by end of 2024","sources":[{"url":"https://gordiehoweinternationalbridge.com/financial-close-reached-on-gordie-howe-international-bridge-project/","outlet":"Gordie Howe International Bridge (WDBA)","published_at":"2018-09-27","quote":"Bridging North America has presented a 74-month construction schedule to complete the four components of the project with the bridge scheduled to be in service by the end of 2024."}]},{"kind":"cost","statement_date":"2024-01-04","date_precision":"day","speaker":{"type":"proponent","name":"Windsor-Detroit Bridge Authority"},"cost":{"low":null,"high":null,"point":6.4,"currency":"CAD","dollar_year":2024,"covers":"design-build contract plus operations and maintenance"},"headline":"Now $6.4B, all paid by Canada","note":"The increase is tied to a 10-month delay after the pandemic.","sources":[{"url":"https://www.cbc.ca/1.7074156","outlet":"CBC News","published_at":"2024-01-04","quote":"The new targeted opening date means the international border crossing will now cost $6.4 billion Cdn, up from the original $5.7-billion cost estimate"}]},{"kind":"completion_target","statement_date":"2024-01-04","date_precision":"day","speaker":{"type":"proponent","name":"Windsor-Detroit Bridge Authority"},"target":{"date":"2025-09-01","precision":"month","event":"first_service"},"headline":"Opening moved to September 2025","sources":[{"url":"https://www.cbsnews.com/amp/detroit/news/gordie-howe-international-bridge-wont-open-until-fall-2025","outlet":"CBS News Detroit","published_at":"2024-01-04","quote":"The target now is September 2025, though the bridge deck should be finished this year."}]},{"kind":"completion_target","statement_date":"2025-10-16","date_precision":"day","speaker":{"type":"proponent","name":"Windsor-Detroit Bridge Authority"},"target":{"date":"2026-01-01","precision":"month","event":"first_service"},"headline":"Opening as soon as early 2026","sources":[{"url":"https://www.blogto.com/city/2025/10/gordie-howe-international-bridge-2026/","outlet":"blogTO","published_at":"2025-10-16","quote":"\"The project team is progressing well toward construction completion this year with opening of the Gordie Howe International Bridge as soon as early 2026.\""}]},{"kind":"status","statement_date":"2026-07-27","date_precision":"day","speaker":{"type":"proponent","name":"Windsor-Detroit Bridge Authority"},"new_status":"operational","headline":"Opened to traffic July 27, 2026","note":"Opening came about 19 months after the original end-of-2024 target.","sources":[{"url":"https://www.bnnbloomberg.ca/business/2026/07/27/gordie-howe-bridge-officially-open-after-months-of-cross-border-controversy/","outlet":"BNN Bloomberg (The Canadian Press)","published_at":"2026-07-27","quote":"And so, I think that makes today all the more amazing that it has actually opened today, and a lot of people are very happy.\""},{"url":"https://sarnianewstoday.ca/windsor/news/2026/07/27/gordie-howe-bridge-opens-to-traffic","outlet":"Sarnia News Today","published_at":"2026-07-27","quote":"Construction began in 2018 with the opening originally planned for 2024."}]}]},{"slug":"grays-bay-road-port","name":"Grays Bay Road and Port","short_name":"Grays Bay road and port","sector":"road_bridge","jurisdiction":"NU","status":"planning","owner":"West Kitikmeot Resources Corp. (Kitikmeot Inuit Association); federal funding","url":"https://www.overruns.ca/projects/grays-bay-road-port","first_announced":"2016-01-01","first_price":"$550M","first_price_date":"2016-01-01","first_price_speaker":"Kitikmeot Inuit Association and Government of Nunavut","latest_estimate":"$1B","latest_estimate_date":"2024-10-15","latest_estimate_speaker":"West Kitikmeot Resources Corp. (Brendan Bell, CEO)","cost_basis":"capital cost","multiple_after_inflation":1.45,"multiple_as_announced":1.82,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A proposed ~230 km all-season road from the end of the Tibbitt-Contwoyto winter road to a deep-water port at Grays Bay on Nunavut's Coronation Gulf. The proponent is West Kitikmeot Resources Corp. (owned by the Kitikmeot Inuit Association); Ottawa funds pre-construction.","observations":[{"kind":"cost","statement_date":"2016-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Kitikmeot Inuit Association and Government of Nunavut"},"cost":{"low":null,"high":null,"point":0.55,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"$550M","note":"Reported in 2024; the 2016 source was not found.","sources":[{"url":"https://nunatsiaq.com/stories/article/grays-bay-road-and-port-could-be-open-by-2035-proponent/","outlet":"Nunatsiaq News","published_at":"2024-10-15","quote":"Grays Bay was first proposed by the Kitikmeot Inuit Association and the Government of Nunavut in 2016 as a $550-million “nation-building”"}]},{"kind":"cost","statement_date":"2018-04-16","date_precision":"day","speaker":{"type":"government","name":"Government of Nunavut"},"cost":{"low":null,"high":null,"point":0.527,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"$527M (January 2018 economic assessment)","note":"The territorial minister gave $435M in the same story.","sources":[{"url":"https://www.cbc.ca/news/canada/north/grays-bay-project-funding-denied-1.4620802","outlet":"CBC News","published_at":"2018-04-16","quote":"The Nunavut government has pulled its resources out of the Grays Bay Road and Port Project, after its request for federal funding to cover three-quarters of the estimated $527-million price tag was denied by Ottawa last week."}]},{"kind":"status","statement_date":"2018-04-16","date_precision":"day","speaker":{"type":"government","name":"Government of Nunavut"},"new_status":"paused","headline":"Federal funding denied; Nunavut pulls out","sources":[{"url":"https://www.cbc.ca/news/canada/north/grays-bay-project-funding-denied-1.4620802","outlet":"CBC News","published_at":"2018-04-16","quote":"The Nunavut government has pulled its resources out of the Grays Bay Road and Port Project, after its request for federal funding to cover three-quarters of the estimated $527-million price tag was denied by Ottawa last week."}]},{"kind":"status","statement_date":"2019-04-09","date_precision":"day","speaker":{"type":"proponent","name":"Kitikmeot Inuit Association"},"new_status":"planning","headline":"Project restarts at $550M","sources":[{"url":"https://nunatsiaq.com/stories/article/grays-bay-road-and-port-gets-on-the-go-again/","outlet":"Nunatsiaq News","published_at":"2019-04-09","quote":"The $550-million Grays Bay project would involve the construction of a 227-kilometre all-weather road running from the site of the defunct Jericho mine, which is located at the northern end of the Tibbit-Contwoyto winter road, to a deep-sea port at Grays Bay on Coronation Gulf."}]},{"kind":"cost","statement_date":"2024-10-15","date_precision":"day","speaker":{"type":"proponent","name":"West Kitikmeot Resources Corp. (Brendan Bell, CEO)"},"cost":{"low":null,"high":null,"point":1,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"'Close to $1 billion'","sources":[{"url":"https://nunatsiaq.com/stories/article/grays-bay-road-and-port-could-be-open-by-2035-proponent/","outlet":"Nunatsiaq News","published_at":"2024-10-15","quote":"Since 2016, the estimated price tag for the project has nearly doubled to close to $1 billion due to inflation, Bell said."}]},{"kind":"completion_target","statement_date":"2024-10-15","date_precision":"day","speaker":{"type":"proponent","name":"West Kitikmeot Resources Corp. (Brendan Bell, CEO)"},"target":{"date":"2035-01-01","precision":"year","event":"completion"},"headline":"Could be operational by 2035","sources":[{"url":"https://nunatsiaq.com/stories/article/grays-bay-road-and-port-could-be-open-by-2035-proponent/","outlet":"Nunatsiaq News","published_at":"2024-10-15","quote":"The proposed Grays Bay 230-kilometre all-season road and deepsea port that would link western Nunavut to the rest of Canada might be operational by 2035, says Brendan Bell, CEO of West Kitikmeot Resources Corp."}]},{"kind":"milestone","statement_date":"2026-05-20","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"milestone":{"title":"Up to $50M federal pre-construction funding","achieved":true},"headline":"Up to $50M for pre-construction","sources":[{"url":"https://nunatsiaq.com/stories/article/feds-give-50m-for-grays-bay-preconstruction/","outlet":"Nunatsiaq News","published_at":"2026-05-20","quote":"Preconstruction work inched another step closer for the Grays Bay Road and Port project after the federal government announced up to $50 million in funding."}]}]},{"slug":"hamilton-lrt","name":"Hamilton LRT (B-Line)","short_name":"Hamilton LRT","sector":"transit","jurisdiction":"ON","status":"procurement","owner":"Metrolinx (Province of Ontario), with federal funding","url":"https://www.overruns.ca/projects/hamilton-lrt","first_announced":"2015-05-26","first_price":"$1B","first_price_date":"2015-05-26","first_price_speaker":"Province of Ontario (Premier Kathleen Wynne)","latest_estimate":"$3.4B","latest_estimate_date":"2021-05-11","latest_estimate_speaker":"Governments of Canada and Ontario","cost_basis":"capital cost","multiple_after_inflation":3.04,"multiple_as_announced":3.4,"delay_months":36,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 14 km light rail line across Hamilton from McMaster University to the east end. Funded in 2015, cancelled by the province in 2019, and revived in 2021 at more than three times the original commitment.","observations":[{"kind":"cost","statement_date":"2015-05-26","date_precision":"month","speaker":{"type":"government","name":"Province of Ontario (Premier Kathleen Wynne)"},"cost":{"low":null,"high":null,"point":1,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"Province commits $1B","sources":[{"url":"https://thepublicrecord.ca/2025/11/federal-hamilton-lrt-funding-agreement-still-not-finalized/","outlet":"The Public Record","published_at":"2025-11-15","quote":"The project was first funded with a $1-billion provincial funding commitment announced in May 2015 by the Ontario Liberal government of Premier Kathleen Wynne."}]},{"kind":"completion_target","statement_date":"2019-12-16","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"target":{"date":"2021-01-01","precision":"year","event":"construction_start"},"headline":"Construction expected to start in 2021","sources":[{"url":"https://globalnews.ca/news/6303578/hamilton-lrt-cancelled-ontario-government","outlet":"Global News","published_at":"2019-12-16","quote":"Work on the line was expected to start in 2021."}]},{"kind":"cost","statement_date":"2019-12-16","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario (Transportation Minister Caroline Mulroney)"},"cost":{"low":5.5,"high":null,"point":null,"currency":"CAD","dollar_year":2019,"covers":"total as stated by the province"},"headline":"Province: approaching $5.5B, project cancelled","note":"The province did not break this figure down at the time, so it is not compared with the capital commitments.","sources":[{"url":"https://www.link2build.ca/news/posts/hamilton-lrt-project-cancelled/","outlet":"Link2Build","published_at":"2019-12-18","quote":"The Conservatives confirmed their commitment to funding the project during the 2018 election, but Mulroney said at her announcement that the project price tag is now approaching $5.5 billion."}]},{"kind":"status","statement_date":"2019-12-16","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario"},"new_status":"cancelled","headline":"Cancelled","sources":[{"url":"https://thepublicrecord.ca/2025/11/federal-hamilton-lrt-funding-agreement-still-not-finalized/","outlet":"The Public Record","published_at":"2025-11-15","quote":"The current Conservative government under Premier Doug Ford cancelled the project in December 2019, citing escalating costs."}]},{"kind":"cost","statement_date":"2021-05-11","date_precision":"month","speaker":{"type":"government","name":"Governments of Canada and Ontario"},"cost":{"low":null,"high":null,"point":3.4,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"Revived with $3.4B","sources":[{"url":"https://thepublicrecord.ca/2025/11/federal-hamilton-lrt-funding-agreement-still-not-finalized/","outlet":"The Public Record","published_at":"2025-11-15","quote":"The project was revived in May 2021 with a new total capital commitment of $3.4 billion, jointly funded by the federal and provincial governments, with each committing $1.7 billion."}]},{"kind":"status","statement_date":"2021-05-11","date_precision":"day","speaker":{"type":"government","name":"Governments of Canada and Ontario"},"new_status":"planning","headline":"Revived","sources":[{"url":"https://globalnews.ca/news/7851194/hamilton-transit-announcement","outlet":"Global News","published_at":"2021-05-11","quote":"The federal and provincial governments have offered $3.4 billion to build the 14 kilometre line."}]},{"kind":"completion_target","statement_date":"2021-05-11","date_precision":"month","speaker":{"type":"government","name":"Governments of Canada and Ontario"},"target":{"date":"2024-01-01","precision":"year","event":"construction_start"},"headline":"Construction to begin in 2024","sources":[{"url":"https://thepublicrecord.ca/2025/11/federal-hamilton-lrt-funding-agreement-still-not-finalized/","outlet":"The Public Record","published_at":"2025-11-15","quote":"At the time, it was promised that construction would begin in 2024."}]},{"kind":"status","statement_date":"2025-05-01","date_precision":"month","speaker":{"type":"proponent","name":"Metrolinx"},"new_status":"procurement","headline":"Civil works tender issued","note":"As of November 2025 the federal-provincial funding agreement was still not final.","sources":[{"url":"https://thepublicrecord.ca/2025/11/federal-hamilton-lrt-funding-agreement-still-not-finalized/","outlet":"The Public Record","published_at":"2025-11-15","quote":"The request for proposals for the Hamilton LRT civil and utilities works package was issued in May 2025."}]}]},{"slug":"hurontario-lrt","name":"Hazel McCallion Line (Hurontario LRT)","short_name":"Hurontario LRT","sector":"transit","jurisdiction":"ON","status":"construction","owner":"Metrolinx (Province of Ontario)","url":"https://www.overruns.ca/projects/hurontario-lrt","first_announced":"2015-04-21","first_price":"$1.6B","first_price_date":"2015-04-21","first_price_speaker":"Province of Ontario","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":21,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"An 18 km light rail line along Hurontario Street from Port Credit in Mississauga to the Brampton Gateway terminal, built by Mobilinx for Metrolinx. Due in 2022, it has no opening date.","observations":[{"kind":"cost","statement_date":"2015-04-21","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario"},"cost":{"low":null,"high":null,"point":1.6,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"Province funds the estimated $1.6B","sources":[{"url":"https://stevemunro.ca/2015/04/21/ontario-funds-100-of-the-hurontario-main-lrt/","outlet":"Steve Munro","published_at":"2015-04-21","quote":"The Transit Project Assessment for this route was approved in August 2014, but the debate remained on who would pay the estimated $1.6-billion cost."}]},{"kind":"completion_target","statement_date":"2015-04-21","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario"},"target":{"date":"2022-01-01","precision":"year","event":"first_service"},"headline":"Service by 2022","sources":[{"url":"https://stevemunro.ca/2015/04/21/ontario-funds-100-of-the-hurontario-main-lrt/","outlet":"Steve Munro","published_at":"2015-04-21","quote":"If the Hurontario-Main project proceeds as expected, detailed design will get underway soon, construction will begin in 2018, and revenue service would start in 2022."}]},{"kind":"scope_change","statement_date":"2019-03-01","date_precision":"year","speaker":{"type":"proponent","name":"Metrolinx"},"scope":{"description":"The Mississauga City Centre loop (three stations) was cut to save money; the Brampton downtown extension had already been dropped."},"headline":"Downtown loop cut","sources":[{"url":"https://www.cbc.ca/lite/story/1.7087719","outlet":"CBC News","published_at":"2024-01-18","quote":"Then, in 2019, Metrolinx removed the Mississauga loop from the line's design, citing financial pressures associated with the $4.6 billion project."}]},{"kind":"cost","statement_date":"2019-03-01","date_precision":"year","speaker":{"type":"proponent","name":"Metrolinx"},"cost":{"low":null,"high":null,"point":4.6,"currency":"CAD","dollar_year":2019,"covers":"project total as quoted (includes long-term operations and maintenance contract)"},"headline":"$4.6B project","note":"Includes the builder's long-term operations and maintenance contract, so it is not compared with the $1.6B capital estimate.","sources":[{"url":"https://www.cbc.ca/lite/story/1.7087719","outlet":"CBC News","published_at":"2024-01-18","quote":"Then, in 2019, Metrolinx removed the Mississauga loop from the line's design, citing financial pressures associated with the $4.6 billion project."}]},{"kind":"status","statement_date":"2020-03-13","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"new_status":"construction","headline":"Construction begins","sources":[{"url":"https://urbantoronto.ca/news/2025/10/construction-planning-plodding-along-hurontario-lrt.59681","outlet":"UrbanToronto","published_at":"2025-10-27","quote":"With both the City Centre Loop and Brampton extension cancelled, construction began shortly thereafter on March 13, 2020, with the line’s completion projected for 2024."}]},{"kind":"completion_target","statement_date":"2020-03-13","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"target":{"date":"2024-01-01","precision":"year","event":"first_service"},"headline":"Completion projected for 2024","sources":[{"url":"https://urbantoronto.ca/news/2025/10/construction-planning-plodding-along-hurontario-lrt.59681","outlet":"UrbanToronto","published_at":"2025-10-27","quote":"With both the City Centre Loop and Brampton extension cancelled, construction began shortly thereafter on March 13, 2020, with the line’s completion projected for 2024."}]},{"kind":"completion_target","statement_date":"2024-01-18","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"target":{"date":"2024-09-01","precision":"month","event":"first_service"},"headline":"Scheduled for September 2024","sources":[{"url":"https://www.cbc.ca/lite/story/1.7087719","outlet":"CBC News","published_at":"2024-01-18","quote":"Metrolinx started rail track installation for the project last year, which is currently scheduled to open in September 2024."}]},{"kind":"milestone","statement_date":"2026-08-12","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"milestone":{"title":"No opening date; construction continues into 2027","achieved":false},"headline":"Construction into 2027, no opening date","sources":[{"url":"https://www.insauga.com/construction-on-hazel-mccallion-lrt-to-continue-into-2027-in-mississauga/","outlet":"INsauga","published_at":"2026-08-12","quote":"Metrolinx declined to provide an estimated date for when the new line would be open for passengers."}]}]},{"slug":"iqaluit-hydro","name":"Iqaluit Nukkiksautiit Hydro Project","short_name":"Iqaluit hydro","sector":"hydro","jurisdiction":"NU","status":"planning","owner":"Nunavut Nukkiksautiit Corporation (Inuit-owned); formerly Qulliq Energy Corporation (Government of Nunavut); federal funding expected","url":"https://www.overruns.ca/projects/iqaluit-hydro","first_announced":"2013-01-01","first_price":"$356M","first_price_date":"2013-01-01","first_price_speaker":"Qulliq Energy Corporation (Government of Nunavut)","latest_estimate":"up to $500M","latest_estimate_date":"2017-01-01","latest_estimate_speaker":"Johnny Mike, minister responsible for Qulliq Energy Corporation","cost_basis":"capital cost","multiple_after_inflation":1.32,"multiple_as_announced":1.4,"delay_months":-36,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A hydroelectric plant on the Kuugaluk River about 60 km from Iqaluit to replace the city's diesel power. Started by Nunavut's Crown utility Qulliq Energy, shelved in 2014, and revived by the Inuit-owned Nunavut Nukkiksautiit Corp.; Ottawa is expected to be the main funder.","observations":[{"kind":"cost","statement_date":"2013-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Qulliq Energy Corporation (Government of Nunavut)"},"cost":{"low":null,"high":null,"point":0.356,"currency":"CAD","dollar_year":2013,"covers":"capital cost"},"headline":"About $356M for two sites","note":"Jaynes Inlet and Armshow South.","sources":[{"url":"https://assembly.nu.ca/sites/default/files/TD-330-4(3)-EN-Qulliq-Energy-Corporation-Iqaluit-Hydroelectric-Project-Report.pdf","outlet":"Qulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3))","published_at":"2017-06-08","quote":"As of 2013, the total cost of the project is estimated at approximately $356 million to construct both hydro development sites."},{"url":"https://assembly.nu.ca/sites/default/files/TD-330-4(3)-EN-Qulliq-Energy-Corporation-Iqaluit-Hydroelectric-Project-Report.pdf","outlet":"Qulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3))","published_at":"2017-06-08","quote":"A 2013 capital estimate quoted the price of constructing the first phase of the hydro development at Jaynes Inlet to be $211.5 million and the second phase at Armshow South to be $144.5 million."}]},{"kind":"status","statement_date":"2014-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Qulliq Energy Corporation"},"new_status":"paused","headline":"Put on hold: too costly for QEC","sources":[{"url":"https://assembly.nu.ca/sites/default/files/TD-330-4(3)-EN-Qulliq-Energy-Corporation-Iqaluit-Hydroelectric-Project-Report.pdf","outlet":"Qulliq Energy Corporation report tabled in the Legislative Assembly of Nunavut (TD-330-4(3))","published_at":"2017-06-08","quote":"In 2014, the Iqaluit Hydroelectric project was put on hold due to the large capital investment required to proceed with the project which is beyond QEC’s funding and borrowing ability."}]},{"kind":"cost","statement_date":"2017-01-01","date_precision":"year","speaker":{"type":"government","name":"Johnny Mike, minister responsible for Qulliq Energy Corporation"},"cost":{"low":null,"high":0.5,"point":null,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"Approaching $500M","note":"Told to Nunavut's legislative assembly.","sources":[{"url":"https://nunatsiaq.com/stories/article/iqaluit-hydroelectric-project-proponent-makes-pitch-for-modern-arctic-capital/","outlet":"Nunatsiaq News","published_at":"2025-11-07","quote":"In 2017, its cost was estimated to be “approaching $500 million,” Johnny Mike, then-minister for QEC, told the legislative assembly."}]},{"kind":"scope_change","statement_date":"2023-01-01","date_precision":"year","speaker":{"type":"proponent","name":"Nunavut Nukkiksautiit Corporation"},"scope":{"description":"Project taken over by Nunavut Nukkiksautiit Corp. and moved from the Jaynes Inlet/Armshow South sites to the Kuugaluk River."},"headline":"New owner, new site: Kuugaluk River","sources":[{"url":"https://www.cbc.ca/lite/story/1.7450146","outlet":"CBC News","published_at":"2025-02-04","quote":"Nunavut Nukkiksautiit Corporation identified the Kuugaluk River (McKeand River South), 60 kilometres northwest of Iqaluit, as a possible site for the project after doing community consultations in 2023."}]},{"kind":"cost","statement_date":"2024-10-01","date_precision":"month","speaker":{"type":"media_estimate","name":"CBC News (estimator not named)"},"cost":{"low":0.4,"high":0.5,"point":null,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Reported: $400-500M","note":"CBC didn't say who estimated it, so it isn't used as the official figure.","sources":[{"url":"https://www.cbc.ca/lite/story/1.7450146","outlet":"CBC News","published_at":"2025-02-04","quote":"As of last fall, the project's price tag was between $400 and $500 million."}]},{"kind":"completion_target","statement_date":"2025-11-07","date_precision":"day","speaker":{"type":"proponent","name":"Nunavut Nukkiksautiit Corporation"},"target":{"date":"2033-01-01","precision":"year","event":"completion"},"headline":"Proponent: operational by 2033","sources":[{"url":"https://nunatsiaq.com/stories/article/iqaluit-hydroelectric-project-proponent-makes-pitch-for-modern-arctic-capital/","outlet":"Nunatsiaq News","published_at":"2025-11-07","quote":"It would include an approximately 50-metre-high dam and a powerhouse and could be operational by 2033 generating 15 megawatts for about 100 years."},{"url":"https://nunatsiaq.com/stories/article/what-a-day-this-is-iqaluit-hydroelectric-project-could-be-ready-3-years-sooner-than-expected/","outlet":"Nunatsiaq News","published_at":"2025-11-14","quote":"Originally, proponents hoped to have the plant running by 2033."}]},{"kind":"milestone","statement_date":"2025-11-13","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"milestone":{"title":"$26M in federal funding for design, data collection and engagement","achieved":true},"headline":"$26M federal for design; referred to the Major Projects Office","sources":[{"url":"https://www.nationalobserver.com/2025/11/14/news/iqaluit-hydro-power-nunavut-major-project","outlet":"Canada's National Observer","published_at":"2025-11-14","quote":"Since February 2025, the federal government has allocated $26 million toward design, data collection and public engagement."}]},{"kind":"completion_target","statement_date":"2025-11-14","date_precision":"day","speaker":{"type":"proponent","name":"Nunavut Nukkiksautiit Corporation (Heather Shilton)"},"target":{"date":"2030-01-01","precision":"year","event":"completion"},"headline":"Commissioning targeted for 2030 after fast-tracking","sources":[{"url":"https://nunatsiaq.com/stories/article/what-a-day-this-is-iqaluit-hydroelectric-project-could-be-ready-3-years-sooner-than-expected/","outlet":"Nunatsiaq News","published_at":"2025-11-14","quote":"“We would be looking at a three-year construction window, so 2030 would be the target for commissioning,”"}]}]},{"slug":"joint-support-ships","name":"Joint Support Ships (Protecteur-class)","short_name":"Joint support ships","sector":"defence","jurisdiction":"federal","status":"construction","owner":"National Defence (Royal Canadian Navy), with Public Services and Procurement Canada","url":"https://www.overruns.ca/projects/joint-support-ships","first_announced":"2004-01-01","first_price":"$2.1B","first_price_date":"2004-01-01","first_price_speaker":"Government of Canada","latest_estimate":"$5B+","latest_estimate_date":"2026-10-02","latest_estimate_speaker":"National Defence","cost_basis":"capital cost","multiple_after_inflation":1.48,"multiple_as_announced":2.38,"delay_months":180,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Two naval supply ships, HMCS Protecteur and HMCS Preserver, being built by Seaspan in Vancouver to replace the navy's ageing replenishment ships. The program was announced in 2004 for three ships, cancelled in 2008, and restarted for two.","observations":[{"kind":"cost","statement_date":"2004-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":2.1,"currency":"CAD","dollar_year":2004,"covers":"capital cost"},"headline":"$2.1B allocated for three ships","note":"The replacement was announced in 2004. The PBO report that describes this figure was published in 2013.","sources":[{"url":"https://www.marinelog.com/news/big-questions-on-costs-of-canadas-nsps/","outlet":"Marine Log (quoting a Parliamentary Budget Officer report)","published_at":"2013-02-28","quote":"The Government allocated $2.1 billion to design, develop, and acquire the three ships."}]},{"kind":"completion_target","statement_date":"2004-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2012-01-01","precision":"year","event":"first_delivery"},"headline":"First of three ships due in 2012","sources":[{"url":"https://www.marinelog.com/news/big-questions-on-costs-of-canadas-nsps/","outlet":"Marine Log (quoting a Parliamentary Budget Officer report)","published_at":"2013-02-28","quote":"Three Joint Support Ships (JSS) were proposed, with a contract to be awarded in 2008, the first ship delivered in 2012, and the project completed in 2016."}]},{"kind":"milestone","statement_date":"2008-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"milestone":"Program shut down in 2008 after bids exceeded the cost limit","headline":"Cancelled in 2008 when bids ran over budget","note":"It was later folded into the National Shipbuilding Strategy and relaunched.","sources":[{"url":"https://globalnews.ca/news/1095187/failed-navy-supply-ship-bid-costs-harper-government-up-to-8-million/","outlet":"The Canadian Press, via Global News","published_at":"2014-01-20","quote":"The program was shut down in 2008, on the eve of the election that year, when the bids exceeded the Harper government’s cost limits."}]},{"kind":"scope_change","statement_date":"2009-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"scope":{"description":"Number of ships reduced from three to two, delivery dates pushed out and requirements changed."},"headline":"Cut from three ships to two","sources":[{"url":"https://www.marinelog.com/news/big-questions-on-costs-of-canadas-nsps/","outlet":"Marine Log (quoting a Parliamentary Budget Officer report)","published_at":"2013-02-28","quote":"In 2009, however, the Government found that the three ships would not fit within the $2.1 billion budget. In response, the number of ships was reduced to two, delivery dates pushed out, and requirements changed."}]},{"kind":"cost","statement_date":"2009-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":2.6,"currency":"CAD","dollar_year":2009,"covers":"capital cost"},"headline":"Relaunched with a $2.6B budget for two ships","note":"Two ships instead of three. The figure is in fixed nominal dollars with no adjustment for inflation.","sources":[{"url":"https://www.marinelog.com/news/big-questions-on-costs-of-canadas-nsps/","outlet":"Marine Log (quoting a Parliamentary Budget Officer report)","published_at":"2013-02-28","quote":"The new budget was set at $2.60 billion in fixed nominal dollars."}]},{"kind":"cost","statement_date":"2013-02-28","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":null,"point":4.13,"currency":"CAD","dollar_year":2013,"covers":"capital cost"},"headline":"PBO: budget should be $4.13B","note":"Compared with the program's original budget, $1.5B more.","sources":[{"url":"https://amp.cbc.ca/lite/story/1.1320633","outlet":"The Canadian Press, via CBC News","published_at":"2013-02-28","quote":"Parliamentary Budget Officer Kevin Page recommended Thursday that the government budget $4.13 billion for purchasing the two new ships, $1.5 billion more than the program's original budget."}]},{"kind":"completion_target","statement_date":"2014-01-20","date_precision":"day","speaker":{"type":"government","name":"National Defence"},"target":{"date":"2018-01-01","precision":"year","event":"first_delivery"},"headline":"First delivery hoped for 2018-19","sources":[{"url":"https://globalnews.ca/news/1095187/failed-navy-supply-ship-bid-costs-harper-government-up-to-8-million/","outlet":"The Canadian Press, via Global News","published_at":"2014-01-20","quote":"One of the companies that received payment has subsequently been hired to work with Vancouver-based Seaspan Shipyards to provide the design for the new program, which hopes to deliver vessels by 2018-19."}]},{"kind":"cost","statement_date":"2020-06-15","date_precision":"day","speaker":{"type":"government","name":"National Defence"},"cost":{"low":null,"high":null,"point":4.1,"currency":"CAD","dollar_year":2020,"covers":"capital cost"},"headline":"Total project cost now $4.1B","note":"Reported as the third figure after $2.3B in 2011 and $3.4B. The Naval News breakdown is $3.1B to buy the two ships and spares plus $1B for design, project management and contingency.","sources":[{"url":"https://www.navalnews.com/naval-news/2024/12/canada-names-and-launches-first-of-new-protecteur-class-aor-ships/","outlet":"Naval News","published_at":"2024-12-16","quote":"The total JSS budget includes $3.1 billion for the purchase of the two ships and initial spares, as well as $1 billion for design and production engineering work, project management and associated contingency costs, resulting in a total value of $4.1B."},{"url":"https://www.cheknews.ca/?p=675295","outlet":"The Canadian Press, via CHEK News","published_at":"2020-06-15","quote":"That figure was later revised up to $3.4 billion before today’s announcement, which brings the total cost to $4.1 billion."}]},{"kind":"completion_target","statement_date":"2020-06-15","date_precision":"day","speaker":{"type":"government","name":"National Defence"},"target":{"date":"2023-01-01","precision":"year","event":"first_delivery"},"headline":"First ship now due in 2023","sources":[{"url":"https://www.cheknews.ca/?p=675295","outlet":"The Canadian Press, via CHEK News","published_at":"2020-06-15","quote":"Work on the first of the two ships has already started and the government says it expects the vessel to be delivered in 2023, four years later than originally planned."}]},{"kind":"completion_target","statement_date":"2024-12-16","date_precision":"month","speaker":{"type":"proponent","name":"Seaspan Shipyards / Royal Canadian Navy"},"target":{"date":"2025-12-01","precision":"year","event":"first_delivery"},"headline":"HMCS Protecteur launched, delivery end of 2025","note":"Naval News reports the first ship had been expected in 2023 and was delayed by a year at the time of the 2024 launch.","sources":[{"url":"https://www.bairdmaritime.com/security/naval/naval-auxiliary-support/canadian-navy-launches-first-of-class-joint-support-ship-hmcs-protecteur-in-vancouver","outlet":"Baird Maritime","published_at":"2024-12-16","quote":"The ship is scheduled to be delivered to the RCN at the end of 2025."}]},{"kind":"cost","statement_date":"2026-10-02","date_precision":"month","speaker":{"type":"government","name":"National Defence"},"cost":{"low":5,"high":null,"point":null,"currency":"CAD","dollar_year":2026,"covers":"capital cost"},"headline":"National Defence: funding over $5B","note":"The department's project page gives a funding band rather than a point estimate. The page is undated; the date shown is when it was checked.","sources":[{"url":"https://apps.forces.gc.ca/en/defence-capabilities-blueprint/project-details.asp?id=2510","outlet":"National Defence, Defence Capabilities Blueprint","published_at":"2026-10-02","quote":"Funding Range Greater than $5 billion Anticipated Timeline (Fiscal Year) Options Analysis Phase Completed Definition Phase Completed Implementation Phase In Progress Initial Delivery 2027/2028 Final Delivery 2027/2028"}]},{"kind":"completion_target","statement_date":"2026-10-02","date_precision":"month","speaker":{"type":"government","name":"National Defence"},"target":{"date":"2027-04-01","precision":"year","event":"first_delivery"},"headline":"First delivery now in fiscal 2027-28","note":"Fiscal 2027-28 runs from April 2027 to March 2028. The page is undated; the date shown is when it was checked.","sources":[{"url":"https://apps.forces.gc.ca/en/defence-capabilities-blueprint/project-details.asp?id=2510","outlet":"National Defence, Defence Capabilities Blueprint","published_at":"2026-10-02","quote":"Funding Range Greater than $5 billion Anticipated Timeline (Fiscal Year) Options Analysis Phase Completed Definition Phase Completed Implementation Phase In Progress Initial Delivery 2027/2028 Final Delivery 2027/2028"}]}]},{"slug":"keeyask-generating-station","name":"Keeyask Generating Station","short_name":"Keeyask dam","sector":"hydro","jurisdiction":"MB","status":"complete","owner":"Keeyask Hydropower Limited Partnership (Manitoba Hydro and four Cree Nations)","url":"https://www.overruns.ca/projects/keeyask-generating-station","first_announced":"2011-07-25","first_price":"$5.6B","first_price_date":"2011-07-25","first_price_speaker":"Manitoba Hydro","latest_estimate":"$8.7B","latest_estimate_date":"2021-02-18","latest_estimate_speaker":"Manitoba Hydro","cost_basis":"capital cost","multiple_after_inflation":1.31,"multiple_as_announced":1.55,"delay_months":27,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 695-megawatt hydroelectric station on the Nelson River in northern Manitoba, built by Manitoba Hydro in partnership with four Cree Nations. All seven units were in service by March 2022.","observations":[{"kind":"cost","statement_date":"2011-07-25","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"cost":{"low":null,"high":null,"point":5.6,"currency":"CAD","dollar_year":2011,"covers":"capital cost"},"headline":"Early works begin on a $5.6B station","note":"The earliest public cost figure found for the station, quoted as infrastructure work started ahead of regulatory review.","sources":[{"url":"https://canadianconsultingengineer.com/first-nations-on-board-to-develop-new-manitoba-hydro-station","outlet":"Canadian Consulting Engineer","published_at":"2011-07-25","quote":"Work is beginning this summer on infrastructure to support the $5.6-billion Keeyask hydroelectric generating station on the Nelson River in Manitoba."}]},{"kind":"completion_target","statement_date":"2011-07-25","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"target":{"date":"2019-01-01","precision":"year","event":"first_service"},"headline":"First unit targeted for 2019","sources":[{"url":"https://canadianconsultingengineer.com/first-nations-on-board-to-develop-new-manitoba-hydro-station","outlet":"Canadian Consulting Engineer","published_at":"2011-07-25","quote":"There will be seven generator units, with 2019 targeted as the date for the first unit to go into service."}]},{"kind":"cost","statement_date":"2014-07-16","date_precision":"day","speaker":{"type":"proponent","name":"Keeyask Hydropower Limited Partnership (Manitoba Hydro and four Cree Nations)"},"cost":{"low":null,"high":null,"point":6.5,"currency":"CAD","dollar_year":2014,"covers":"capital cost"},"headline":"Construction starts at $6.5B","note":"The budget approved after the 2014 Needs For and Alternatives To review by the Public Utilities Board.","sources":[{"url":"https://keeyask.com/wp-content/uploads/2014/07/07-16-KHLP-News-Release01-Revised.pdf","outlet":"Keeyask Hydropower Limited Partnership","published_at":"2014-07-16","quote":"The first generator unit in-service date is targeted for 2019 with all units being commissioned by 2020 at a total cost of $6.5 billion."}]},{"kind":"completion_target","statement_date":"2014-07-16","date_precision":"day","speaker":{"type":"proponent","name":"Keeyask Hydropower Limited Partnership"},"target":{"date":"2020-01-01","precision":"year","event":"completion"},"headline":"All seven units by 2020","sources":[{"url":"https://keeyask.com/wp-content/uploads/2014/07/07-16-KHLP-News-Release01-Revised.pdf","outlet":"Keeyask Hydropower Limited Partnership","published_at":"2014-07-16","quote":"The first generator unit in-service date is targeted for 2019 with all units being commissioned by 2020 at a total cost of $6.5 billion."}]},{"kind":"completion_target","statement_date":"2014-07-16","date_precision":"day","speaker":{"type":"proponent","name":"Keeyask Hydropower Limited Partnership"},"target":{"date":"2019-11-01","precision":"month","event":"first_service"},"headline":"First power set for November 2019","sources":[{"url":"https://www.cbc.ca/lite/story/1.5918974","outlet":"CBC News","published_at":"2021-02-18","quote":"It was initially estimated to cost $6.5 billion and expected to be in service by November 2019."}]},{"kind":"cost","statement_date":"2016-09-21","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro-Electric Board (review)"},"cost":{"low":7.2,"high":7.8,"point":null,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"Board review: $7.2B to $7.8B","note":"From a review by Manitoba Hydro's board, released by the new provincial government. It also projected a delay of 21 to 31 months.","sources":[{"url":"https://news.gov.mb.ca/news/print,index.html?item=39290","outlet":"Government of Manitoba","published_at":"2016-09-21","quote":"the cost for Bipole III is also expected to rise to between $4.9 and $5 billion from the current budget of $4.65 billion, whereas Keeyask is expected to rise to between $7.2 and $7.8 billion from the current budget of $6.5 billion"}]},{"kind":"cost","statement_date":"2017-03-07","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro (Kelvin Shepherd, CEO)"},"cost":{"low":null,"high":null,"point":8.7,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"Control budget raised to $8.7B","note":"Hydro blamed poor contractor productivity and foundation work once the bedrock was better understood.","sources":[{"url":"https://www.cbc.ca/lite/story/1.4013521","outlet":"CBC News","published_at":"2017-03-07","quote":"Dam project now expected to cost $8.7B; in-service date pushed back 21 months"},{"url":"https://globalnews.ca/news/3293420/manitoba-generating-station-costs-jump-again","outlet":"Global News","published_at":"2017-03-07","quote":"In a news release sent Tuesday Manitoba Hydro said the previously approved budget of $6.5 billion had been revised to not only include rising costs, but a revised completion date."}]},{"kind":"completion_target","statement_date":"2017-03-07","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"target":{"date":"2021-08-01","precision":"month","event":"first_service"},"headline":"In-service date moved to August 2021","sources":[{"url":"https://globalnews.ca/news/3293420/manitoba-generating-station-costs-jump-again","outlet":"Global News","published_at":"2017-03-07","quote":"Instead of November 2019, the new ‘in-service date’ is August 2021."}]},{"kind":"cost","statement_date":"2017-12-19","date_precision":"day","speaker":{"type":"other","name":"MGF Project Services (consultant to the Manitoba Public Utilities Board)"},"cost":{"low":null,"high":10.5,"point":null,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"PUB consultant: could reach $10.5B","note":"Manitoba Hydro called this a worst-case scenario, not a projected outcome.","sources":[{"url":"https://www.cbc.ca/lite/story/1.4455342","outlet":"CBC News","published_at":"2017-12-19","quote":"It found the Keeyask dam could cost as much as $10.5 billion due to the \"contractor's poor productivity and increased indirect costs\" associated with the project."}]},{"kind":"cost","statement_date":"2021-02-18","date_precision":"day","speaker":{"type":"proponent","name":"Manitoba Hydro"},"cost":{"low":null,"high":null,"point":8.7,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"First unit produces power, budget still $8.7B","note":"Hydro reaffirmed the 2017 control budget as the first unit began producing electricity.","sources":[{"url":"https://www.cbc.ca/lite/story/1.5918974","outlet":"CBC News","published_at":"2021-02-18","quote":"In March 2017, Hydro revised that cost estimate to its current control budget of $8.7 billion, which the Crown energy corporation says it's on track to meet."}]},{"kind":"status","statement_date":"2022-03-09","date_precision":"day","speaker":{"type":"proponent","name":"Keeyask Hydropower Limited Partnership"},"new_status":"complete","headline":"Seventh and final unit online","note":"Some construction inside the powerhouse continued through late summer 2022.","sources":[{"url":"https://keeyask.com/2022/06/keeyasks-seventh-and-final-unit-brought-online/","outlet":"Keeyask Hydropower Limited Partnership","published_at":"2022-06-09","quote":"Wednesday, March 9, 2022, this is the final unit — of Keeyask’s total of seven units — to be brought online."}]}]},{"slug":"mackenzie-valley-highway","name":"Mackenzie Valley Highway","short_name":"Mackenzie Valley Highway","sector":"road_bridge","jurisdiction":"NT","status":"planning","owner":"Government of the Northwest Territories, with federal funding","url":"https://www.overruns.ca/projects/mackenzie-valley-highway","first_announced":"2005-01-01","first_price":"$700M","first_price_date":"2005-01-01","first_price_speaker":"Government of the Northwest Territories ('Connecting Canada', 2005)","latest_estimate":"$3.65B","latest_estimate_date":"2026-03-04","latest_estimate_speaker":"Government of the Northwest Territories (presenters at community meetings)","cost_basis":"capital cost","multiple_after_inflation":3.31,"multiple_as_announced":5.21,"delay_months":null,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"An all-season road down the Mackenzie Valley from Wrigley, N.W.T., replacing winter roads: first 321 km to Norman Wells, then on to Inuvik. Proposed in some form for over 50 years; the Government of the Northwest Territories is the proponent.","observations":[{"kind":"cost","statement_date":"2005-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of the Northwest Territories ('Connecting Canada', 2005)"},"cost":{"low":null,"high":null,"point":0.7,"currency":"CAD","dollar_year":2005,"covers":"capital cost"},"headline":"$700M","note":"From the territory's 2005 'Connecting Canada' proposal, as reported later. It then included the road on to Tuktoyaktuk.","sources":[{"url":"https://ucalgary.scholaris.ca/server/api/core/bitstreams/64dd9cc5-89f0-41b6-b0f9-91193cd59727/content","outlet":"Alan Windhorst, University of Alberta (conference paper), citing GNWT","published_at":"2006-07-13","quote":"The GNWT (Connecting Canada, 2005, p.6) estimates the costs to be $700 million."}]},{"kind":"cost","statement_date":"2009-09-16","date_precision":"day","speaker":{"type":"government","name":"GNWT Department of Transportation"},"cost":{"low":null,"high":null,"point":1.67,"currency":"CAD","dollar_year":2009,"covers":"capital cost"},"headline":"$1.67B, Wrigley to Tuktoyaktuk","sources":[{"url":"https://www.inf.gov.nt.ca/sites/inf/files/resources/mvh_economic_analysis.pdf","outlet":"GNWT Department of Transportation (Mackenzie Valley All-Weather Road Economic Analysis)","published_at":"2009-09-16","quote":"The total estimated cost of building the AWR including costs for engineering design is approximately $1.67 billion, of which $1.3 billion is for road building, $223 million is for bridge construction, and $178 million is for engineering."}]},{"kind":"cost","statement_date":"2013-06-06","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories (Corridors for Canada III)"},"cost":{"low":null,"high":null,"point":1.7,"currency":"CAD","dollar_year":2012,"covers":"capital cost"},"headline":"$1.7B to complete (2012 dollars)","sources":[{"url":"https://www.ntlegislativeassembly.ca/sites/default/files/legacy/13-06-06td_102-174.pdf","outlet":"GNWT, Corridors for Canada III (tabled document 102-17(4))","published_at":"2013-06-06","quote":"Continued support for the Mackenzie Valley Highway project, a major corridor estimated to cost $1.7 billion to complete (2012 $s), is crucial to ensure resource development in the NWT contributes to selfreliant communities and a strong and prosperous nation"},{"url":"https://www.cbc.ca/news/canada/north/mackenzie-hwy-extension-to-dempster-could-cost-1-7b-1.1928488","outlet":"CBC News","published_at":"2013-10-09","quote":"The Government of the Northwest Territories says it will cost about $1.7 billion to extend the Mackenzie Valley Highway to the Dempster Highway."}]},{"kind":"scope_change","statement_date":"2013-10-09","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories"},"scope":{"description":"The Inuvik-Tuktoyaktuk section was built as a separate highway (opened 2017). The remaining project runs from Wrigley to the Dempster Highway/Inuvik."},"headline":"Tuktoyaktuk leg split off as its own road","sources":[{"url":"https://www.cbc.ca/news/canada/north/mackenzie-hwy-extension-to-dempster-could-cost-1-7b-1.1928488","outlet":"CBC News","published_at":"2013-10-09","quote":"The Government of the Northwest Territories says it will cost about $1.7 billion to extend the Mackenzie Valley Highway to the Dempster Highway."},{"url":"https://amp.cbc.ca/lite/story/1.3760960","outlet":"CBC News","published_at":"2016-09-14","quote":"The $300-million highway to Tuktoyaktuk is still expected to open in the fall of 2017, after some summer 2017 construction work to finalize the grading and install the road's grav"}]},{"kind":"milestone","statement_date":"2018-06-27","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"milestone":{"title":"Federal funding for the Great Bear River bridge and Wrigley-Mount Gaudet road","achieved":true},"headline":"$102.5M federal: Great Bear River bridge and first 15 km","sources":[{"url":"https://www.cbc.ca/1.4724467","outlet":"CBC News","published_at":"2018-06-27","quote":"The federal government has announced it is investing $102.5 million in Northwest Territories' Mackenzie Valley Highway project, aimed to construct a bridge over the Great Bear River as well as an all-weather road."}]},{"kind":"cost","statement_date":"2026-03-04","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories (presenters at community meetings)"},"cost":{"low":null,"high":null,"point":3.65,"currency":"CAD","dollar_year":2026,"covers":"capital cost","derived":[{"field":"point","sum_of":[1.65,2]}]},"headline":"$1.65B to Norman Wells plus about $2B to Inuvik","note":"Both phases added together, to compare with earlier whole-route estimates.","sources":[{"url":"https://www.cbc.ca/news/canada/north/mackenzie-valley-highway-plans-move-ahead-but-funding-likely-depends-on-extension-to-inuvik-9.7116066","outlet":"CBC News","published_at":"2026-03-05","quote":"The cost for the first phase to Norman Wells is estimated at $1.65 billion. An additional $2 billion could be needed to complete planning and construction to Inuvik."}]},{"kind":"milestone","statement_date":"2026-09-08","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Ministers MacKinnon and Alty)"},"milestone":{"title":"$405M from the Arctic Infrastructure Fund","achieved":true},"headline":"$405M federal, the largest yet","sources":[{"url":"https://cabinradio.ca/307892/news/travel/405m-announced-for-mackenzie-valley-highway-assessment-bridges/","outlet":"Cabin Radio","published_at":"2026-09-08","quote":"The federal government is investing $405 million to advance design work on the Mackenzie Valley Highway and the building of related bridges – the biggest investment yet in the project."}]},{"kind":"completion_target","statement_date":"2026-09-08","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories"},"target":{"date":"2032-01-01","precision":"year","event":"first_service"},"headline":"Open by 2032 (Wrigley-Norman Wells)","note":"First phase, to Norman Wells. The Inuvik section has no date.","sources":[{"url":"https://cabinradio.ca/307892/news/travel/405m-announced-for-mackenzie-valley-highway-assessment-bridges/","outlet":"Cabin Radio","published_at":"2026-09-08","quote":"Under the GNWT’s proposed schedule, the Mackenzie Valley Highway could be fully constructed and open for use by 2032, meaning construction would begin in 2028."}]}]},{"slug":"montreal-blue-line-extension","name":"Montreal Metro Blue Line extension","short_name":"Blue Line extension","sector":"transit","jurisdiction":"QC","status":"construction","owner":"Société de transport de Montréal (Government of Quebec funding, federal contribution)","url":"https://www.overruns.ca/projects/montreal-blue-line-extension","first_announced":"2018-04-09","first_price":"$3.9B","first_price_date":"2018-04-09","first_price_speaker":"Governments of Canada and Quebec, City of Montreal","latest_estimate":"$7.6B","latest_estimate_date":"2024-08-23","latest_estimate_speaker":"Société de transport de Montréal","cost_basis":"capital cost","multiple_after_inflation":1.62,"multiple_as_announced":1.95,"delay_months":60,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 5.8 km, five-station eastward extension of the Montreal Metro's Blue Line from Saint-Michel to Anjou, built by the STM with provincial and federal money.","observations":[{"kind":"cost","statement_date":"2018-04-09","date_precision":"day","speaker":{"type":"government","name":"Governments of Canada and Quebec, City of Montreal"},"cost":{"low":null,"high":null,"point":3.9,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"Announced: five stations for $3.9B","note":"The extension was also announced in 2009 and 2013; earlier figures are not yet sourced (see RESEARCH_TODO).","sources":[{"url":"https://www.theglobeandmail.com/canada/article-montreal-subway-extension-delayed-until-2029-as-cost-estimate-rises-to/","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2022-03-18","quote":"Four years ago, then-premier Philippe Couillard was accompanied by Ms. Plante, Mr. Rodriguez and Prime Minister Justin Trudeau to announce that five stations serving the city’s east end would be complete by 2026 at a cost of $3.9-billion."}]},{"kind":"completion_target","statement_date":"2018-04-09","date_precision":"day","speaker":{"type":"government","name":"Governments of Canada and Quebec, City of Montreal"},"target":{"date":"2026-01-01","precision":"year","event":"first_service"},"headline":"Opening by 2026","sources":[{"url":"https://www.theglobeandmail.com/canada/article-montreal-subway-extension-delayed-until-2029-as-cost-estimate-rises-to/","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2022-03-18","quote":"Four years ago, then-premier Philippe Couillard was accompanied by Ms. Plante, Mr. Rodriguez and Prime Minister Justin Trudeau to announce that five stations serving the city’s east end would be complete by 2026 at a cost of $3.9-billion."}]},{"kind":"cost","statement_date":"2021-05-12","date_precision":"day","speaker":{"type":"media_estimate","name":"Radio-Canada (internal documents)"},"cost":{"low":null,"high":null,"point":6,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"Documents: about $6B","sources":[{"url":"https://amp.cbc.ca/news/canada/montreal/montreal-metro-blue-line-1.6022980","outlet":"CBC News","published_at":"2021-05-12","quote":"According to documents obtained by Radio-Canada, the updated price tag is estimated around $6 billion as sky-high expropriation costs put the future of the project in question."}]},{"kind":"cost","statement_date":"2022-03-18","date_precision":"day","speaker":{"type":"government","name":"Government of Quebec"},"cost":{"low":null,"high":null,"point":6.4,"currency":"CAD","dollar_year":2022,"covers":"capital cost"},"headline":"$6.4B","sources":[{"url":"https://www.cbc.ca/news/canada/montreal/blue-line-metro-stm-government-funding-1.6389902","outlet":"CBC News","published_at":"2022-03-18","quote":"The cost of the Blue line extension has ballooned, now estimated to be $6.4 billion, and construction is expected to be completed in 2029."}]},{"kind":"completion_target","statement_date":"2022-03-18","date_precision":"day","speaker":{"type":"government","name":"Government of Quebec"},"target":{"date":"2029-01-01","precision":"year","event":"first_service"},"headline":"Opening 2029","sources":[{"url":"https://www.theglobeandmail.com/canada/article-montreal-subway-extension-delayed-until-2029-as-cost-estimate-rises-to/","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2022-03-18","quote":"The long-planned extension of a Montreal subway line will open in 2029 and cost some $6.4-billion, government officials said Friday."}]},{"kind":"cost","statement_date":"2024-08-23","date_precision":"day","speaker":{"type":"proponent","name":"Société de transport de Montréal"},"cost":{"low":null,"high":null,"point":7.6,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"STM: $7.6B","sources":[{"url":"https://www.thesuburban.com/news/city_news/blue-line-extension-inches-towards-2031/article_46648872-66bc-11ef-aadb-1f9cc7676f2a.html","outlet":"The Suburban","published_at":"2024-09-04","quote":"The STM also told reporters that the price tag has gone up more than $1 billion since its last estimate, and the project, expected to service almost 70,000 passengers daily, and feature up to 2,000 workers, is now expected to cost $7.6 billion."}]},{"kind":"completion_target","statement_date":"2024-08-23","date_precision":"day","speaker":{"type":"proponent","name":"Société de transport de Montréal"},"target":{"date":"2031-01-01","precision":"year","event":"first_service"},"headline":"Trains now expected in 2031","sources":[{"url":"https://www.thesuburban.com/news/city_news/blue-line-extension-inches-towards-2031/article_46648872-66bc-11ef-aadb-1f9cc7676f2a.html","outlet":"The Suburban","published_at":"2024-09-04","quote":"The Société de transport de Montréal (STM) announced last week that the project, first envisioned some 36 year ago and slated for completion in 2026, and since twice delayed, has been delayed another year with train cars expected to roll in 2031."}]},{"kind":"status","statement_date":"2024-09-04","date_precision":"day","speaker":{"type":"proponent","name":"Société de transport de Montréal"},"new_status":"construction","headline":"Main construction begins","sources":[{"url":"https://www.thesuburban.com/news/city_news/blue-line-extension-inches-towards-2031/article_46648872-66bc-11ef-aadb-1f9cc7676f2a.html","outlet":"The Suburban","published_at":"2024-09-04","quote":"It all comes with a fair share of detours as digging begins this month, and Jean-Talon traffic will be exacerbated for at least the next 24 months, as new structures are constructed at Langelier, Lacordaire and Pie-IX."}]}]},{"slug":"muskrat-falls","name":"Muskrat Falls","short_name":"Muskrat Falls","sector":"hydro","jurisdiction":"NL","status":"complete","owner":"Nalcor Energy, now Newfoundland and Labrador Hydro (Province of Newfoundland and Labrador); federal loan guarantee","url":"https://www.overruns.ca/projects/muskrat-falls","first_announced":"2010-11-18","first_price":"$5B","first_price_date":"2010-11-18","first_price_speaker":"Nalcor Energy","latest_estimate":"$10.1B","latest_estimate_date":"2017-06-23","latest_estimate_speaker":"Nalcor Energy (Stan Marshall, CEO)","cost_basis":"capital cost","multiple_after_inflation":1.8,"multiple_as_announced":2.02,"delay_months":64,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"An 824-megawatt hydroelectric dam on the lower Churchill River in Labrador, with a transmission link to the island of Newfoundland, built by the provincial Crown corporation Nalcor Energy. Ottawa guaranteed the loans and later helped pay for the overrun.","observations":[{"kind":"cost","statement_date":"2010-11-18","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy"},"cost":{"low":null,"high":null,"point":5,"currency":"CAD","dollar_year":2010,"covers":"capital cost"},"headline":"Announced: $5B for Newfoundland and Labrador's share","note":"Announced in November 2010 with Emera. Covers the dam and the transmission link to the island; Emera's Maritime Link is separate.","sources":[{"url":"https://amp.cbc.ca/news/canada/newfoundland-labrador/muskrat-falls-costs-rise-to-almost-7b-1.2688582","outlet":"CBC News","published_at":"2014-06-26","quote":"The share of expenses for Muskrat Falls that Newfoundland and Labrador ratepayers were initially expected to bear was $5 billion."}]},{"kind":"cost","statement_date":"2012-12-17","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy"},"cost":{"low":null,"high":null,"point":6.2,"currency":"CAD","dollar_year":2012,"covers":"capital cost"},"headline":"Sanctioned at $6.2B","note":"Capital cost only. With financing, the sanction figure was about $7.4B.","sources":[{"url":"https://amp.cbc.ca/news/canada/newfoundland-labrador/muskrat-falls-costs-rise-to-almost-7b-1.2688582","outlet":"CBC News","published_at":"2014-06-26","quote":"When the Muskrat Falls Project was sanctioned in December 2012, the estimated capital cost of the development was $6.2 billion."}]},{"kind":"cost","statement_date":"2012-12-17","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy"},"cost":{"low":null,"high":null,"point":7.4,"currency":"CAD","dollar_year":2012,"covers":"total including financing"},"headline":"About $7.4B including financing","sources":[{"url":"https://globalnews.ca/news/9619115/muskrat-falls-hydroelectric-project-in-n-l-considered-commissioned-ceo","outlet":"The Canadian Press, via Global News","published_at":"2023-04-12","quote":"Muskrat Falls was officially approved in 2012 with an initial price tag of around $7.4 billion, which has ballooned to more than $13 billion."}]},{"kind":"cost","statement_date":"2014-06-26","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy (Ed Martin, CEO)"},"cost":{"low":null,"high":null,"point":6.99,"currency":"CAD","dollar_year":2014,"covers":"capital cost"},"headline":"$6.99B","sources":[{"url":"https://amp.cbc.ca/news/canada/newfoundland-labrador/muskrat-falls-costs-rise-to-almost-7b-1.2688582","outlet":"CBC News","published_at":"2014-06-26","quote":"This new $6.99-billion price tag is the second upwards shift since the megaproject was announced in late 2010."}]},{"kind":"completion_target","statement_date":"2014-06-26","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy"},"target":{"date":"2017-01-01","precision":"year","event":"first_service"},"headline":"Power expected in 2017","sources":[{"url":"https://amp.cbc.ca/news/canada/newfoundland-labrador/muskrat-falls-costs-rise-to-almost-7b-1.2688582","outlet":"CBC News","published_at":"2014-06-26","quote":"Nalcor says the latest jump in construction costs will add $8 a month to the average electricity bill in the province when Muskrat comes on stream in 2017."}]},{"kind":"cost","statement_date":"2017-06-23","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy (Stan Marshall, CEO)"},"cost":{"low":null,"high":null,"point":10.1,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"Capital cost now $10.1B","note":"Nalcor's CEO called the project a boondoggle.","sources":[{"url":"https://www.cbc.ca/lite/story/1.4174569","outlet":"CBC News","published_at":"2017-06-23","quote":"It's not only the capital cost of building Muskrat Falls that has risen — to $10.1 billion from $6.2 billion, plus financing."}]},{"kind":"cost","statement_date":"2017-06-23","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy (Stan Marshall, CEO)"},"cost":{"low":null,"high":null,"point":12.7,"currency":"CAD","dollar_year":2017,"covers":"total including financing"},"headline":"$12.7B including financing","sources":[{"url":"https://www.cbc.ca/lite/story/1.4174569","outlet":"CBC News","published_at":"2017-06-23","quote":"Labrador's Muskrat Falls price tag now $12.7B: Worse than 1969 Quebec deal, CEO says"}]},{"kind":"cost","statement_date":"2020-05-26","date_precision":"day","speaker":{"type":"proponent","name":"Nalcor Energy (Stan Marshall, CEO)"},"cost":{"low":null,"high":null,"point":13.1,"currency":"CAD","dollar_year":2020,"covers":"total including financing"},"headline":"Up to $13.1B including financing","note":"After a four-month pandemic shutdown of construction.","sources":[{"url":"https://www.cbc.ca/lite/story/1.5584735","outlet":"CBC News","published_at":"2020-05-26","quote":"That could bring the total cost of the project from $12.7 billion to $13.1 billion."}]},{"kind":"status","statement_date":"2023-04-12","date_precision":"day","speaker":{"type":"proponent","name":"Newfoundland and Labrador Hydro"},"new_status":"complete","headline":"Project declared commissioned","note":"With financing, the total is more than $13B.","sources":[{"url":"https://globalnews.ca/news/9619115/muskrat-falls-hydroelectric-project-in-n-l-considered-commissioned-ceo","outlet":"The Canadian Press, via Global News","published_at":"2023-04-12","quote":"Muskrat Falls hydroelectric project in N.L. considered commissioned: CEO"}]}]},{"slug":"niagara-tunnel","name":"Niagara Tunnel (Sir Adam Beck water tunnel)","short_name":"Niagara Tunnel","sector":"hydro","jurisdiction":"ON","status":"complete","owner":"Ontario Power Generation (Province of Ontario)","url":"https://www.overruns.ca/projects/niagara-tunnel","first_announced":"2005-08-01","first_price":"$985M","first_price_date":"2005-08-01","first_price_speaker":"Ontario Power Generation","latest_estimate":"$1.6B","latest_estimate_date":"2010-12-01","latest_estimate_speaker":"Ontario Power Generation","cost_basis":"capital cost","multiple_after_inflation":1.49,"multiple_as_announced":1.62,"delay_months":39,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 10 km tunnel under the city of Niagara Falls carrying extra water from the Niagara River to OPG's Sir Adam Beck generating stations, bored by the machine known as Big Becky.","observations":[{"kind":"cost","statement_date":"2005-08-01","date_precision":"year","speaker":{"type":"proponent","name":"Ontario Power Generation"},"cost":{"low":null,"high":null,"point":0.985,"currency":"CAD","dollar_year":2005,"covers":"capital cost"},"headline":"Original estimate $985M","sources":[{"url":"https://electricityforum.com/news-archive/dec10/bigbeckybreaksdown","outlet":"Electricity Forum","published_at":"2010-12-01","quote":"The cost of the project has risen to $1.6 billion from the original estimate of $985 million."}]},{"kind":"completion_target","statement_date":"2005-08-01","date_precision":"year","speaker":{"type":"proponent","name":"Ontario Power Generation"},"target":{"date":"2009-01-01","precision":"year","event":"completion"},"headline":"Due by 2009","sources":[{"url":"https://electricityforum.com/news-archive/dec10/bigbeckybreaksdown","outlet":"Electricity Forum","published_at":"2010-12-01","quote":"Big Becky, which started boring in 2006, was supposed to have completed the job by 2009."}]},{"kind":"cost","statement_date":"2010-12-01","date_precision":"month","speaker":{"type":"proponent","name":"Ontario Power Generation"},"cost":{"low":null,"high":null,"point":1.6,"currency":"CAD","dollar_year":2010,"covers":"capital cost"},"headline":"Revised budget $1.6B","note":"OPG rebaselined the project after the tunnel boring machine hit poor rock.","sources":[{"url":"https://electricityforum.com/news-archive/dec10/bigbeckybreaksdown","outlet":"Electricity Forum","published_at":"2010-12-01","quote":"The cost of the project has risen to $1.6 billion from the original estimate of $985 million."}]},{"kind":"completion_target","statement_date":"2010-12-01","date_precision":"month","speaker":{"type":"proponent","name":"Ontario Power Generation"},"target":{"date":"2013-01-01","precision":"year","event":"completion"},"headline":"Now 2013","sources":[{"url":"https://electricityforum.com/news-archive/dec10/bigbeckybreaksdown","outlet":"Electricity Forum","published_at":"2010-12-01","quote":"Although the boring will be completed early in the New Year, the project as a whole won’t be finished until 2013, as the rough tunnel must be lined before it can be used."}]},{"kind":"status","statement_date":"2013-03-21","date_precision":"month","speaker":{"type":"proponent","name":"Ontario Power Generation"},"new_status":"complete","headline":"Completed, under the revised budget","note":"Reported as finished $100M under the revised $1.6B budget and ahead of the revised schedule; still four years later and well above the original $985M.","sources":[{"url":"https://tunnelingonline.com/hatch-mott-macdonaldhatch-recognized-niagara-tunnel-project/","outlet":"Tunneling Online","published_at":"2013-12-18","quote":"As Platts reported, “The Niagara Tunnel was safely completed in March 2013, nine months ahead of schedule and $100 million under its $1.6 billion budget."}]}]},{"slug":"north-coast-transmission-line","name":"North Coast Transmission Line","short_name":"North Coast Transmission","sector":"energy","jurisdiction":"BC","status":"construction","owner":"BC Hydro (Province of British Columbia); federal funding under the 2026 Canada-B.C. agreement","url":"https://www.overruns.ca/projects/north-coast-transmission-line","first_announced":"2023-01-19","first_price":"$3B","first_price_date":"2023-02-21","first_price_speaker":"BC Hydro (Chris O'Riley, CEO)","latest_estimate":"$6B","latest_estimate_date":"2025-10-20","latest_estimate_speaker":"Government of British Columbia","cost_basis":"capital cost","multiple_after_inflation":1.91,"multiple_as_announced":2,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A second 500-kilovolt line from Prince George to Terrace (phases 1 and 2), later extended north toward Bob Quinn Lake (phase 3), built by Crown utility BC Hydro to power LNG and mining projects on the North Coast.","observations":[{"kind":"announcement","statement_date":"2023-01-19","date_precision":"day","speaker":{"type":"proponent","name":"BC Hydro (Chris O'Riley, CEO)"},"headline":"BC Hydro starts planning a second Prince George-Terrace line","note":"O'Riley said construction would likely not start this decade.","sources":[{"url":"https://www.prpeak.com/highlights/bc-hydro-plans-to-twin-pg-terrace-transmission-line-6406759","outlet":"Prince George Citizen (Glacier Media), via Powell River Peak","published_at":"2023-01-19","quote":"“Today we announced the start of a process to look at twinning the 500,000 volt transmission line between Prince George and Terrace and that would support potential industrial development on the North Coast,” said BC Hydro president/CEO Chris O’Riley"}]},{"kind":"cost","statement_date":"2023-02-21","date_precision":"day","speaker":{"type":"proponent","name":"BC Hydro (Chris O'Riley, CEO)"},"cost":{"low":null,"high":null,"point":3,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"$3B","note":"For the Prince George–Terrace line, later phases 1 and 2.","sources":[{"url":"https://www.theglobeandmail.com/business/article-bc-hydro-north-coast-transmission-project/","outlet":"The Globe and Mail","published_at":"2023-02-21","quote":"The time frame for a $3-billion transmission project in northern British Columbia could be accelerated to supply more hydroelectricity to industrial customers such as LNG Canada, BC Hydro’s chief executive officer says."}]},{"kind":"cost","statement_date":"2025-10-20","date_precision":"day","speaker":{"type":"government","name":"Government of British Columbia"},"cost":{"low":null,"high":null,"point":6,"currency":"CAD","dollar_year":2025,"covers":"capital cost"},"headline":"Phases 1 and 2 now $6B","sources":[{"url":"https://thetyee.ca/News/2025/10/21/BC-Fast-Tracks-North-Coast-Transmission-Line/","outlet":"The Tyee","published_at":"2025-10-21","quote":"The government estimates the first two phases will cost $6 billion."},{"url":"https://dailyhive.com/vancouver/north-coast-transmission-line-nctl-bc-hydro-expedited-construction","outlet":"Daily Hive","published_at":"2025-10-26","quote":"The project’s estimated cost has risen from $3 billion to $6 billion, and the provincial government is seeking federal support to help cover a portion of the investment."}]},{"kind":"status","statement_date":"2026-09-03","date_precision":"day","speaker":{"type":"government","name":"Government of Canada and Province of British Columbia"},"new_status":"construction","headline":"Construction begins; $3.9B committed by Ottawa and B.C.","note":"$3.9B is funding, not a cost estimate.","sources":[{"url":"https://boereport.com/2026/09/03/canada-breaks-ground-on-north-coast-transmission-line-to-deliver-clean-power-and-reduce-emissions/","outlet":"Government of Canada news release, via BOE Report","published_at":"2026-09-03","quote":"Under the agreement, the Government of Canada and the Province of British Columbia are committing $3.9 billion toward phases 1 and 2 of the project to deliver clean, reliable, and affordable electricity to communities across British Columbia."}]},{"kind":"completion_target","statement_date":"2026-09-03","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2032-01-01","precision":"year","event":"completion"},"headline":"Phase 2 complete by winter 2032","note":"Phase 1 is due mid-2030.","sources":[{"url":"https://www.renewcanada.net/construction-begins-on-b-c-s-north-coast-transmission-line/","outlet":"ReNew Canada","published_at":"2026-09-04","quote":"Construction of Phase 2 is anticipated to begin in 2027 and be complete by winter 2032."}]}]},{"slug":"ontario-line","name":"Ontario Line","short_name":"Ontario Line","sector":"transit","jurisdiction":"ON","status":"construction","owner":"Metrolinx (Province of Ontario)","url":"https://www.overruns.ca/projects/ontario-line","first_announced":"2019-04-10","first_price":"$10.9B","first_price_date":"2019-04-10","first_price_speaker":"Government of Ontario (Premier Doug Ford)","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":48,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A planned 15.6 km subway line in Toronto from Exhibition Place through downtown to the Ontario Science Centre, announced by the Ontario government in 2019 and delivered by Metrolinx.","observations":[{"kind":"cost","statement_date":"2019-04-10","date_precision":"month","speaker":{"type":"government","name":"Government of Ontario (Premier Doug Ford)"},"cost":{"low":null,"high":null,"point":10.9,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"Announced at $10.9B","note":"Construction only, according to Global News. It did not include the cost of running the line for 30 years.","sources":[{"url":"https://toronto.ctvnews.ca/it-is-quite-a-shock-cost-of-building-the-ontario-line-has-nearly-doubled-1.6167242","outlet":"CTV News","published_at":"2022-11-24","quote":"When the Ford government first unveiled plans for the 15.6-kilometre relief subway line in 2019, it pegged the cost at $10.9 billion and said that it would be completed by 2027."},{"url":"https://globalnews.ca/news/10579363/ontario-line-cost-increase/","outlet":"Global News","published_at":"2024-06-21","quote":"When the project was first unveiled by Premier Ford, in 2019, the province pegged the cost of building the line at $10.9 billion, a number the government said was only for construction and did not capture the money needed to run the line for 30 years."}]},{"kind":"completion_target","statement_date":"2019-04-10","date_precision":"month","speaker":{"type":"government","name":"Government of Ontario (Premier Doug Ford)"},"target":{"date":"2027-01-01","precision":"year","event":"completion"},"headline":"Completion by 2027","sources":[{"url":"https://toronto.ctvnews.ca/it-is-quite-a-shock-cost-of-building-the-ontario-line-has-nearly-doubled-1.6167242","outlet":"CTV News","published_at":"2022-11-24","quote":"When the Ford government first unveiled plans for the 15.6-kilometre relief subway line in 2019, it pegged the cost at $10.9 billion and said that it would be completed by 2027."}]},{"kind":"cost","statement_date":"2022-11-23","date_precision":"day","speaker":{"type":"government","name":"Infrastructure Ontario (contract awards)"},"cost":{"low":17,"high":19,"point":null,"currency":"CAD","dollar_year":2022,"covers":"contracts including financing and 30-year operations and maintenance"},"headline":"Contracts total $17B to $19B","note":"Adds the $6B southern stations and tunnels contract and the $9B trains, systems and operations contract to an estimate for the northern contract. Not comparable with the construction-only $10.9B.","sources":[{"url":"https://globalnews.ca/news/9298381/estimated-cost-ford-government-ontario-line-balloons/amp","outlet":"Global News","published_at":"2022-11-23","quote":"In total, the contracts amount to between $17 and $19 billion, depending on the final value of the northern portions of the line."}]},{"kind":"completion_target","statement_date":"2022-11-24","date_precision":"day","speaker":{"type":"proponent","name":"Infrastructure Ontario"},"target":{"date":"2031-01-01","precision":"year","event":"completion"},"headline":"Completion now expected in 2031","sources":[{"url":"https://toronto.ctvnews.ca/it-is-quite-a-shock-cost-of-building-the-ontario-line-has-nearly-doubled-1.6167242","outlet":"CTV News","published_at":"2022-11-24","quote":"However, new documents released by Infrastructure Ontario this month show that two contracts totalling $15 billion have already been awarded for the project, which is now expected to be completed in 2031."}]},{"kind":"cost","statement_date":"2024-06-21","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx (rapid transit project report)"},"cost":{"low":null,"high":null,"point":27.2,"currency":"CAD","dollar_year":2024,"covers":"total to build and operate"},"headline":"$27.2B to build and operate","sources":[{"url":"https://globalnews.ca/news/10579363/ontario-line-cost-increase/","outlet":"Global News","published_at":"2024-06-21","quote":"A Metrolinx rapid transit project report prepared for late June shows the Ontario Line is now set to cost taxpayers $27.2 billion to build and operate, a 43 per cent increase from two years ago."}]},{"kind":"cost","statement_date":"2026-08-11","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx (CEO Michael Lindsay)"},"cost":{"low":null,"high":null,"point":34,"currency":"CAD","dollar_year":2026,"covers":"total as reported by CTV News (basis not stated)"},"headline":"Current cost about $34B","note":"CTV reports Metrolinx would not give a target opening date from February 2026 and said the line was on track for completion in the \"early 2030s\".","sources":[{"url":"https://www.ctvnews.ca/toronto/article/ontario-line-costs-reach-34b-more-than-triple-the-original-budget/","outlet":"CTV News","published_at":"2026-08-12","quote":"Lindsay confirmed at an unrelated press conference on Tuesday that the awarding of a $4.32 billion contract for three-kilometres of tunneling underneath Pape Avenue and the construction of two underground stations has pushed the current cost of the Ontario Line to around $34 billion."},{"url":"https://www.ctvnews.ca/toronto/article/ontario-line-costs-reach-34b-more-than-triple-the-original-budget/","outlet":"CTV News","published_at":"2026-08-12","quote":"That is more than three times the original $10.9 billion cost estimate that was first shared for the project back in 2019."}]}]},{"slug":"ottawa-hospital-civic-campus","name":"The Ottawa Hospital new Civic campus","short_name":"Ottawa Civic campus","sector":"health","jurisdiction":"ON","status":"procurement","owner":"The Ottawa Hospital (Province of Ontario funding)","url":"https://www.overruns.ca/projects/ottawa-hospital-civic-campus","first_announced":"2021-05-04","first_price":"$2.8B","first_price_date":"2021-05-04","first_price_speaker":"The Ottawa Hospital","latest_estimate":"$2.8B","latest_estimate_date":"2024-02-20","latest_estimate_speaker":"The Ottawa Hospital","cost_basis":"capital cost","multiple_after_inflation":0.88,"multiple_as_announced":1,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A new 641-room hospital campus at Dow's Lake beside the Central Experimental Farm, to replace the Civic campus. Built under a progressive public-private partnership with EllisDon and PCL; most of the money comes from Ontario.","observations":[{"kind":"cost","statement_date":"2021-05-04","date_precision":"day","speaker":{"type":"proponent","name":"The Ottawa Hospital"},"cost":{"low":null,"high":null,"point":2.8,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"$2.8B new campus","sources":[{"url":"https://globalnews.ca/news/7832493/ottawa-hospital-civic-campus-2028/amp/","outlet":"Global News","published_at":"2021-05-04","quote":"The Ottawa Hospital on Tuesday morning showed a first look at plans for its new Civic campus, a long-awaited $2.8-billion project with designs influenced by lessons from the COVID-19 pandemic."}]},{"kind":"completion_target","statement_date":"2021-05-04","date_precision":"day","speaker":{"type":"proponent","name":"The Ottawa Hospital"},"target":{"date":"2028-01-01","precision":"year","event":"first_service"},"headline":"Open in 2028","sources":[{"url":"https://globalnews.ca/news/7832493/ottawa-hospital-civic-campus-2028/amp/","outlet":"Global News","published_at":"2021-05-04","quote":"The new site, set to open to the public in 2028, will be built just down Carling Avenue from the existing Civic campus, coming to a head at Preston Street and Prince of Wales Drive."}]},{"kind":"cost","statement_date":"2024-02-20","date_precision":"day","speaker":{"type":"proponent","name":"The Ottawa Hospital"},"cost":{"low":null,"high":null,"point":2.8,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Builders chosen, still $2.8B","sources":[{"url":"https://obj.ca/?p=150474","outlet":"Ottawa Business Journal","published_at":"2024-02-20","quote":"Partners for the $2.8-billion project were chosen after a 14-month selection process."}]},{"kind":"completion_target","statement_date":"2024-02-20","date_precision":"day","speaker":{"type":"proponent","name":"The Ottawa Hospital"},"target":{"date":"2028-01-01","precision":"year","event":"completion"},"headline":"Construction to finish in 2028","sources":[{"url":"https://obj.ca/?p=150474","outlet":"Ottawa Business Journal","published_at":"2024-02-20","quote":"Construction of the new Civic campus is slated to start later this year and is expected to be completed in 2028."}]},{"kind":"status","statement_date":"2024-02-20","date_precision":"day","speaker":{"type":"proponent","name":"The Ottawa Hospital and Infrastructure Ontario"},"new_status":"procurement","headline":"Progressive P3 development phase","sources":[{"url":"https://obj.ca/?p=150474","outlet":"Ottawa Business Journal","published_at":"2024-02-20","quote":"Partners for the $2.8-billion project were chosen after a 14-month selection process."}]},{"kind":"milestone","statement_date":"2025-02-12","date_precision":"day","speaker":{"type":"proponent","name":"The Ottawa Hospital"},"milestone":{"title":"No construction contract yet; cost and 2028 opening under review","achieved":false},"headline":"Cost and opening date in question","sources":[{"url":"https://amp.cbc.ca/news/canada/ottawa/ottawa-hospital-civic-campus-update-1.7455325","outlet":"CBC News","published_at":"2025-02-12","quote":"It remains to be seen if the original $2.8-billion price tag or 2028 target opening date for the new Civic campus will hold."}]},{"kind":"cost","statement_date":"2026-10-27","date_precision":"day","speaker":{"type":"government","name":"David Piccini, Ontario Minister of Infrastructure"},"cost":{"low":null,"high":10,"point":null,"currency":"CAD","dollar_year":2026,"covers":"provincial investment (as quoted; Ministry of Health would not confirm)"},"headline":"Minister: province investing 'just shy of $10 billion'","sources":[{"url":"https://www.ctvnews.ca/ottawa/article/provincial-investment-into-ottawa-hospital-civic-campus-now-10-billion-minister-says/","outlet":"CTV News Ottawa","published_at":"2026-10-28","quote":"“The investments that we’re making that are putting members to work right now on an investment of just shy of $10 billion towards the hospital,” Piccini said in response to a question from Ottawa MPP Stephen Blais."}]}]},{"slug":"ottawa-lrt-stage-1","name":"Ottawa LRT Stage 1 (Confederation Line, Line 1)","short_name":"Ottawa LRT Stage 1","sector":"transit","jurisdiction":"ON","status":"operational","owner":"City of Ottawa, with federal and provincial funding","url":"https://www.overruns.ca/projects/ottawa-lrt-stage-1","first_announced":"2010-06-09","first_price":"$2.1B","first_price_date":"2010-06-09","first_price_speaker":"City of Ottawa","latest_estimate":"$2.13B","latest_estimate_date":"2012-12-19","latest_estimate_speaker":"City of Ottawa","cost_basis":"capital cost","multiple_after_inflation":0.97,"multiple_as_announced":1.01,"delay_months":9,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 12.5 km light rail line with a downtown tunnel from Tunney's Pasture to Blair, built under a fixed-price contract with the Rideau Transit Group. It opened more than a year late and its failures led to a public inquiry.","observations":[{"kind":"cost","statement_date":"2010-06-09","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa"},"cost":{"low":null,"high":null,"point":2.1,"currency":"CAD","dollar_year":2010,"covers":"capital cost"},"headline":"Phase one estimated at $2.1B","note":"Earlier figures of $1.4B and $1.8B are reported without dates; see RESEARCH_TODO.","sources":[{"url":"https://www.rtands.com/?p=1822","outlet":"Railway Track & Structures","published_at":"2010-06-09","quote":"Now, the total cost for phase one is estimated at C$2.1 billion."}]},{"kind":"completion_target","statement_date":"2010-06-09","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa"},"target":{"date":"2018-01-01","precision":"year","event":"completion"},"headline":"Completion expected 2018","sources":[{"url":"https://www.rtands.com/?p=1822","outlet":"Railway Track & Structures","published_at":"2010-06-09","quote":"Construction on the first phase of the project is expected to begin in 2013, with a completion date of 2018."}]},{"kind":"completion_target","statement_date":"2011-07-07","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa"},"target":{"date":"2017-12-01","precision":"month","event":"completion"},"headline":"Completion end of 2017","sources":[{"url":"https://www.cbc.ca/1.1004851","outlet":"CBC News","published_at":"2011-07-07","quote":"The project is slated to be completed at the end of 2017."}]},{"kind":"cost","statement_date":"2011-07-07","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa (Mayor Jim Watson)"},"cost":{"low":null,"high":null,"point":2.1,"currency":"CAD","dollar_year":2011,"covers":"capital cost"},"headline":"Tunnel moved to Queen Street, still $2.1B","sources":[{"url":"https://www.cbc.ca/1.1004851","outlet":"CBC News","published_at":"2011-07-07","quote":"The cost of the project also drops to $1.74 billion in 2009 dollars, or $2.1 billion in inflation adjusted dollars."}]},{"kind":"cost","statement_date":"2012-12-19","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa"},"cost":{"low":null,"high":null,"point":2.13,"currency":"CAD","dollar_year":2012,"covers":"capital cost"},"headline":"Fixed price $2.13B with Rideau Transit Group","sources":[{"url":"https://www.cbc.ca/1.1187784","outlet":"CBC News","published_at":"2012-12-19","quote":"The Rideau Transit Group will build the 12.5-kilometre line for a fixed price of $2.13 billion."}]},{"kind":"completion_target","statement_date":"2012-12-19","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa"},"target":{"date":"2018-05-24","precision":"day","event":"first_service"},"headline":"Handover due May 24, 2018","note":"The contract handover date; the first of four missed handover dates.","sources":[{"url":"https://globalnews.ca/news/5803885/ottawa-lrt-opening-september","outlet":"Global News","published_at":"2019-08-23","quote":"RTG missed four official handover dates over the last 15 months: May 24, 2018, Nov. 2, 2018, Mar. 31, 2019 and Aug. 16, 2019."}]},{"kind":"status","statement_date":"2019-09-14","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa"},"new_status":"operational","headline":"Opened to the public","note":"Opened 15 months after the original handover date; a provincial public inquiry followed in 2022.","sources":[{"url":"https://globalnews.ca/news/5803885/ottawa-lrt-opening-september","outlet":"Global News","published_at":"2019-08-23","quote":"Ottawa residents can start riding the light-rail trains on the long-delayed Confederation Line on Sept. 14, the mayor of Ottawa announced on Friday."}]}]},{"slug":"ottawa-lrt-stage-2","name":"Ottawa LRT Stage 2 (O-Train extensions)","short_name":"Ottawa LRT Stage 2","sector":"transit","jurisdiction":"ON","status":"construction","owner":"City of Ottawa","url":"https://www.overruns.ca/projects/ottawa-lrt-stage-2","first_announced":"2015-01-01","first_price":"$3B","first_price_date":"2015-01-01","first_price_speaker":"City of Ottawa (council)","latest_estimate":"$4.91B","latest_estimate_date":"2023-11-17","latest_estimate_speaker":"City of Ottawa (staff report)","cost_basis":"capital cost","multiple_after_inflation":1.32,"multiple_as_announced":1.64,"delay_months":48,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"The second stage of Ottawa's O-Train system, extending Line 1 east to Trim and west to Moodie and extending Line 2 (Trillium Line) south to Limebank and north to Bayview. Owned by the City of Ottawa with federal and provincial funding.","observations":[{"kind":"cost","statement_date":"2015-01-01","date_precision":"year","speaker":{"type":"government","name":"City of Ottawa (council)"},"cost":{"low":null,"high":null,"point":3,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"Council approves $3B for Stage 2","note":"Earliest figure found. Global News later reported the project was initially pegged at $3.4 billion and CTV Ottawa reported $3.6 billion, so reporting of the starting figure differs.","sources":[{"url":"https://www.rtands.com/?p=9447","outlet":"Railway Track & Structures","published_at":"2017-03-09","quote":"The budget for the Stage 2 LRT project remains CA$3 billion (US$2.2 billion), as approved in 2015."},{"url":"https://www.rtands.com/?p=9410","outlet":"Railway Track & Structures","published_at":"2017-02-21","quote":"The Stage 2 LRT Project budget is CA$3 billion (US$2.28 billion) and excludes the Trim Extension with one station at CA$160 million (US$121.6 million) and the Airport Rail Link with two stations at CA$155 million (US$117.8 million)."}]},{"kind":"completion_target","statement_date":"2017-03-09","date_precision":"month","speaker":{"type":"government","name":"City of Ottawa (council)"},"target":{"date":"2023-01-01","precision":"year","event":"completion"},"headline":"Line 1 west extension to open by 2023","note":"Staggered openings were planned: Line 2 south in 2021, Line 1 east in 2022 and Line 1 west in 2023.","sources":[{"url":"https://www.rtands.com/?p=9447","outlet":"Railway Track & Structures","published_at":"2017-03-09","quote":"The Stage 2 project is planned to proceed with staggered openings to allow for faster expansions to LRT service and will see the Trillium Line South extension opening in 2021, the Confederation Line East including Trim opening in 2022 and the Confederation Line West to Moodie opening by 2023."},{"url":"https://ottawa.ctvnews.ca/stage-2-of-lrt-1-billion-higher-and-delayed-two-years-1.4309046","outlet":"CTV News Ottawa","published_at":"2019-02-22","quote":"The Director of O-Train Planning, Chris Swail, says the original deadline of 2023 was an ‘aggressive target’ set in 2017."}]},{"kind":"completion_target","statement_date":"2019-02-22","date_precision":"day","speaker":{"type":"proponent","name":"City of Ottawa (staff)"},"target":{"date":"2025-01-01","precision":"year","event":"completion"},"headline":"Completion pushed to 2025","note":"CBC reported the Trillium Line would open first, in fall 2022, with the east extension by fall 2024 and the west extension in spring 2025.","sources":[{"url":"https://ottawa.ctvnews.ca/stage-2-of-lrt-1-billion-higher-and-delayed-two-years-1.4309046","outlet":"CTV News Ottawa","published_at":"2019-02-22","quote":"The project, which will see LRT taken west to Moodie, east to Trim Rd., and extend the O-Train Trillium Line to Riverside South, is also delayed by two years to 2025."}]},{"kind":"cost","statement_date":"2019-03-06","date_precision":"day","speaker":{"type":"government","name":"City of Ottawa (council)"},"cost":{"low":null,"high":null,"point":4.66,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"Council approves $4.66B","note":"The project had grown from 30 km of track to 44 km and from 19 stations to 24, according to CBC.","sources":[{"url":"https://globalnews.ca/news/5026177/ottawa-city-council-approves-funding-stage-2-lrt/","outlet":"Global News","published_at":"2019-03-06","quote":"The $4.66-billion project was initially pegged at $3.4 billion, a shift of over $1.2 billion."},{"url":"https://amp.cbc.ca/news/canada/ottawa/costs-for-lrt-expansion-keep-rising-but-there-s-no-going-back-1.7020695","outlet":"CBC News","published_at":"2023-11-17","quote":"That was already out the window by the time council approved the $4.66-billion budget in 2019."}]},{"kind":"cost","statement_date":"2023-11-17","date_precision":"day","speaker":{"type":"proponent","name":"City of Ottawa (staff report)"},"cost":{"low":null,"high":null,"point":4.91,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"Funding plan reaches $4.91B","note":"Includes unforeseen costs above the contingency fund. CBC reports the report suggested further city investment might be necessary.","sources":[{"url":"https://amp.cbc.ca/news/canada/ottawa/costs-for-lrt-expansion-keep-rising-but-there-s-no-going-back-1.7020695","outlet":"CBC News","published_at":"2023-11-17","quote":"The latest report to councillors confirms the situation has grown worse, with the city now on the hook for 51 per cent of the $4.91-billion funding plan."},{"url":"https://amp.cbc.ca/news/canada/ottawa/costs-for-lrt-expansion-keep-rising-but-there-s-no-going-back-1.7020695","outlet":"CBC News","published_at":"2023-11-17","quote":"Ottawa's light-rail transit system is again bursting beyond its budget, with members of the city's finance committee meeting to rubber stamp an additional $152 million based on new, unforeseen costs."}]},{"kind":"completion_target","statement_date":"2023-11-17","date_precision":"month","speaker":{"type":"proponent","name":"City of Ottawa (staff)"},"target":{"date":"2026-01-01","precision":"year","event":"completion"},"headline":"East extension early 2025, west late 2026","note":"The target date shown is for the west extension, the later of the two.","sources":[{"url":"https://amp.cbc.ca/news/canada/ottawa/costs-for-lrt-expansion-keep-rising-but-there-s-no-going-back-1.7020695","outlet":"CBC News","published_at":"2023-11-17","quote":"It will also extend the eastern and western ends of the Confederation Line, with the completion of those projects now set for early 2025 and late 2026, respectively."}]},{"kind":"milestone","statement_date":"2024-12-06","date_precision":"day","speaker":{"type":"proponent","name":"OC Transpo"},"milestone":{"title":"Line 2 (Trillium Line) south extension opens in stages from Jan. 6, 2025","achieved":true},"headline":"Line 2 south extension to open in stages from Jan. 6, 2025","note":"The first section of Stage 2 to open. The line grows from 8 km to 23 km with 11 stations, according to CBC.","sources":[{"url":"https://www.cbc.ca/news/canada/ottawa/ottawa-trillium-line-2-4-lrt-opening-date-1.7382654","outlet":"CBC News","published_at":"2024-12-06","quote":"Trillium Line to reopen in stages starting Monday, Jan. 6"},{"url":"https://www.cbc.ca/news/canada/ottawa/ottawa-trillium-line-2-4-lrt-opening-date-1.7382654","outlet":"CBC News","published_at":"2024-12-06","quote":"The Trillium Line was originally meant to reopen in 2022 but has faced numerous delays."}]},{"kind":"completion_target","statement_date":"2026-08-05","date_precision":"day","speaker":{"type":"proponent","name":"OC Transpo (director of rail construction Richard Holder)"},"target":{"date":"2027-01-01","precision":"year","event":"completion"},"headline":"Line 1 west extension now slated for 2027","note":"Flood damage is being assessed.","sources":[{"url":"https://www.ctvnews.ca/ottawa/article/transit-exec-says-o-train-west-extension-could-open-in-parts-due-to-flooding-damage/","outlet":"CTV News Ottawa","published_at":"2026-08-06","quote":"Speaking to CTV News Ottawa’s Leah Larocque on Wednesday, director of rail construction Richard Holder said OC Transpo and the constructor, KEV, continue to assess the damage caused by the storm and are considering options for the line, which is currently slated to open sometime in 2027."}]}]},{"slug":"pattullo-bridge-replacement","name":"Pattullo Bridge replacement (stal̕əw̓asəm Bridge)","short_name":"Pattullo Bridge replacement","sector":"road_bridge","jurisdiction":"BC","status":"operational","owner":"Province of British Columbia, with federal funding","url":"https://www.overruns.ca/projects/pattullo-bridge-replacement","first_announced":"2018-02-01","first_price":"$1.38B","first_price_date":"2021-04-01","first_price_speaker":"Province of British Columbia","latest_estimate":"$1.38B","latest_estimate_date":"2024-06-20","latest_estimate_speaker":"BC Ministry of Transportation","cost_basis":"capital cost","multiple_after_inflation":0.88,"multiple_as_announced":1,"delay_months":26,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A four-lane cable-stayed bridge over the Fraser River between New Westminster and Surrey, replacing the 1937 Pattullo Bridge. Built by Fraser Crossing Partners for the province.","observations":[{"kind":"completion_target","statement_date":"2018-02-01","date_precision":"year","speaker":{"type":"government","name":"Province of British Columbia"},"target":{"date":"2023-01-01","precision":"year","event":"first_service"},"headline":"Opening 2023","sources":[{"url":"https://www.newwestrecord.ca/local-news/pattullo-bridge-replacement-projected-delayed-another-year-8872962","outlet":"New West Record","published_at":"2024-05-28","quote":"When work on the new bridge first began, it was projected to open in 2023."}]},{"kind":"cost","statement_date":"2021-04-01","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"cost":{"low":null,"high":null,"point":1.377,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"$1.377B, on budget","note":"The province's 2018 announcement figure is not yet sourced directly; this is the first sourced statement of it.","sources":[{"url":"https://globalnews.ca/news/7734758/toll-free-pattullo-bridge-opening-date-moved-2024/amp","outlet":"Global News","published_at":"2021-04-01","quote":"The government said the new bridge, estimated to cost $1.377-billion, is still on budget."}]},{"kind":"completion_target","statement_date":"2021-04-01","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"target":{"date":"2024-01-01","precision":"year","event":"first_service"},"headline":"Moved to 2024","sources":[{"url":"https://globalnews.ca/news/7734758/toll-free-pattullo-bridge-opening-date-moved-2024/amp","outlet":"Global News","published_at":"2021-04-01","quote":"The opening date for the new toll-free Pattullo Bridge replacement has been moved from late 2023 to sometime in 2024."}]},{"kind":"completion_target","statement_date":"2024-05-27","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"target":{"date":"2025-09-01","precision":"quarter","event":"first_service"},"headline":"Now fall 2025","sources":[{"url":"https://www.newwestrecord.ca/local-news/pattullo-bridge-replacement-projected-delayed-another-year-8872962","outlet":"New West Record","published_at":"2024-05-28","quote":"“As a result, the new bridge is expected to open in fall 2025.” That’s two years later than originally projected."}]},{"kind":"cost","statement_date":"2024-06-20","date_precision":"day","speaker":{"type":"government","name":"BC Ministry of Transportation"},"cost":{"low":null,"high":null,"point":1.38,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Still $1.38B","sources":[{"url":"https://burnabynow.com/highlights/bc-ministry-sticking-to-prior-cost-estimates-on-pattullo-bridge-and-broadway-subway-9114655","outlet":"Burnaby Now","published_at":"2024-06-20","quote":"According to the ministry, the bridge cost remains $1.38 billion and the subway price tag remains $2.83 billion."}]},{"kind":"status","statement_date":"2026-02-21","date_precision":"month","speaker":{"type":"government","name":"Province of British Columbia"},"new_status":"operational","headline":"All four lanes open","sources":[{"url":"https://www.renewcanada.net/new-stal%cc%95%c9%99w%cc%93as%c9%99m-bridge-opens-as-pattullo-bridge-demolition-begins","outlet":"ReNew Canada","published_at":"2026-02-23","quote":"The Government of British Columbia announced that all four lanes on the stal̕əw̓asəm (Riverview) Bridge have now been opened to vehicle traffic between Surrey and New Westminster."}]}]},{"slug":"phoenix-pay-system","name":"Phoenix Pay System","short_name":"Phoenix pay system","sector":"it","jurisdiction":"federal","status":"operational","owner":"Public Services and Procurement Canada","url":"https://www.overruns.ca/projects/phoenix-pay-system","first_announced":"2009-01-01","first_price":"$309M","first_price_date":"2009-01-01","first_price_speaker":"Government of Canada","latest_estimate":"$1.5B+","latest_estimate_date":"2019-05-16","latest_estimate_speaker":"Government of Canada (federal budget)","cost_basis":"total cost of the system","multiple_after_inflation":4.09,"multiple_as_announced":4.85,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"The federal government's public service payroll system, introduced in 2009 at a build cost of $309 million. It began paying employees in 2016, caused widespread pay errors, and is being replaced by Dayforce.","observations":[{"kind":"cost","statement_date":"2009-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":0.309,"currency":"CAD","dollar_year":2009,"covers":"total cost of the system"},"headline":"Introduced in 2009 at $309M","note":"The budget for the whole system. Later totals count the combined cost of building and fixing it, which is what the system has actually cost.","sources":[{"url":"https://www.theglobeandmail.com/canada/article-payroll-dayforce-phoenix-federal-ottawa","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2025-08-25","quote":"The Phoenix pay system was introduced in 2009 at an initial cost of $309 million and began processing public servants’ pay in 2016."}]},{"kind":"cost","statement_date":"2018-03-26","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"cost":{"low":1,"high":null,"point":null,"currency":"CAD","dollar_year":2018,"covers":"total cost of the system"},"headline":"Building and fixing now over $1B","note":"The department's own tally, in a graph of investments, was $1.192 billion.","sources":[{"url":"https://www.cbc.ca/1.4594115","outlet":"CBC News","published_at":"2018-03-26","quote":"The department in charge of the federal government's Phoenix pay system now says the combined cost of implementing and fixing the ailing program has exceeded $1 billion."}]},{"kind":"cost","statement_date":"2018-07-31","date_precision":"day","speaker":{"type":"other","name":"Senate Standing Committee on National Finance"},"cost":{"low":null,"high":null,"point":2.2,"currency":"CAD","dollar_year":2018,"covers":"projected unplanned costs to 2023"},"headline":"Senate: $2.2B in unplanned costs by 2023","note":"The same report put the cost to date at $954 million, including the $309 million originally budgeted. The $2.2B is on top of the original budget.","sources":[{"url":"https://beta.theglobeandmail.com/politics/article-phoenix-pay-system-problems-on-track-to-cost-government-22-billion/","outlet":"The Globe and Mail","published_at":"2018-07-31","quote":"The $2.2-billion to operate and stabilize the pay system by 2023 includes funding for increased processing at the Public Pay Service Centre and money for reviewing employee pay files."}]},{"kind":"cost","statement_date":"2019-05-16","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (federal budget)"},"cost":{"low":1.5,"high":null,"point":null,"currency":"CAD","dollar_year":2019,"covers":"total cost of the system"},"headline":"Spent or planned: over $1.5B","sources":[{"url":"https://amp.cbc.ca/lite/story/1.5138036","outlet":"CBC News","published_at":"2019-05-16","quote":"The government has spent or plans to spend more than $1.5 billion so far, according to the latest federal budget."}]},{"kind":"cost","statement_date":"2019-05-16","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":2.6,"point":null,"currency":"CAD","dollar_year":2019,"covers":"total cost of the system"},"headline":"PBO: final cost could reach $2.6B","note":"The PBO said the replacement system would likely not be ready until 2023 at the earliest.","sources":[{"url":"https://amp.cbc.ca/lite/story/1.5138036","outlet":"CBC News","published_at":"2019-05-16","quote":"the final cost of the system, which has improperly paid tens of thousands of public servants since launching in 2016, could be as high as $2.6 billion."}]},{"kind":"cost","statement_date":"2024-07-09","date_precision":"day","speaker":{"type":"media_estimate","name":"The Canadian Press"},"cost":{"low":null,"high":null,"point":3.5,"currency":"CAD","dollar_year":2024,"covers":"total cost of the system"},"headline":"$3.5B spent so far","note":"Unattributed running total reported by The Canadian Press; shown as a media figure, not the headline.","sources":[{"url":"https://rdnewsnow.com/?p=639673","outlet":"The Canadian Press, via rdnewsnow.com","published_at":"2024-07-09","quote":"The Phoenix pay system debacle has so far cost the federal government $3.5 billion — a number that could continue to grow as the backlog gets dealt with."}]},{"kind":"cost","statement_date":"2025-06-23","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada (Alex Benay)"},"cost":{"low":null,"high":null,"point":5.1,"currency":"CAD","dollar_year":2025,"covers":"cost of fixing errors (excludes original build)"},"headline":"Cost of fixing Phoenix: about $5.1B","note":"Counts only the cost of fixing errors, so it is not compared with the $309M budget. The $309M build cost is on top.","sources":[{"url":"https://www.theglobeandmail.com/canada/article-phoenix-system-federal-government-alex-benay-51-billion","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2025-06-23","quote":"Benay said taxpayers likely spent about $5.1-billion to process the backlog of Phoenix errors that caused some public servants to be paid incorrectly – or sometimes not paid at all."}]},{"kind":"status","statement_date":"2025-08-25","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"new_status":"operational","headline":"In use since 2016, being replaced by Dayforce","note":"Government is paying to run Phoenix and its replacement at the same time.","sources":[{"url":"https://www.theglobeandmail.com/canada/article-payroll-dayforce-phoenix-federal-ottawa","outlet":"The Canadian Press, via The Globe and Mail","published_at":"2025-08-25","quote":"The Phoenix pay system was introduced in 2009 at an initial cost of $309 million and began processing public servants’ pay in 2016."}]},{"kind":"cost","statement_date":"2026-03-23","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (as reported by the Auditor General)"},"cost":{"low":4.2,"high":null,"point":null,"currency":"CAD","dollar_year":2026,"covers":"replacement system (Dayforce)"},"headline":"Replacement with Dayforce: over $4.2B","note":"Separate from the cost of Phoenix. The Auditor General called the estimate rough and expects the actual cost to be higher.","sources":[{"url":"https://www.cp24.com/news/canada/2026/03/23/phoenix-backlog-needs-to-be-cleared-to-avoid-errors-in-new-system-ag/","outlet":"The Canadian Press, via CP24","published_at":"2026-03-23","quote":"The report also said that while the government has estimated replacing Phoenix with Dayforce will cost more than $4.2 billion, preliminary estimates did not include costs for departments and agencies to transition to the new system."}]}]},{"slug":"pickering-refurbishment","name":"Pickering Nuclear Refurbishment (Pickering B, units 5 to 8)","short_name":"Pickering refurbishment","sector":"energy","jurisdiction":"ON","status":"approved","owner":"Ontario Power Generation (Province of Ontario)","url":"https://www.overruns.ca/projects/pickering-refurbishment","first_announced":"2024-01-30","first_price":"$26.8B","first_price_date":"2025-11-26","first_price_speaker":"Government of Ontario / Ontario Power Generation","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":"2026-11-19","last_monthly_review":"2026-11-05","summary":"The mid-life overhaul of the four Pickering B CANDU reactors at OPG's Pickering station east of Toronto, to keep them running for decades more. The province approved the full refurbishment in November 2025.","observations":[{"kind":"announcement","statement_date":"2024-01-30","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario"},"headline":"Province backs refurbishment; total cost to come later","note":"Only the first phase was priced. No total cost was given.","sources":[{"url":"https://www.cbc.ca/lite/story/1.7098524","outlet":"CBC News","published_at":"2024-01-30","quote":"A provincial official says an estimate for the total cost of the Pickering refurbishment will be provided after the year-long initiation phase, including engineering and design work, is complete."},{"url":"https://www.cbc.ca/lite/story/1.7098524","outlet":"CBC News","published_at":"2024-01-30","quote":"OPG's budget for this first phase is $2 billion, to be financed by taking on debt paid off through revenue from ratepayers once the project is generating power, said the provincial official."}]},{"kind":"cost","statement_date":"2025-11-26","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario / Ontario Power Generation"},"cost":{"low":null,"high":null,"point":26.8,"currency":"CAD","dollar_year":2025,"covers":"capital cost"},"headline":"Final budget $26.8B","note":"The first total-cost figure. Earlier phase budgets covered only parts of the work and are not compared.","sources":[{"url":"https://world-nuclear-news.org/articles/pickering-refurbishment-gets-government-go-ahead","outlet":"World Nuclear News","published_at":"2025-11-27","quote":"The final budget for the Pickering refurbishment is CAD26.8 billion (USD19.1 billion), but according to a study by the Conference Board of Canada, the mega-project - which will enable the plant to continue in operation for up to 38 more years - will increase Ontario's GDP by CAD38.2 billion in 2024 dollars over the project's lifespan, including CAD17 billion during the refurbishment phase, and increase Canada's national GDP by CAD41.6 billion over its lifespan."}]},{"kind":"status","statement_date":"2025-11-26","date_precision":"day","speaker":{"type":"government","name":"Government of Ontario"},"new_status":"approved","headline":"Province approves the full refurbishment","sources":[{"url":"https://globalnews.ca/news/11544480/ontario-moves-ahead-pickering-nuclear-refurbishment/","outlet":"Global News","published_at":"2025-11-26","quote":"The Ford government has confirmed it will move forward with the almost $27 billion refurbishment of four reactors at Pickering Nuclear Generating Station, a centrepiece of its energy policy."}]},{"kind":"completion_target","statement_date":"2025-11-26","date_precision":"day","speaker":{"type":"proponent","name":"Ontario Power Generation"},"target":{"date":"2027-01-01","precision":"year","event":"construction_start"},"headline":"Execution phase to start in early 2027","note":"OPG gives completion only as 'the mid-2030s', so no completion year is stored.","sources":[{"url":"https://world-nuclear-news.org/articles/pickering-refurbishment-gets-government-go-ahead","outlet":"World Nuclear News","published_at":"2025-11-27","quote":"It expects to begin the Project Execution Phase in early 2027, with completion expected by the mid-2030s."}]}]},{"slug":"point-lepreau-refurbishment","name":"Point Lepreau nuclear refurbishment","short_name":"Point Lepreau refurbishment","sector":"energy","jurisdiction":"NB","status":"complete","owner":"NB Power (Province of New Brunswick)","url":"https://www.overruns.ca/projects/point-lepreau-refurbishment","first_announced":"2005-08-12","first_price":"$1.4B","first_price_date":"2005-08-12","first_price_speaker":"Province of New Brunswick","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"The life-extension overhaul of New Brunswick's only nuclear reactor, done by Atomic Energy of Canada Limited for NB Power. Planned as an 18-month job, it took three years longer.","observations":[{"kind":"cost","statement_date":"2005-08-12","date_precision":"day","speaker":{"type":"government","name":"Province of New Brunswick"},"cost":{"low":null,"high":null,"point":1.4,"currency":"CAD","dollar_year":2005,"covers":"capital cost"},"headline":"Refurbishment approved at $1.4B","sources":[{"url":"https://canadianconsultingengineer.com/point-lepreau-nuclear-power-plant-to-be-fixed-at-fixed-price","outlet":"Canadian Consulting Engineer","published_at":"2005-08-12","quote":"However, the province is going to have to spend an estimated $1.4 billion on the overhaul."}]},{"kind":"status","statement_date":"2008-04-01","date_precision":"year","speaker":{"type":"proponent","name":"NB Power"},"new_status":"construction","headline":"Reactor shut for refurbishment","sources":[{"url":"https://www.cbc.ca/lite/story/1.5393207","outlet":"CBC News","published_at":"2019-12-12","quote":"AECL, a federal Crown corporation, was hired by NB Power as the contractor to overhaul Point Lepreau beginning in 2008, as the plant was nearing the end of its initial 25-year lifespan."}]},{"kind":"status","statement_date":"2012-11-23","date_precision":"month","speaker":{"type":"proponent","name":"NB Power"},"new_status":"complete","headline":"Back online, three years late","sources":[{"url":"https://www.cbc.ca/lite/story/1.5393207","outlet":"CBC News","published_at":"2019-12-12","quote":"In its first seven operational years since coming back online in November 2012, the rebuilt reactor has run at an average of 82 per cent capacity, well below the 91 per cent level NB Power predicted for those early years during hearings in 2013 on that issue."}]},{"kind":"cost","statement_date":"2019-12-12","date_precision":"day","speaker":{"type":"media_estimate","name":"CBC News"},"cost":{"low":null,"high":null,"point":2.4,"currency":"CAD","dollar_year":2019,"covers":"capital cost","derived":[{"field":"point","sum_of":[1.4,1]}]},"headline":"About $2.4B: $1B over budget","note":"CBC's account: the $1.4B budget plus $1B of overruns. No NB Power final-cost statement has been sourced yet, so this is shown as a media figure.","sources":[{"url":"https://www.cbc.ca/lite/story/1.5393207","outlet":"CBC News","published_at":"2019-12-12","quote":"The work was expected to take 18 months and cost NB Power $1.4 billion but became mired in a number of problems and eventually took three years longer than expected. Those delays pushed costs $1 billion over budget."}]}]},{"slug":"polar-icebreakers","name":"Polar icebreakers (Polar Icebreaker Project)","short_name":"Polar icebreakers","sector":"defence","jurisdiction":"federal","status":"construction","owner":"Government of Canada (Canadian Coast Guard)","url":"https://www.overruns.ca/projects/polar-icebreakers","first_announced":"2008-01-01","first_price":"$721M","first_price_date":"2008-01-01","first_price_speaker":"Government of Canada","latest_estimate":"$3.15B","latest_estimate_date":"2025-03-07","latest_estimate_speaker":"Public Services and Procurement Canada","cost_basis":"one polar icebreaker","multiple_after_inflation":3.04,"multiple_as_announced":4.37,"delay_months":156,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Heavy icebreakers for the Canadian Coast Guard. Announced in 2008 as one ship, the CCGS John G. Diefenbaker, for delivery by 2017; now two ships being built by Seaspan and Davie.","observations":[{"kind":"cost","statement_date":"2008-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":0.721,"currency":"CAD","dollar_year":2008,"covers":"one polar icebreaker"},"headline":"Announced: $721M for the CCGS John G. Diefenbaker","sources":[{"url":"https://globalnews.ca/news/7838942/canada-icebreaker-contract-awarded/","outlet":"The Canadian Press, via Global News","published_at":"2021-05-06","quote":"Originally budgeted at $721 million, the icebreaker was supposed to be delivered by 2017 and replace the Coast Guard’s flagship, the CCGS Louis S."}]},{"kind":"completion_target","statement_date":"2008-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2017-01-01","precision":"year","event":"first_delivery"},"headline":"Delivery by 2017","sources":[{"url":"https://globalnews.ca/news/7838942/canada-icebreaker-contract-awarded/","outlet":"The Canadian Press, via Global News","published_at":"2021-05-06","quote":"Originally budgeted at $721 million, the icebreaker was supposed to be delivered by 2017 and replace the Coast Guard’s flagship, the CCGS Louis S."}]},{"kind":"cost","statement_date":"2013-01-01","date_precision":"year","speaker":{"type":"government","name":"Government of Canada"},"cost":{"low":null,"high":null,"point":1.3,"currency":"CAD","dollar_year":2013,"covers":"one polar icebreaker"},"headline":"Budget raised to $1.3B","sources":[{"url":"https://globalnews.ca/news/7838942/canada-icebreaker-contract-awarded/","outlet":"The Canadian Press, via Global News","published_at":"2021-05-06","quote":"St-Laurent.But scheduling conflicts, technical problems and other issues scuttled the timeline and budget — which was increased to $1.3 billion in 2013 — before the Trudeau government quietly lifted the ship from Seaspan’s order book in August 2019."}]},{"kind":"scope_change","statement_date":"2021-05-06","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"scope":{"description":"Two polar icebreakers instead of one: one built by Seaspan in Vancouver, one by Davie in Lévis."},"headline":"Now two icebreakers","sources":[{"url":"https://globalnews.ca/news/7838942/canada-icebreaker-contract-awarded/","outlet":"The Canadian Press, via Global News","published_at":"2021-05-06","quote":"Ottawa doubling icebreaker orders as one ship goes to Quebec yard, another to Vancouver"}]},{"kind":"cost","statement_date":"2025-03-07","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"cost":{"low":null,"high":null,"point":3.15,"currency":"CAD","dollar_year":2025,"covers":"one polar icebreaker"},"headline":"Seaspan's ship contracted at $3.15B","note":"Construction contract value before tax for the ship that replaced the Diefenbaker order at Seaspan. Davie's second ship is $3.25B.","sources":[{"url":"https://search.open.canada.ca/qpnotes/record/pwgsc-tpsgc%2CPSPC-2025-QP-00035","outlet":"Public Services and Procurement Canada (Question Period note)","published_at":"2025-08-29","quote":"On March 7, 2025, Seaspan’s Vancouver Shipyards was awarded a $3.15-billion contract (excluding taxes) to build one polar icebreaker."}]},{"kind":"cost","statement_date":"2025-03-08","date_precision":"day","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"cost":{"low":null,"high":null,"point":6.4,"currency":"CAD","dollar_year":2025,"covers":"two polar icebreakers (construction contracts)","derived":[{"field":"point","sum_of":[3.15,3.25]}]},"headline":"Both ships: $6.4B in construction contracts","sources":[{"url":"https://search.open.canada.ca/qpnotes/record/pwgsc-tpsgc%2CPSPC-2025-QP-00035","outlet":"Public Services and Procurement Canada (Question Period note)","published_at":"2025-08-29","quote":"On March 7, 2025, Seaspan’s Vancouver Shipyards was awarded a $3.15-billion contract (excluding taxes) to build one polar icebreaker. On March 8, 2025, Chantier Davie Canada Inc. was awarded a $3.25-billion contract (excluding taxes) to build the other polar icebreaker."}]},{"kind":"completion_target","statement_date":"2025-03-08","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"target":{"date":"2030-01-01","precision":"year","event":"first_delivery"},"headline":"Davie's Polar Max due by 2030","sources":[{"url":"https://www.workboat.com/canada-awards-polar-icebreaker-contracts-to-davie-and-seaspan","outlet":"WorkBoat","published_at":"2025-03-10","quote":"The vessel, Polar Max, is expected to be delivered by 2030.Meanwhile, Seaspan Shipyards, North Vancouver, British Columbia, has been awarded a $3.15 billion contract to construct the other polar icebreaker."}]},{"kind":"status","statement_date":"2025-07-01","date_precision":"month","speaker":{"type":"government","name":"Public Services and Procurement Canada"},"new_status":"construction","headline":"Construction under way","sources":[{"url":"https://search.open.canada.ca/qpnotes/record/pwgsc-tpsgc%2CPSPC-2025-QP-00035","outlet":"Public Services and Procurement Canada (Question Period note)","published_at":"2025-08-29","quote":"Full-rate production of the future CCGS Imnaryuaq started in July 2025 at Seaspan’s Vancouver Shipyards, while steel cutting for the future CCGS Arpatuuq took place in August 2025 at the Canadian-owned Helsinki Shipyard in Finland, marking the start of its construction phase Background: The National Shipbuilding Strategy is a long-term plan to renew the Royal Canadian Navy and Canadian Coast Guard fleets."}]}]},{"slug":"port-lands-flood-protection","name":"Port Lands Flood Protection (Toronto)","short_name":"Port Lands flood protection","sector":"other","jurisdiction":"multi","status":"complete","owner":"Waterfront Toronto (Government of Canada, Province of Ontario, City of Toronto)","url":"https://www.overruns.ca/projects/port-lands-flood-protection","first_announced":"2016-10-20","first_price":"$1.25B","first_price_date":"2016-10-20","first_price_speaker":"Waterfront Toronto","latest_estimate":"$1.25B","latest_estimate_date":"2024-01-27","latest_estimate_speaker":"Waterfront Toronto","cost_basis":"capital cost","multiple_after_inflation":0.8,"multiple_as_announced":1,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A new mouth for the Don River and a new island in Toronto's Port Lands to protect 240 hectares from flooding, paid for equally by Ottawa, Ontario and Toronto and run by Waterfront Toronto.","observations":[{"kind":"cost","statement_date":"2016-10-20","date_precision":"day","speaker":{"type":"proponent","name":"Waterfront Toronto"},"cost":{"low":null,"high":null,"point":1.25,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"$1.25B, up from $975M","note":"An earlier $975M estimate is not yet traced to its original statement and date (see RESEARCH_TODO), so it is not the baseline.","sources":[{"url":"https://insurancebusinessmag.com/ca/news/breaking-news/port-lands-flood-protection-costs-up-to-1-25bn-44954.aspx","outlet":"Insurance Business","published_at":"2016-10-21","quote":"The cost of the flood protection project as part of the development of eastern Toronto’s Port Lands has risen from $975m to $1.25bn, it was confirmed yesterday."}]},{"kind":"cost","statement_date":"2024-01-27","date_precision":"day","speaker":{"type":"proponent","name":"Waterfront Toronto"},"cost":{"low":null,"high":null,"point":1.25,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Still $1.25B","sources":[{"url":"https://www.theglobeandmail.com/canada/toronto/article-torontos-port-lands-revitalization-project-proves-different/","outlet":"The Globe and Mail","published_at":"2024-01-27","quote":"This $1.25-billion effort involves, quite literally, building a new river."}]},{"kind":"status","statement_date":"2025-09-30","date_precision":"day","speaker":{"type":"government","name":"City of Toronto"},"new_status":"complete","headline":"Substantially complete","sources":[{"url":"https://www.toronto.ca/legdocs/mmis/2026/ex/bgrd/backgroundfile-284782.pdf","outlet":"City of Toronto (staff report to Executive Committee)","published_at":"2026-02-24","quote":"This report provides an update on the Port Lands Flood Protection project, which reached substantial completion on September 30, 2025."}]}]},{"slug":"qeii-halifax-infirmary","name":"QEII Health Sciences Centre redevelopment (Halifax Infirmary expansion)","short_name":"QEII Halifax Infirmary","sector":"health","jurisdiction":"NS","status":"construction","owner":"Province of Nova Scotia (Plenary PCL Health P3)","url":"https://www.overruns.ca/projects/qeii-halifax-infirmary","first_announced":"2018-10-04","first_price":"$2B","first_price_date":"2018-10-04","first_price_speaker":"Government of Nova Scotia (Premier Stephen McNeil)","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost (all QEII redevelopment sites)","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":"2026-11-19","last_monthly_review":"2026-11-05","summary":"Nova Scotia's replacement for the aging Victoria General hospital: announced in 2016 as a multi-site QEII redevelopment, now centred on a 14-floor acute-care tower at the Halifax Infirmary, built and maintained under a public-private partnership with Plenary PCL Health.","observations":[{"kind":"cost","statement_date":"2018-10-04","date_precision":"day","speaker":{"type":"government","name":"Government of Nova Scotia (Premier Stephen McNeil)"},"cost":{"low":null,"high":null,"point":2,"currency":"CAD","dollar_year":2018,"covers":"capital cost (all QEII redevelopment sites)"},"headline":"About $2B for the whole redevelopment","note":"Covered several sites, including a new cancer centre and the Halifax Infirmary.","sources":[{"url":"https://globalnews.ca/news/4515858/halifax-new-cancer-care-centre/","outlet":"Global News","published_at":"2018-10-04","quote":"The redevelopment of Nova Scotia’s largest hospital complex will cost about $2 billion – the bulk of which will be funded through a public-private partnership, says Premier Stephen McNeil."}]},{"kind":"cost","statement_date":"2022-08-18","date_precision":"day","speaker":{"type":"media_estimate","name":"CBC News (unattributed estimate)"},"cost":{"low":3,"high":null,"point":null,"currency":"CAD","dollar_year":2022,"covers":"capital cost (Halifax Infirmary only)"},"headline":"Infirmary alone: more than $3B","note":"CBC reported the estimate without naming who made it. It covers the infirmary only, so it is not compared with the 2018 total.","sources":[{"url":"https://www.cbc.ca/1.6553888","outlet":"CBC News","published_at":"2022-08-18","quote":"CBC News has learned the estimated price of the Halifax Infirmary redevelopment project has ballooned to more than $3 billion, a number so high that the group bidding on the work has concerns about its ability to get sufficient insurance coverage."}]},{"kind":"cost","statement_date":"2025-02-19","date_precision":"day","speaker":{"type":"government","name":"Government of Nova Scotia"},"cost":{"low":null,"high":null,"point":7.4,"currency":"CAD","dollar_year":2025,"covers":"P3 total to 2061 (infirmary tower construction plus 30 years of maintenance)"},"headline":"P3 deal: $7.4B to 2061","note":"Includes 30 years of maintenance, so it is not compared with construction-only figures.","sources":[{"url":"https://news.novascotia.ca/en/2025/02/19/qeii-halifax-infirmary-expansion-enters-main-construction-phase","outlet":"Government of Nova Scotia","published_at":"2025-02-19","quote":"The project’s total cost between now and 2061 will be $7.4 billion."}]},{"kind":"status","statement_date":"2025-02-19","date_precision":"day","speaker":{"type":"government","name":"Government of Nova Scotia"},"new_status":"construction","headline":"Main construction phase begins","sources":[{"url":"https://news.novascotia.ca/en/2025/02/19/qeii-halifax-infirmary-expansion-enters-main-construction-phase","outlet":"Government of Nova Scotia","published_at":"2025-02-19","quote":"The next phase of construction will soon begin, with the government finalizing an agreement with Plenary PCL Health to build the tower."}]},{"kind":"completion_target","statement_date":"2025-02-19","date_precision":"day","speaker":{"type":"government","name":"Government of Nova Scotia"},"target":{"date":"2031-01-01","precision":"year","event":"first_service"},"headline":"Tower open to patients in fall 2031","sources":[{"url":"https://news.novascotia.ca/en/2025/02/19/qeii-halifax-infirmary-expansion-enters-main-construction-phase","outlet":"Government of Nova Scotia","published_at":"2025-02-19","quote":"The new tower is expected to be fully complete and open to patients and providers in the fall of 2031."}]}]},{"slug":"quebec-city-tramway","name":"Quebec City Tramway (TramCité)","short_name":"Quebec tramway","sector":"transit","jurisdiction":"QC","status":"planning","owner":"Ville de Québec and Government of Quebec (CDPQ Infra as prime contractor since 2024)","url":"https://www.overruns.ca/projects/quebec-city-tramway","first_announced":"2018-03-16","first_price":"$3B","first_price_date":"2018-03-16","first_price_speaker":"Ville de Québec and Government of Quebec","latest_estimate":"$7.6B","latest_estimate_date":"2024-12-16","latest_estimate_speaker":"Government of Quebec (Transport Minister Geneviève Guilbault)","cost_basis":"capital cost","multiple_after_inflation":2.1,"multiple_as_announced":2.53,"delay_months":84,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A planned tramway in Quebec City, first announced by the City and the Quebec government in 2018. Funding comes from the federal, provincial and municipal governments, and CDPQ Infra, the infrastructure arm of Quebec's public pension fund manager, took over planning in 2024.","observations":[{"kind":"cost","statement_date":"2018-03-16","date_precision":"day","speaker":{"type":"government","name":"Ville de Québec and Government of Quebec"},"cost":{"low":null,"high":null,"point":3,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"Announced: $3B tramway network","note":"Announced by Mayor Régis Labeaume and Premier Philippe Couillard.","sources":[{"url":"https://montreal.ctvnews.ca/quebec-city-lays-out-plans-for-3b-tramway-project-1.3846653","outlet":"CTV News Montreal","published_at":"2018-03-16","quote":"Quebec City has laid out its plans for a $3 billion tramway network and wants Ottawa and Quebec to pay for it."}]},{"kind":"cost","statement_date":"2019-08-19","date_precision":"day","speaker":{"type":"government","name":"Government of Canada, Quebec and Ville de Québec"},"cost":{"low":null,"high":null,"point":3.3,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"Cost now $3.3B","sources":[{"url":"https://amp.cbc.ca/news/canada/montreal/quebec-city-tramway-funding-1.5251897","outlet":"CBC News","published_at":"2019-08-19","quote":"The project is expected to cost $3.3 billion in total, with contributions coming from the federal, provincial and municipal governments."}]},{"kind":"completion_target","statement_date":"2019-08-19","date_precision":"day","speaker":{"type":"government","name":"Government of Canada, Quebec and Ville de Québec"},"target":{"date":"2026-01-01","precision":"year","event":"first_service"},"headline":"Service to start in 2026","sources":[{"url":"https://amp.cbc.ca/news/canada/montreal/quebec-city-tramway-funding-1.5251897","outlet":"CBC News","published_at":"2019-08-19","quote":"First announced in 2018, the tramway is scheduled to start running in 2026."}]},{"kind":"cost","statement_date":"2023-04-12","date_precision":"day","speaker":{"type":"media_estimate","name":"Urban Transport Magazine"},"cost":{"low":null,"high":null,"point":3.965,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"About $3.97B before the 2023 revision","note":"The article does not say who made this estimate.","sources":[{"url":"https://www.urban-transport-magazine.com/en/alstom-preferred-bidder-for-tramway-quebec/","outlet":"Urban Transport Magazine","published_at":"2023-04-12","quote":"However, the overall tram project has currently an estimated cost of 3.965 billion Canadian dollars (ca 2.7 billion Euros)."}]},{"kind":"cost","statement_date":"2023-11-01","date_precision":"day","speaker":{"type":"proponent","name":"Ville de Québec (Mayor Bruno Marchand)"},"cost":{"low":null,"high":null,"point":8.365,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"City revises cost to $8.4B","note":"Announced after the only consortium bidding for the infrastructure contract could not meet the deadline or guarantee financing.","sources":[{"url":"https://qcna.qc.ca/tramway-costs-soar-to-8-4-billion-but-marchand-still-all-in/","outlet":"Quebec Chronicle-Telegraph","published_at":"2023-11-27","quote":"Though the projected $8.365-billion cost is more than double the initial estimate five years ago, Mayor Bruno Marchand has said the city is still “all in” on the tramway project."}]},{"kind":"scope_change","statement_date":"2024-06-12","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra (La Caisse)"},"scope":{"description":"CDPQ Infra's CITE plan (June 2024) proposed a central tramway line from Cap-Rouge to Charlesbourg, with the D'Estimauville extension deferred to a later phase, and smaller tram cars and stations to cut cost."},"headline":"Caisse plan phases the line","sources":[{"url":"https://qcna.qc.ca/caisse-proposes-tramway-in-master-plan-for-regional-transit/","outlet":"Quebec Chronicle-Telegraph","published_at":"2024-06-19","quote":"Under the Caisse plan, the D’Estimauville extension would be built in Phase 2, and a line from Charlesbourg to the Lebourgneuf sector in the northwest in Phase 3."}]},{"kind":"cost","statement_date":"2024-12-16","date_precision":"day","speaker":{"type":"government","name":"Government of Quebec (Transport Minister Geneviève Guilbault)"},"cost":{"low":null,"high":null,"point":7.6,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Now $7.6B for the revised line","note":"The minister said the new evaluation includes the costs of the preparatory and related work required to deliver the project. It is for the shorter 19 km line.","sources":[{"url":"https://www.ctvnews.ca/montreal/article/province-announces-quebec-city-tramway-will-cost-76b-should-be-in-service-in-2033/","outlet":"The Canadian Press, via CTV News","published_at":"2024-12-16","quote":"However, she pointed out that the $7.6 billion figure represents the current estimate, and that this figure could change over time."}]},{"kind":"scope_change","statement_date":"2024-12-16","date_precision":"day","speaker":{"type":"government","name":"Government of Quebec, Ville de Québec and CDPQ Infra"},"scope":{"description":"Development agreement with CDPQ Infra as prime contractor. The first line is 19 km from Le Gendre to Charlesbourg, compared with the 23 km Cap-Rouge to Charlesbourg line announced in 2018."},"headline":"Reconfigured as 19 km TramCité line","sources":[{"url":"https://www.railwaygazette.com/urban-rail/tramcite-de-quebec-development-agreement-signed/68022.article","outlet":"Railway Gazette International","published_at":"2024-12-17","quote":"The first line of the tramway, which has been named TramCité, will run 19 km from Le Gendre to Charlesbourg, via Sainte-Foy, Université Laval, Parliament Hill and Saint-Roch with 29 stops and an underground section."},{"url":"https://www.cbc.ca/lite/story/1.4577912","outlet":"CBC News","published_at":"2018-03-16","quote":"The tramway would extend over 23 kilometres, including two sections that would run underground."}]},{"kind":"completion_target","statement_date":"2024-12-16","date_precision":"day","speaker":{"type":"government","name":"Government of Quebec, Ville de Québec and CDPQ Infra"},"target":{"date":"2033-01-01","precision":"year","event":"first_service"},"headline":"Commissioning in 2033","sources":[{"url":"https://www.ctvnews.ca/montreal/article/province-announces-quebec-city-tramway-will-cost-76b-should-be-in-service-in-2033/","outlet":"The Canadian Press, via CTV News","published_at":"2024-12-16","quote":"According to agreements signed between the government, Quebec City and CDPQ Infra, which will be the project's prime contractor, work is due to start in the summer of 2027, with commissioning scheduled for 2033."}]},{"kind":"cost","statement_date":"2026-10-28","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"cost":{"low":null,"high":null,"point":4.8,"currency":"CAD","dollar_year":2024,"covers":"CDPQ Infra's portion only (tramway delivery), not the full $7.6B"},"headline":"CDPQ Infra's share of the $7.6B is $4.8B","note":"CDPQ Infra's written statement says its 2024 estimate covered only the part under its responsibility. Not a new total; the $7.6B (full line, including land and City items) is unchanged.","sources":[{"url":"https://www.lesoleil.com/actualites/actualites-locales/la-capitale/2026/10/28/le-tramway-sera-livre-au-meilleur-cout-assure-cdpq-infra-HGYD4Z3KT5HSNK4AS42E3MAGSM/","outlet":"Le Soleil","published_at":"2026-10-28","quote":"Dans sa déclaration, CDPQ Infra rappelle que son estimation de 2024 couvrait uniquement la portion pour la «réalisation du tramway» sous sa responsabilité, évaluée à 4,8 milliards de dollars."}]}]},{"slug":"regina-bypass","name":"Regina Bypass","short_name":"Regina Bypass","sector":"road_bridge","jurisdiction":"SK","status":"complete","owner":"Government of Saskatchewan, with federal funding","url":"https://www.overruns.ca/projects/regina-bypass","first_announced":"2015-08-05","first_price":"$1.88B","first_price_date":"2015-08-05","first_price_speaker":"Government of Saskatchewan","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"total including financing and 30-year operations and maintenance","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":1,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 61 km highway bypass around the south and east of Regina with 12 overpasses, delivered as a public-private partnership. The total jumped before the contract was signed, then the project finished on time.","observations":[{"kind":"cost","statement_date":"2015-08-05","date_precision":"day","speaker":{"type":"media_estimate","name":"Global News"},"cost":{"low":null,"high":null,"point":1.2,"currency":"CAD","dollar_year":2015,"covers":"as quoted (earlier estimate)"},"headline":"Earlier estimate about $1.2B","note":"Unattributed in the report. The opposition cited other earlier figures ($400M, $700M to $800M); none is yet traced to a government statement.","sources":[{"url":"https://globalnews.ca/news/2149065/regina-bypass-costs-pegged-at-1-88-billion","outlet":"Global News","published_at":"2015-08-05","quote":"Originally estimated to cost approximately $1.2 billion, the new higher price-tag isn’t sitting well with the opposition."}]},{"kind":"cost","statement_date":"2015-08-05","date_precision":"day","speaker":{"type":"government","name":"Government of Saskatchewan"},"cost":{"low":null,"high":null,"point":1.88,"currency":"CAD","dollar_year":2015,"covers":"total including financing and 30-year operations and maintenance"},"headline":"P3 total: $1.88B","sources":[{"url":"https://globalnews.ca/news/2149065/regina-bypass-costs-pegged-at-1-88-billion","outlet":"Global News","published_at":"2015-08-05","quote":"The $1.88 billion investment is expected to cover all project costs – design, construction, finance, operations and maintenance."}]},{"kind":"completion_target","statement_date":"2015-08-05","date_precision":"day","speaker":{"type":"government","name":"Government of Saskatchewan"},"target":{"date":"2019-09-01","precision":"quarter","event":"completion"},"headline":"Finished by fall 2019","sources":[{"url":"https://www.cjme.com/?p=15507","outlet":"CJME","published_at":"2015-08-05","quote":"All construction on the massive project is still scheduled to be finished in the fall of 2019."}]},{"kind":"status","statement_date":"2019-10-29","date_precision":"day","speaker":{"type":"government","name":"Government of Saskatchewan"},"new_status":"complete","headline":"Fully open, on schedule","sources":[{"url":"https://globalnews.ca/news/6092557/regina-bypass-opening","outlet":"Global News","published_at":"2019-10-28","quote":"The Saskatchewan government says the Regina Bypass will officially open to motorists on Tuesday, Oct. 29, as a ceremony marked the grand opening on Monday."}]}]},{"slug":"reseau-express-metropolitain","name":"Réseau express métropolitain (REM)","short_name":"REM (Montreal)","sector":"transit","jurisdiction":"QC","status":"construction","owner":"CDPQ Infra (subsidiary of the Caisse de dépôt et placement du Québec)","url":"https://www.overruns.ca/projects/reseau-express-metropolitain","first_announced":"2016-04-26","first_price":"$5.5B","first_price_date":"2016-04-26","first_price_speaker":"CDPQ Infra","latest_estimate":"$8.3B","latest_estimate_date":"2024-11-14","latest_estimate_speaker":"CDPQ Infra","cost_basis":"capital cost","multiple_after_inflation":1.2,"multiple_as_announced":1.51,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 67-kilometre automated light-rail network linking downtown Montreal to the South Shore, Deux-Montagnes, the West Island and the airport. It is public money: CDPQ Infra is a subsidiary of Quebec's public pension fund manager (the Caisse), and Quebec and Canada contributed funding, including a $1.28B Canada Infrastructure Bank loan.","observations":[{"kind":"cost","statement_date":"2016-04-26","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"cost":{"low":null,"high":null,"point":5.5,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"Announced: about $5.5B","note":"Announced by CDPQ Infra, a subsidiary of Quebec's public pension fund manager. The release said the financing would also require investments from the governments of Quebec and Canada.","sources":[{"url":"https://cdpq.com/en/node/2650","outlet":"CDPQ (La Caisse) news release","published_at":"2016-04-26","quote":"The new network represents an investment of approximately $5.5 billion."}]},{"kind":"completion_target","statement_date":"2016-04-26","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"target":{"date":"2020-01-01","precision":"year","event":"first_service"},"headline":"First trains by end of 2020","sources":[{"url":"https://cdpq.com/en/node/2650","outlet":"CDPQ (La Caisse) news release","published_at":"2016-04-26","quote":"If all these steps are taken successfully, construction is currently expected to begin in the spring of 2017, so that the first trains can be in service towards the end of 2020."}]},{"kind":"cost","statement_date":"2018-02-08","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"cost":{"low":null,"high":null,"point":6.7,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"Cost raised to $6.7B","sources":[{"url":"https://search.open.canada.ca/qpnotes/record/infc%2CINFC-012021-INFC-0015","outlet":"Infrastructure Canada, Question Period Note","published_at":"2020-09-21","quote":"On February 8, 2018, CDPQ Infra announced the selected consortia for the project's two main contracts, as well as an increase of $300 million to the total project cost, which is now $6.7 billion."}]},{"kind":"milestone","statement_date":"2023-07-27","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"milestone":{"title":"First segment (Brossard to Central Station) opens to paying passengers","achieved":true},"headline":"South Shore branch opens to passengers","sources":[{"url":"https://www.theglobeandmail.com/business/article-montreal-light-rail-rem-caisse","outlet":"The Globe and Mail","published_at":"2023-07-27","quote":"The first 17-kilometre branch of the Caisse’s Réseau express métropolitain (REM) light rail line will welcome dignitaries and media Friday and its first paying customers Monday"}]},{"kind":"cost","statement_date":"2023-09-13","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"cost":{"low":null,"high":null,"point":7.95,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"Cost rises to $7.95B","note":"CBC reports CDPQ Infra attributed the increase to the COVID-19 pandemic and inflation.","sources":[{"url":"https://amp.cbc.ca/lite/story/1.6965566","outlet":"CBC News","published_at":"2023-09-13","quote":"Montreal's REM cost rises 26% to $7.95B"}]},{"kind":"cost","statement_date":"2024-11-14","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"cost":{"low":null,"high":null,"point":8.3,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Cost now $8.3B","sources":[{"url":"https://www.cbc.ca/news/canada/montreal/rem-light-speed-north-west-island-1.7383026","outlet":"CBC News","published_at":"2024-11-14","quote":"CDPQ Infra said the total cost of the project is now $8.3 billion, up five per cent from last year."}]},{"kind":"cost","statement_date":"2024-11-20","date_precision":"day","speaker":{"type":"watchdog","name":"Auditor General of Quebec (Guylaine Leclerc)"},"cost":{"low":null,"high":null,"point":9.4,"currency":"CAD","dollar_year":2024,"covers":"total project cost per Auditor General of Quebec"},"headline":"Auditor General: $9.4B","note":"The Auditor General's series starts from $7B in 2018 and is not the same measure as CDPQ Infra's capital cost figures.","sources":[{"url":"https://www.ctvnews.ca/montreal/article/montreal-rem-light-rail-cost-rises-to-94-billion/","outlet":"The Canadian Press, via CTV News","published_at":"2024-11-20","quote":"The estimated cost of the project has risen from $7 billion in 2018 to $9.4 billion in 2024, according to Quebec auditor general Guylaine Leclerc."}]},{"kind":"milestone","statement_date":"2025-11-14","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Prime Minister)"},"milestone":{"title":"Central Station to Deux-Montagnes segment opens","achieved":true},"headline":"Deux-Montagnes branch opens","note":"Passenger service began on Nov. 17, 2025.","sources":[{"url":"https://www.pm.gc.ca/en/node/51838","outlet":"Prime Minister of Canada","published_at":"2025-11-14","quote":"Stretching from downtown Montréal to Deux-Montagnes, the new 30-kilometre extension adds 14 stations to the network, expanding REM service to nearly 50 kilometres and a total of 19 stations."}]},{"kind":"milestone","statement_date":"2026-05-18","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"milestone":{"title":"Anse-à-l'Orme (West Island) branch opens to passengers","achieved":true},"headline":"Anse-à-l'Orme branch opens","sources":[{"url":"https://www.masstransitmag.com/rail/infrastructure/news/55378865/reseau-express-metropolitain-rem-rems-anse-a-lorme-branch-begins-passenger-service","outlet":"Mass Transit","published_at":"2026-05-20","quote":"The Anse-à-l’Orme branch began passenger service on the Réseau express métropolitain on May 18."}]},{"kind":"completion_target","statement_date":"2026-06-08","date_precision":"day","speaker":{"type":"proponent","name":"CDPQ Infra"},"target":{"date":"2027-01-01","precision":"year","event":"full_service"},"headline":"Airport branch due 2027","note":"Three of four segments are in service. The airport station is being built by Aéroports de Montréal.","sources":[{"url":"https://cdpqinfra.com/en/node/9791","outlet":"CDPQ Infra","published_at":"2026-06-08","quote":"The last commissioning is scheduled for 2027 and will extend to the Montréal-Trudeau International Airport."}]}]},{"slug":"roberts-bank-terminal-2","name":"Roberts Bank Terminal 2","short_name":"Roberts Bank T2","sector":"other","jurisdiction":"BC","status":"procurement","owner":"Vancouver Fraser Port Authority (federal port authority under the Canada Marine Act); self-funded","url":"https://www.overruns.ca/projects/roberts-bank-terminal-2","first_announced":"2015-02-06","first_price":"$1.9B","first_price_date":"2015-02-06","first_price_speaker":"Port Metro Vancouver (now Vancouver Fraser Port Authority)","latest_estimate":"$5.9B","latest_estimate_date":"2026-10-30","latest_estimate_speaker":"Government of Canada (Transport Canada)","cost_basis":"capital cost","multiple_after_inflation":2.26,"multiple_as_announced":3.11,"delay_months":132,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A new three-berth container terminal on reclaimed land at Roberts Bank in Delta, B.C., proposed by the Vancouver Fraser Port Authority, a federal port authority. Approved in 2023; construction is planned from 2028.","observations":[{"kind":"cost","statement_date":"2015-02-06","date_precision":"day","speaker":{"type":"proponent","name":"Port Metro Vancouver (now Vancouver Fraser Port Authority)"},"cost":{"low":null,"high":null,"point":1.9,"currency":"CAD","dollar_year":2013,"covers":"capital cost"},"headline":"About $1.9B","note":"From the environmental impact statement, in 2013 dollars.","sources":[{"url":"https://iaac-aeic.gc.ca/050/documents/p80054/101352E.pdf","outlet":"Port Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates)","published_at":"2015-02-06","quote":"The estimated economic cost is approximately $1.9 billion for building the new marine terminal, widening the causeway, dredging the dredge basin, expanding the existing tug basin, and testing and training on the container handling equipment."}]},{"kind":"completion_target","statement_date":"2015-02-06","date_precision":"day","speaker":{"type":"proponent","name":"Port Metro Vancouver"},"target":{"date":"2024-01-01","precision":"year","event":"first_service"},"headline":"Fully operational from 2024","sources":[{"url":"https://iaac-aeic.gc.ca/050/documents/p80054/101352E.pdf","outlet":"Port Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates)","published_at":"2015-02-06","quote":"The Project would have the capacity to be fully operational beginning in 2024."}]},{"kind":"completion_target","statement_date":"2015-02-06","date_precision":"day","speaker":{"type":"proponent","name":"Port Metro Vancouver"},"target":{"date":"2023-01-01","precision":"year","event":"completion"},"headline":"Construction to finish in 2023","sources":[{"url":"https://iaac-aeic.gc.ca/050/documents/p80054/101352E.pdf","outlet":"Port Metro Vancouver, RBT2 Environmental Impact Statement, Appendix 20-A (Golder Associates)","published_at":"2015-02-06","quote":"This equipment is projected to be installed in the last construction year, 2023, and there will be on-site training and start-up measures undertaken by the Terminal Operator Concessionaire during this year too."}]},{"kind":"status","statement_date":"2023-04-20","date_precision":"day","speaker":{"type":"government","name":"Government of Canada"},"new_status":"approved","headline":"Federal approval","sources":[{"url":"https://www.cbc.ca/news/canada/british-columbia/delta-container-expansion-approval-1.6817357","outlet":"CBC News","published_at":"2023-04-20","quote":"The federal government has given the OK for a major new container terminal on Canada's West Coast"}]},{"kind":"cost","statement_date":"2023-04-20","date_precision":"day","speaker":{"type":"media_estimate","name":"Daily Hive (figure not attributed)"},"cost":{"low":2,"high":null,"point":null,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"'Over $2 billion'","note":"The article doesn't say who estimated it, so it isn't used as the official figure.","sources":[{"url":"https://dailyhive.com/vancouver/roberts-bank-terminal-2-vancouver-delta-approved","outlet":"Daily Hive","published_at":"2023-04-20","quote":"The estimated cost of building Roberts Bank Terminal 2 is over $2 billion, with the project self-funded by the port authority."}]},{"kind":"cost","statement_date":"2023-04-20","date_precision":"day","speaker":{"type":"media_estimate","name":"The Globe and Mail; Global News"},"cost":{"low":null,"high":null,"point":3.5,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"Widely reported: $3.5B","note":"Reported at federal approval without saying who estimated it, so not used as the official figure.","sources":[{"url":"https://www.theglobeandmail.com/business/article-ottawa-approves-35-billion-bc-container-terminal/","outlet":"The Globe and Mail","published_at":"2023-04-20","quote":"The federal government has approved the Port of Vancouver’s proposed $3.5-billion container terminal, saying the project will spur economic growth while complying with environmental rules."},{"url":"https://globalnews.ca/news/9640216/ottawa-greenlights-roberts-bank-terminal-project/amp","outlet":"Global News","published_at":"2023-04-20","quote":"Private investments and the Vancouver Fraser Port Authority will fund its estimated $3.5 billion cost."}]},{"kind":"completion_target","statement_date":"2025-05-14","date_precision":"day","speaker":{"type":"proponent","name":"Vancouver Fraser Port Authority"},"target":{"date":"2028-01-01","precision":"year","event":"construction_start"},"headline":"Major construction to start in 2028","sources":[{"url":"https://www.delta-optimist.com/local-news/roberts-bank-terminal-2-project-moving-closer-to-reality-10662481","outlet":"Delta Optimist","published_at":"2025-05-14","quote":"Construction mobilization and early works are expected to occur in 2027, with major land reclamation works expected to begin in 2028."}]},{"kind":"milestone","statement_date":"2026-07-20","date_precision":"day","speaker":{"type":"proponent","name":"Vancouver Fraser Port Authority"},"milestone":{"title":"Preferred proponent selected for landmass and wharf","achieved":true},"headline":"TerraMarine joint venture picked to build the landmass and wharf","sources":[{"url":"https://finance.yahoo.com/economy/articles/terramarine-jv-lead-roberts-bank-094932858.html","outlet":"Yahoo Finance","published_at":"2026-07-20","quote":"The Vancouver Fraser Port Authority has selected the TerraMarine joint venture (JV) as the preferred proponent for the landmass and wharf infrastructure component of the Roberts Bank Terminal 2 Project in Delta city of British Columbia."}]},{"kind":"completion_target","statement_date":"2026-07-20","date_precision":"day","speaker":{"type":"proponent","name":"Vancouver Fraser Port Authority"},"target":{"date":"2034-01-01","precision":"year","event":"completion"},"headline":"Completion now targeted for early 2034","sources":[{"url":"https://finance.yahoo.com/economy/articles/terramarine-jv-lead-roberts-bank-094932858.html","outlet":"Yahoo Finance","published_at":"2026-07-20","quote":"Completion is targeted for early 2034, and terminal operations are anticipated to begin in the mid-2030s."}]},{"kind":"cost","statement_date":"2026-10-30","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Transport Canada)"},"cost":{"low":null,"high":null,"point":5.9,"currency":"CAD","dollar_year":2026,"covers":"capital cost"},"headline":"Federal release: a $5.9B investment","sources":[{"url":"https://voiceonline.com/roberts-bank-terminal-2-listed-as-a-project-of-national-interest/","outlet":"Indo-Canadian Voice (Government of Canada news release, reprinted in full)","published_at":"2026-10-30","quote":"Through collaboration with the Major Projects Office, the VFPA, and other federal partners, RBT2, a $5.9 billion investment in Canada’s trade infrastructure, is on a viable path to Final Investment Decision (FID) by mid-2027."}]},{"kind":"completion_target","statement_date":"2026-10-30","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Transport Canada)"},"target":{"date":"2035-01-01","precision":"year","event":"first_service"},"headline":"Commercial operations targeted for 2035","sources":[{"url":"https://voiceonline.com/roberts-bank-terminal-2-listed-as-a-project-of-national-interest/","outlet":"Indo-Canadian Voice (Government of Canada news release, reprinted in full)","published_at":"2026-10-30","quote":"Friday’s listing decision provides upfront certainty on the remaining applicable federal regulatory authorizations, and accelerates the project’s commercial operations by up to four years, from 2039 to 2035."}]},{"kind":"milestone","statement_date":"2026-10-30","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Transport Canada)"},"milestone":{"title":"Listed as a project of national interest under the Building Canada Act","achieved":true},"headline":"Listed as a project of national interest","sources":[{"url":"https://dailyhive.com/vancouver/roberts-bank-terminal-2-superport-canada-national-interest-status","outlet":"Daily Hive","published_at":"2026-10-30","quote":"The Government of Canada announced the formal designation today, noting that it could bring the superport into operation in 2035 instead of 2039 by speeding up the remaining federal approvals."}]}]},{"slug":"saaqclic","name":"SAAQclic (SAAQ digital transformation, CASA program)","short_name":"SAAQclic","sector":"it","jurisdiction":"QC","status":"operational","owner":"Société de l'assurance automobile du Québec (Government of Quebec)","url":"https://www.overruns.ca/projects/saaqclic","first_announced":"2015-04-01","first_price":"$200M","first_price_date":"2015-04-01","first_price_speaker":"SAAQ (CEO Nathalie Tremblay) and Quebec Transport Minister Robert Poëti","latest_estimate":"$638M","latest_estimate_date":"2017-06-01","latest_estimate_speaker":"SAAQ","cost_basis":"10-year program cost","multiple_after_inflation":3.1,"multiple_as_announced":3.19,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"The Quebec auto insurance board's IT overhaul, including the SAAQclic online platform. Its 2023 launch caused months of disruption and led to a public inquiry, the Gallant commission.","observations":[{"kind":"cost","statement_date":"2015-04-01","date_precision":"month","speaker":{"type":"proponent","name":"SAAQ (CEO Nathalie Tremblay) and Quebec Transport Minister Robert Poëti"},"cost":{"low":null,"high":null,"point":0.2,"currency":"CAD","dollar_year":2015,"covers":"10-year program cost"},"headline":"First estimate: $200M over 10 years","note":"From the SAAQ's April 2015 request to the Treasury Board, made public at the Gallant inquiry in 2025.","sources":[{"url":"https://www.noovo.info/nouvelle/la-saaq-evaluait-au-depart-a-200-m-sa-transformation-technologique.html","outlet":"La Presse canadienne, via Noovo Info","published_at":"2025-05-01","quote":"Selon la demande signée par la PDG de la SAAQ et le ministre des Transports de l'époque, Nathalie Tremblay et Robert Poëti, la modernisation des systèmes informatiques de l'organisation était évaluée à 200 millions $ sur 10 ans."}]},{"kind":"cost","statement_date":"2017-06-01","date_precision":"year","speaker":{"type":"proponent","name":"SAAQ"},"cost":{"low":null,"high":null,"point":0.638,"currency":"CAD","dollar_year":2017,"covers":"10-year program cost"},"headline":"Budget set at $638M","sources":[{"url":"https://www.cbc.ca/lite/story/1.7463880","outlet":"CBC News","published_at":"2025-02-20","quote":"Leclerc found that in 2017, when the SAAQ began an attempt to digitize its services, it budgeted $638 million over a 10-year period to, among other things, build the online SAAQclic platform."}]},{"kind":"status","statement_date":"2023-02-20","date_precision":"year","speaker":{"type":"proponent","name":"SAAQ"},"new_status":"operational","headline":"SAAQclic launched, with major disruptions","sources":[{"url":"https://www.insurancebusinessmag.com/ca/news/breaking-news/inquiry-reveals-huge-costs-from-quebecs-auto-insurance-overhaul-533702.aspx","outlet":"Insurance Business","published_at":"2025-04-29","quote":"Instead, its launch in 2023 led to widespread service disruptions, including long wait times at in-person service centres."}]},{"kind":"cost","statement_date":"2025-02-20","date_precision":"day","speaker":{"type":"watchdog","name":"Auditor General of Quebec (Guylaine Leclerc)"},"cost":{"low":1.1,"high":null,"point":null,"currency":"CAD","dollar_year":2025,"covers":"10-year program cost"},"headline":"Auditor General: over $1.1B","sources":[{"url":"https://www.cbc.ca/lite/story/1.7463880","outlet":"CBC News","published_at":"2025-02-20","quote":"The true cost of the SAAQ's digitization attempt is now likely to climb over $1.1 billion, Leclerc found."}]}]},{"slug":"scarborough-subway-extension","name":"Scarborough Subway Extension (Line 2 East Extension)","short_name":"Scarborough subway","sector":"transit","jurisdiction":"ON","status":"construction","owner":"Metrolinx (Province of Ontario), with federal funding","url":"https://www.overruns.ca/projects/scarborough-subway-extension","first_announced":"2013-10-03","first_price":"$3.56B","first_price_date":"2013-10-03","first_price_speaker":"City of Toronto and TTC","latest_estimate":"$10.2B+","latest_estimate_date":"2025-06-24","latest_estimate_speaker":"Metrolinx","cost_basis":"project cost","multiple_after_inflation":2.14,"multiple_as_announced":2.87,"delay_months":84,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 7.8 km, three-stop extension of Toronto's Line 2 subway into Scarborough, replacing the Scarborough RT. Chosen by city council over a funded LRT in 2013, cut to one stop, then taken over by the province in 2019.","observations":[{"kind":"cost","statement_date":"2013-10-03","date_precision":"year","speaker":{"type":"government","name":"City of Toronto and TTC"},"cost":{"low":null,"high":null,"point":3.56,"currency":"CAD","dollar_year":2013,"covers":"project cost"},"headline":"Three-stop subway first estimated at $3.56B","note":"City figure in year-of-expenditure dollars (it allows for future inflation). Council chose the subway over a funded LRT.","sources":[{"url":"https://www.cp24.com/news/2025/06/24/scarborough-extension-cost-now-102-billion-nearly-double-2019-estimate/","outlet":"CTV News Toronto, via CP24","published_at":"2025-06-24","quote":"The initial estimate for building the three-station project when it was first proposed back in 2013 was $3.56 billion."}]},{"kind":"completion_target","statement_date":"2013-10-03","date_precision":"year","speaker":{"type":"government","name":"TTC"},"target":{"date":"2023-01-01","precision":"year","event":"first_service"},"headline":"Opening planned for 2023","note":"From the TTC's capital plans, as analysed by transit writer Steve Munro.","sources":[{"url":"https://stevemunro.ca/2017/03/03/scarborough-subway-cost-rises-again-ii/","outlet":"Steve Munro","published_at":"2017-03-03","quote":"This corresponds to the original scheme to open the line in 2023, but not to the current fleet plan."}]},{"kind":"scope_change","statement_date":"2017-03-28","date_precision":"year","speaker":{"type":"government","name":"Toronto City Council"},"scope":{"description":"Cut back to a single stop at Scarborough Town Centre."},"headline":"Cut to one stop","sources":[{"url":"https://blogto.com/city/2019/04/doug-ford-three-stop-scarborough-subway-extension-revival","outlet":"blogTO","published_at":"2019-04-10","quote":"And then how, in 2017, they voted again to scale the extension back to just one station?"}]},{"kind":"scope_change","statement_date":"2019-04-10","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario"},"scope":{"description":"The province took over the project and restored three stops (Lawrence East, Scarborough Town Centre, McCowan)."},"headline":"Province takes over, back to three stops","sources":[{"url":"https://blogto.com/city/2019/04/doug-ford-three-stop-scarborough-subway-extension-revival","outlet":"blogTO","published_at":"2019-04-10","quote":"Set to open sometime \"before 2030,\" the new extension will cost $5.5 billion to build and will include stops at Lawrence East Station, Scarborough Town Centre Station and McCowan Station, according to the province."}]},{"kind":"cost","statement_date":"2019-04-10","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario"},"cost":{"low":null,"high":null,"point":5.5,"currency":"CAD","dollar_year":2019,"covers":"construction cost"},"headline":"Province: $5.5B","note":"Metrolinx later said this figure covered construction only.","sources":[{"url":"https://blogto.com/city/2019/04/doug-ford-three-stop-scarborough-subway-extension-revival","outlet":"blogTO","published_at":"2019-04-10","quote":"Set to open sometime \"before 2030,\" the new extension will cost $5.5 billion to build and will include stops at Lawrence East Station, Scarborough Town Centre Station and McCowan Station, according to the province."}]},{"kind":"completion_target","statement_date":"2019-04-10","date_precision":"day","speaker":{"type":"government","name":"Province of Ontario"},"target":{"date":"2030-01-01","precision":"year","event":"first_service"},"headline":"Opening \"before 2030\"","note":"Stored as 2030, which gives the project the benefit of the doubt.","sources":[{"url":"https://blogto.com/city/2019/04/doug-ford-three-stop-scarborough-subway-extension-revival","outlet":"blogTO","published_at":"2019-04-10","quote":"Set to open sometime \"before 2030,\" the new extension will cost $5.5 billion to build and will include stops at Lawrence East Station, Scarborough Town Centre Station and McCowan Station, according to the province."}]},{"kind":"cost","statement_date":"2025-06-24","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"cost":{"low":10.2,"high":null,"point":null,"currency":"CAD","dollar_year":2025,"covers":"project cost"},"headline":"Metrolinx: more than $10.2B","sources":[{"url":"https://www.cp24.com/news/2025/06/24/scarborough-extension-cost-now-102-billion-nearly-double-2019-estimate/","outlet":"CTV News Toronto, via CP24","published_at":"2025-06-24","quote":"Scarborough’s subway extension will cost more than $10.2 billion, nearly double the initial estimate announced by the province six years ago, according to updated figures from Metrolinx."}]},{"kind":"completion_target","statement_date":"2025-06-24","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"target":{"date":"2030-01-01","precision":"year","event":"first_service"},"headline":"Service expected in 2030","sources":[{"url":"https://www.cp24.com/news/2025/06/24/scarborough-extension-cost-now-102-billion-nearly-double-2019-estimate/","outlet":"CTV News Toronto, via CP24","published_at":"2025-06-24","quote":"The transit line isn’t expected to be up and running until 2030, but a progress report on the project says the tunnel’s boring machine, dubbed “Diggy Scardust,” is progressing well and averaging 12 metres per day."}]}]},{"slug":"site-c-dam","name":"Site C dam","short_name":"Site C dam","sector":"hydro","jurisdiction":"BC","status":"complete","owner":"BC Hydro (Province of British Columbia)","url":"https://www.overruns.ca/projects/site-c-dam","first_announced":"2007-01-01","first_price":"up to $6.6B","first_price_date":"2007-01-01","first_price_speaker":"BC Hydro (feasibility study)","latest_estimate":"$16B","latest_estimate_date":"2021-02-26","latest_estimate_speaker":"Government of British Columbia","cost_basis":"capital cost","multiple_after_inflation":1.91,"multiple_as_announced":2.42,"delay_months":9,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 1,100-megawatt hydroelectric dam on the Peace River near Fort St. John, B.C., built by the provincial Crown utility BC Hydro. Renamed the John Horgan Dam in 2026.","observations":[{"kind":"cost","statement_date":"2007-01-01","date_precision":"year","speaker":{"type":"proponent","name":"BC Hydro (feasibility study)"},"cost":{"low":null,"high":6.6,"point":null,"currency":"CAD","dollar_year":2007,"covers":"capital cost"},"headline":"Feasibility study: up to $6.6B","note":"BC Hydro's 2007 feasibility work, the first figure for the revived project. A 1980s version of the dam was rejected in 1983 and is treated as a separate proposal.","sources":[{"url":"https://www.cbc.ca/news/canada/british-columbia/bc-hydro-reservoir-site-c-1.7304535","outlet":"The Canadian Press, via CBC News","published_at":"2024-08-25","quote":"Liberal government and has seen cost estimates spike from up to $6.6 billion in 2007 to $16 billion in 2021."}]},{"kind":"cost","statement_date":"2011-05-20","date_precision":"day","speaker":{"type":"proponent","name":"BC Hydro"},"cost":{"low":null,"high":null,"point":7.9,"currency":"CAD","dollar_year":2011,"covers":"capital cost"},"headline":"$7.9B in regulatory filings","sources":[{"url":"https://www.princegeorgecitizen.com/local-news/price-of-site-c-dam-in-northern-bc-increased-to-79-b-3701519","outlet":"Prince George Citizen","published_at":"2011-05-20","quote":"Hydro has filed submissions with the provincial and federal regulators on its Site C Dam project in northern B.C. which comes with a $2-billion increased price tag to $7.9 billion."}]},{"kind":"cost","statement_date":"2014-12-16","date_precision":"day","speaker":{"type":"government","name":"Government of British Columbia (Premier Christy Clark)"},"cost":{"low":null,"high":null,"point":8.8,"currency":"CAD","dollar_year":2014,"covers":"capital cost"},"headline":"Approved at $8.8B","note":"Includes a $440M project reserve on top of the $8.335B estimate.","sources":[{"url":"https://www.cbc.ca/lite/story/1.2874433","outlet":"CBC News","published_at":"2014-12-16","quote":"B.C. has approved the $8.8 billion Site C dam — a massive hydroelectric project that would flood a large area of the Peace River Valley in northeastern B.C."}]},{"kind":"completion_target","statement_date":"2014-12-16","date_precision":"day","speaker":{"type":"government","name":"Government of British Columbia"},"target":{"date":"2024-11-01","precision":"month","event":"completion"},"headline":"Completion set for November 2024","note":"The schedule set at approval in 2014.","sources":[{"url":"https://dailyhive.com/vancouver/bc-ndp-site-c-review-decision-december-2017","outlet":"Daily Hive","published_at":"2017-12-12","quote":"The BCUC report, released last month, warned that the project is unlikely to meet its November 2024 completion and could cost 20% to 50% more when fully complete."}]},{"kind":"cost","statement_date":"2017-12-11","date_precision":"day","speaker":{"type":"government","name":"Government of British Columbia (Premier John Horgan)"},"cost":{"low":null,"high":null,"point":10.7,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"New government continues the dam at $10.7B","sources":[{"url":"https://dailyhive.com/vancouver/bc-ndp-site-c-review-decision-december-2017","outlet":"Daily Hive","published_at":"2017-12-12","quote":"As well, the latest official project budget has risen from $8.8 billion to $10.7 billion."}]},{"kind":"cost","statement_date":"2021-02-26","date_precision":"day","speaker":{"type":"government","name":"Government of British Columbia"},"cost":{"low":null,"high":null,"point":16,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"$16B and a year late","note":"Blamed on geotechnical problems on the dam's right bank and the pandemic.","sources":[{"url":"https://globalnews.ca/news/7664332/site-c-dam-decision","outlet":"Global News","published_at":"2021-02-26","quote":"The B.C. government reported on Friday the project will now cost an estimated $16 billion to complete, up from the previous estimate of $10.7 billion."}]},{"kind":"completion_target","statement_date":"2021-02-26","date_precision":"day","speaker":{"type":"government","name":"Government of British Columbia"},"target":{"date":"2025-01-01","precision":"year","event":"completion"},"headline":"Completion pushed to 2025","sources":[{"url":"https://globalnews.ca/news/7664332/site-c-dam-decision","outlet":"Global News","published_at":"2021-02-26","quote":"The project is now expected to be completed in 2025, a year after its original completion date."}]},{"kind":"status","statement_date":"2025-08-09","date_precision":"day","speaker":{"type":"proponent","name":"BC Hydro"},"new_status":"complete","headline":"All six generating units in service","sources":[{"url":"https://www.bchydro.com/news/press_centre/news_releases/2025/site-c-full-operation.html","outlet":"BC Hydro","published_at":"2025-08-09","quote":"With all six units now in service, Site C has the capacity to generate more than 1,100 megawatts of electricity, and enough energy to reliably power about 500,000 homes annually."}]}]},{"slug":"spadina-subway-extension","name":"Toronto-York Spadina Subway Extension (Line 1)","short_name":"Spadina subway extension","sector":"transit","jurisdiction":"ON","status":"operational","owner":"TTC (City of Toronto), York Region, Province of Ontario, Government of Canada","url":"https://www.overruns.ca/projects/spadina-subway-extension","first_announced":"2008-03-01","first_price":"$2.09B","first_price_date":"2008-03-01","first_price_speaker":"TTC","latest_estimate":"$3.18B","latest_estimate_date":"2016-01-15","latest_estimate_speaker":"TTC (CEO Andy Byford)","cost_basis":"capital cost","multiple_after_inflation":1.29,"multiple_as_announced":1.52,"delay_months":24,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"An 8.6 km, six-station extension of Toronto's Line 1 subway from Downsview to Vaughan Metropolitan Centre, built by the TTC with federal, provincial, Toronto and York Region money.","observations":[{"kind":"cost","statement_date":"2008-03-01","date_precision":"month","speaker":{"type":"government","name":"TTC"},"cost":{"low":null,"high":null,"point":2.09,"currency":"CAD","dollar_year":2006,"covers":"capital cost"},"headline":"Estimated at $2.09B (2006 dollars)","note":"From the TTC's March 2008 report on project delivery. The same report put the cost at $2.633B in year-of-expenditure dollars.","sources":[{"url":"https://stevemunro.ca/2015/03/14/how-much-will-the-spadina-subway-extension-cost/","outlet":"Steve Munro (quoting the TTC's March 2008 report)","published_at":"2015-03-14","quote":"The estimated cost of the Project, unescalated (July 2006$), is $2.090 billion."}]},{"kind":"completion_target","statement_date":"2008-03-01","date_precision":"year","speaker":{"type":"government","name":"TTC"},"target":{"date":"2015-01-01","precision":"year","event":"first_service"},"headline":"Opening expected 2015","sources":[{"url":"https://stevemunro.ca/2015/03/14/how-much-will-the-spadina-subway-extension-cost/","outlet":"Steve Munro","published_at":"2015-03-14","quote":"The line was originally expected to open in 2015, even in early rosy estimates before the Pan Am Games, but now will not be in service until 2017."}]},{"kind":"completion_target","statement_date":"2014-12-01","date_precision":"month","speaker":{"type":"government","name":"TTC (CEO's report)"},"target":{"date":"2016-09-01","precision":"quarter","event":"first_service"},"headline":"Now fall 2016","sources":[{"url":"https://stevemunro.ca/2015/03/14/how-much-will-the-spadina-subway-extension-cost/","outlet":"Steve Munro (quoting the TTC CEO's report)","published_at":"2015-03-14","quote":"The in-service date is targeted for the fall of 2016 however the project is facing a serious schedule challenge."}]},{"kind":"cost","statement_date":"2016-01-15","date_precision":"day","speaker":{"type":"government","name":"TTC (CEO Andy Byford)"},"cost":{"low":null,"high":null,"point":3.184,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"Budget now $3.18B","sources":[{"url":"https://amp.cbc.ca/news/canada/toronto/spadina-subway-cost-1.3404472","outlet":"CBC News","published_at":"2016-01-15","quote":"Total budget now $3.184 billion."}]},{"kind":"completion_target","statement_date":"2016-01-15","date_precision":"day","speaker":{"type":"government","name":"TTC (CEO Andy Byford)"},"target":{"date":"2017-12-31","precision":"day","event":"first_service"},"headline":"Now December 31, 2017","sources":[{"url":"https://amp.cbc.ca/news/canada/toronto/spadina-subway-cost-1.3404472","outlet":"CBC News","published_at":"2016-01-15","quote":"BREAKING: TTC says an additional $400 million needed to complete York-Spadina extension by Dec 31 2017."}]},{"kind":"status","statement_date":"2017-12-17","date_precision":"day","speaker":{"type":"government","name":"TTC"},"new_status":"operational","headline":"Opened to the public","sources":[{"url":"https://c3.vaughan.ca/news/2017/12-December/clip12-18-4.html","outlet":"CP24, via City of Vaughan news clippings","published_at":"2017-12-17","quote":"Toronto-York Spadina Subway Extension officially opens to public Cp24.com Codi Wilson Dec. 17, 2017 A new subway that will take commuters from Vaughan to Union Station in an estimated 42 minutes officially opened to the public today."}]}]},{"slug":"sturgeon-refinery","name":"Sturgeon Refinery (North West Redwater)","short_name":"Sturgeon Refinery","sector":"energy","jurisdiction":"AB","status":"operational","owner":"North West Redwater Partnership (Province of Alberta via APMC 50%, Canadian Natural 50%)","url":"https://www.overruns.ca/projects/sturgeon-refinery","first_announced":"2012-11-08","first_price":"$5.7B","first_price_date":"2012-11-08","first_price_speaker":"North West Redwater Partnership","latest_estimate":"$8.5B","latest_estimate_date":"2013-12-01","latest_estimate_speaker":"North West Redwater Partnership","cost_basis":"capital cost","multiple_after_inflation":1.48,"multiple_as_announced":1.49,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A bitumen refinery near Redwater, Alberta, built by the North West Redwater Partnership under a deal in which the province supplies most of the bitumen and pays processing tolls for decades. Alberta became a 50 per cent owner in 2021.","observations":[{"kind":"cost","statement_date":"2012-11-08","date_precision":"day","speaker":{"type":"proponent","name":"North West Redwater Partnership"},"cost":{"low":null,"high":null,"point":5.7,"currency":"CAD","dollar_year":2012,"covers":"capital cost"},"headline":"Sanctioned: $5.7B","sources":[{"url":"https://amp.cbc.ca/news/canada/edmonton/alberta-takes-50-per-cent-equity-stake-in-sturgeon-refinery-1.6090845","outlet":"CBC News","published_at":"2021-07-05","quote":"The cost of building the refinery was estimated at $5.7 billion when construction started in 2013 and ended up at $10.1 billion last year."}]},{"kind":"cost","statement_date":"2013-12-01","date_precision":"month","speaker":{"type":"proponent","name":"North West Redwater Partnership"},"cost":{"low":null,"high":null,"point":8.5,"currency":"CAD","dollar_year":2013,"covers":"capital cost"},"headline":"Raised to $8.5B","note":"The province's estimate of the tolls it would pay to have its bitumen refined rose from $19B to $26B the following June.","sources":[{"url":"https://www.cbc.ca/news/canada/calgary/alberta-bitumen-sturgeon-refinery-nwrp-1.5718044","outlet":"CBC News (opinion, Andrew Leach)","published_at":"2020-09-14","quote":"In December of 2013, the expected capital cost of the project was increased from $5.7 billion to $8.5 billion, and the following June, the government's estimate of the tolls we would all pay to refine our bitumen was increased from $19 billion to $26 billion."}]},{"kind":"completion_target","statement_date":"2016-01-05","date_precision":"day","speaker":{"type":"proponent","name":"North West Redwater Partnership"},"target":{"date":"2017-01-01","precision":"year","event":"first_service"},"headline":"Slated to open in 2017","sources":[{"url":"https://www.cbc.ca/lite/story/1.3389425","outlet":"CBC News","published_at":"2016-01-05","quote":"It's slated to open in 2017."}]},{"kind":"cost","statement_date":"2017-06-29","date_precision":"day","speaker":{"type":"other","name":"AltaCorp Capital (analyst)"},"cost":{"low":null,"high":null,"point":9.3,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"Analyst: $9.3B","sources":[{"url":"https://www.oilsandsmagazine.com/news/2017/6/29/sturgeon-bitumen-upgrader-refinery-capital-costs-revision","outlet":"Oil Sands Magazine","published_at":"2017-06-29","quote":"According to AltaCorp Capital, the latest price tag for the Sturgeon Refinery is now $9.3 billion, up another $800 million from previous estimates."}]},{"kind":"cost","statement_date":"2020-12-31","date_precision":"year","speaker":{"type":"media_estimate","name":"CBC News"},"cost":{"low":null,"high":null,"point":10.1,"currency":"CAD","dollar_year":2020,"covers":"capital cost"},"headline":"Ended up at $10.1B","note":"Reported by CBC without attribution, so shown as a media figure.","sources":[{"url":"https://amp.cbc.ca/news/canada/edmonton/alberta-takes-50-per-cent-equity-stake-in-sturgeon-refinery-1.6090845","outlet":"CBC News","published_at":"2021-07-05","quote":"The cost of building the refinery was estimated at $5.7 billion when construction started in 2013 and ended up at $10.1 billion last year."}]},{"kind":"milestone","statement_date":"2021-07-05","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta"},"milestone":{"title":"Alberta takes a 50 per cent ownership stake","achieved":true},"headline":"Province becomes half-owner","sources":[{"url":"https://amp.cbc.ca/news/canada/edmonton/alberta-takes-50-per-cent-equity-stake-in-sturgeon-refinery-1.6090845","outlet":"CBC News","published_at":"2021-07-05","quote":"The deal announced Monday has North West Refining transferring its ownership stake to the government of Alberta, which gives the province an equal vote in the operations."}]}]},{"slug":"surrey-langley-skytrain","name":"Surrey Langley SkyTrain (Expo Line extension)","short_name":"Surrey-Langley SkyTrain","sector":"transit","jurisdiction":"BC","status":"construction","owner":"Province of British Columbia, with federal funding and TransLink","url":"https://www.overruns.ca/projects/surrey-langley-skytrain","first_announced":"2019-07-19","first_price":"$3.12B","first_price_date":"2019-07-19","first_price_speaker":"TransLink (CEO Kevin Desmond)","latest_estimate":"$6B","latest_estimate_date":"2024-08-15","latest_estimate_speaker":"Province of British Columbia","cost_basis":"capital cost (full line to Langley)","multiple_after_inflation":1.62,"multiple_as_announced":1.92,"delay_months":10,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 16 km, eight-station extension of the Expo Line from King George station in Surrey to Langley City. It replaced a planned Surrey light rail line in 2018.","observations":[{"kind":"cost","statement_date":"2019-07-19","date_precision":"day","speaker":{"type":"proponent","name":"TransLink (CEO Kevin Desmond)"},"cost":{"low":null,"high":null,"point":3.12,"currency":"CAD","dollar_year":2019,"covers":"capital cost (full line to Langley)"},"headline":"TransLink: $3.12B to Langley","sources":[{"url":"https://www.cbc.ca/1.5218178","outlet":"CBC News","published_at":"2019-07-19","quote":"TransLink CEO Kevin Desmond said Friday a full-length Surrey Langley SkyTrain would cost $3.12 billion but only $1.6 billion is currently available."}]},{"kind":"completion_target","statement_date":"2019-07-19","date_precision":"day","speaker":{"type":"proponent","name":"TransLink"},"target":{"date":"2025-01-01","precision":"year","event":"first_service"},"headline":"First section to open 2025","sources":[{"url":"https://www.cbc.ca/1.5218178","outlet":"CBC News","published_at":"2019-07-19","quote":"Construction could begin in early 2022, with service beginning in 2025."}]},{"kind":"cost","statement_date":"2021-08-31","date_precision":"day","speaker":{"type":"proponent","name":"TransLink"},"cost":{"low":null,"high":null,"point":3.94,"currency":"CAD","dollar_year":2021,"covers":"capital cost (full line to Langley)"},"headline":"Budget $3.94B","sources":[{"url":"https://www.castanetkamloops.net/news/BC/346475/Surrey-Langley-SkyTrain-extension-wont-open-until-2028","outlet":"Castanet","published_at":"2021-09-22","quote":"In the most recent report, issued Aug. 31, noted funding is still being sought for the project, currently estimated to have a $3.94 billion budget."}]},{"kind":"cost","statement_date":"2022-07-14","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia (business case)"},"cost":{"low":null,"high":null,"point":4.01,"currency":"CAD","dollar_year":2022,"covers":"capital cost (full line to Langley)"},"headline":"Business case approved: $4.01B","sources":[{"url":"https://www.ctvnews.ca/vancouver/article/cost-of-surrey-langley-skytrain-extension-balloons-to-6b/","outlet":"CTV News","published_at":"2024-08-16","quote":"The price tag of the expansion is now estimated at $5.996 billion, up from the $4.01 billion outlined in the 2022 business case for the project."}]},{"kind":"completion_target","statement_date":"2022-07-14","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia (Transportation Minister Rob Fleming)"},"target":{"date":"2028-01-01","precision":"year","event":"completion"},"headline":"Full line by 2028","sources":[{"url":"https://www.cbc.ca/1.6521120","outlet":"The Canadian Press, via CBC News","published_at":"2022-07-14","quote":"Rob Fleming says the project is expected to be completed by 2028, two years earlier than originally planned."}]},{"kind":"cost","statement_date":"2024-08-15","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"cost":{"low":null,"high":null,"point":5.996,"currency":"CAD","dollar_year":2024,"covers":"capital cost (full line to Langley)"},"headline":"Now $6B","sources":[{"url":"https://www.ctvnews.ca/vancouver/article/cost-of-surrey-langley-skytrain-extension-balloons-to-6b/","outlet":"CTV News","published_at":"2024-08-16","quote":"The price tag of the expansion is now estimated at $5.996 billion, up from the $4.01 billion outlined in the 2022 business case for the project."}]},{"kind":"completion_target","statement_date":"2024-08-15","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"target":{"date":"2029-10-01","precision":"quarter","event":"completion"},"headline":"Opening pushed to late 2029","sources":[{"url":"https://www.ctvnews.ca/vancouver/article/cost-of-surrey-langley-skytrain-extension-balloons-to-6b/","outlet":"CTV News","published_at":"2024-08-16","quote":"The opening date has been pushed back from late 2028 to late 2029, a move also being attributed – in part – to the \"current market climate.\""}]},{"kind":"status","statement_date":"2024-08-15","date_precision":"day","speaker":{"type":"government","name":"Province of British Columbia"},"new_status":"construction","headline":"Under construction","sources":[{"url":"https://globalnews.ca/news/10701039/surrey-langley-skytrain-cost/amp","outlet":"Global News","published_at":"2024-08-15","quote":"Early work on the project is already underway."}]}]},{"slug":"taltson-hydro-expansion","name":"Taltson Hydro Expansion","short_name":"Taltson hydro expansion","sector":"hydro","jurisdiction":"NT","status":"planning","owner":"Government of the Northwest Territories (with the N.W.T. Power Corporation); seeking federal funding","url":"https://www.overruns.ca/projects/taltson-hydro-expansion","first_announced":"2010-01-14","first_price":"up to $700M","first_price_date":"2013-10-18","first_price_speaker":"Government of the Northwest Territories","latest_estimate":"$2–3B","latest_estimate_date":"2025-06-09","latest_estimate_speaker":"Strategic Infrastructure Minister Caroline Wawzonek","cost_basis":"capital cost","multiple_after_inflation":2.67,"multiple_as_announced":3.57,"delay_months":null,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"Expanding the Taltson hydro plant south of Great Slave Lake to about 60 MW and linking it to the Snare/Yellowknife grid with a cable under the lake. Pursued in several forms since the 2000s by the Government of the Northwest Territories and its power corporation.","observations":[{"kind":"cost","statement_date":"2010-01-14","date_precision":"day","speaker":{"type":"media_estimate","name":"CBC News (estimator not named; Dezé Energy proposal)"},"cost":{"low":0.5,"high":0.6,"point":null,"currency":"CAD","dollar_year":2010,"covers":"capital cost"},"headline":"Dezé plan: $500-600M with a line to the diamond mines","note":"Not attributed to anyone, so not used as the first price. Proposed by Dezé Energy, part-owned by the territory's power corporation.","sources":[{"url":"https://www.cbc.ca/news/canada/north/taltson-dam-expansion-questioned-by-fishing-camp-owner-1.961908","outlet":"CBC News","published_at":"2010-01-14","quote":"Expanding the dam, as well as building a power line that would connect the facility to the N.W.T.'s diamond mines, is estimated to cost between $500 million and $600 million."}]},{"kind":"status","statement_date":"2011-03-02","date_precision":"day","speaker":{"type":"government","name":"Premier Floyd Roland"},"new_status":"paused","headline":"Dezé project put on hold","sources":[{"url":"https://www.cbc.ca/1.1027782","outlet":"CBC News","published_at":"2011-03-02","quote":"A major hydroelectric expansion project in the Northwest Territories is being put on hold because it is not viable at this time, says Premier Floyd Roland."}]},{"kind":"cost","statement_date":"2013-10-18","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories"},"cost":{"low":null,"high":0.7,"point":null,"currency":"CAD","dollar_year":2013,"covers":"capital cost"},"headline":"Up to $700M to expand Taltson","note":"The first figure from the government, given by the premier and finance minister.","sources":[{"url":"https://amp.cbc.ca/news/canada/north/n-w-t-premier-eyes-hydro-expansion-1.2125578","outlet":"CBC News","published_at":"2013-10-18","quote":"Hydro expansion in the South Slave could cost as much as $700 million, but the territory doesn't have enough borrowing power to start another mega project now."}]},{"kind":"scope_change","statement_date":"2013-10-18","date_precision":"day","speaker":{"type":"government","name":"Premier Bob McLeod"},"scope":{"description":"Rescoped from powering the diamond mines to connecting N.W.T. hydro with grids to the south."},"headline":"Goal shifts to linking northern hydro with the southern grid","sources":[{"url":"https://amp.cbc.ca/news/canada/north/n-w-t-premier-eyes-hydro-expansion-1.2125578","outlet":"CBC News","published_at":"2013-10-18","quote":"Bob McLeod says building transmission lines to connect northern power with the southern grid will be the territorial government's biggest project in the second half of its term."}]},{"kind":"cost","statement_date":"2014-10-27","date_precision":"day","speaker":{"type":"government","name":"Finance Minister Michael Miltenberger (business case)"},"cost":{"low":null,"high":null,"point":1.2,"currency":"CAD","dollar_year":2014,"covers":"capital cost"},"headline":"Business case: $1.2B, 'not economically viable'","sources":[{"url":"https://amp.cbc.ca/news/canada/north/n-w-t-abandons-1-2b-plan-to-export-electricity-south-1.2814190","outlet":"CBC News","published_at":"2014-10-27","quote":"Officials completed a business case this year and found it would cost $1.2 billion, more than double what was initially estimated."}]},{"kind":"status","statement_date":"2014-10-27","date_precision":"day","speaker":{"type":"government","name":"Finance Minister Michael Miltenberger"},"new_status":"paused","headline":"Plan shelved","sources":[{"url":"https://amp.cbc.ca/news/canada/north/n-w-t-abandons-1-2b-plan-to-export-electricity-south-1.2814190","outlet":"CBC News","published_at":"2014-10-27","quote":"\"But at $1.2 billion, it's just not economically viable for us so we have to look at a plan B.”"}]},{"kind":"cost","statement_date":"2016-03-11","date_precision":"day","speaker":{"type":"proponent","name":"N.W.T. Power Corporation (Sebert)"},"cost":{"low":0.5,"high":null,"point":null,"currency":"CAD","dollar_year":2016,"covers":"capital cost"},"headline":"Saskatchewan option: 'over $500 million'","sources":[{"url":"https://amp.cbc.ca/news/canada/north/taltson-hydro-expansion-saskatchewan-1.3487488","outlet":"CBC News","published_at":"2016-03-11","quote":"\"The likely cost of the project would probably be over $500 million, perhaps between that and a billion dollars,\" said Sebert."}]},{"kind":"status","statement_date":"2019-01-23","date_precision":"day","speaker":{"type":"government","name":"Governments of Canada and the N.W.T."},"new_status":"planning","headline":"Studies restart with $1.2M","sources":[{"url":"https://www.cbc.ca/news/canada/north/investment-taltson-hydroelectricity-1.4990400","outlet":"CBC News","published_at":"2019-01-23","quote":"The federal and Northwest Territories governments are investing $1.2 million into preliminary work for a proposed expansion of the Taltson Hydroelectricity Expansion Project."}]},{"kind":"completion_target","statement_date":"2024-11-13","date_precision":"day","speaker":{"type":"government","name":"GNWT (David Mahon, senior engineer)"},"target":{"date":"2033-01-01","precision":"year","event":"completion"},"headline":"In operation by 2033","sources":[{"url":"https://cabinradio.ca/210003/news/yellowknife/gnwt-sets-tentative-taltson-expansion-date-with-new-funding","outlet":"Cabin Radio","published_at":"2024-11-13","quote":"Senior GNWT engineer David Mahon, elaborating on a possible timeline, said: “We would like to be in operation in 2033.”"}]},{"kind":"cost","statement_date":"2025-06-09","date_precision":"day","speaker":{"type":"government","name":"Strategic Infrastructure Minister Caroline Wawzonek"},"cost":{"low":2,"high":3,"point":null,"currency":"CAD","dollar_year":2025,"covers":"capital cost"},"headline":"Now $2-3B","sources":[{"url":"https://cabinradio.ca/242592/news/politics/taltson-hydro-expansion-will-cost-up-to-3-billion-minister-says","outlet":"Cabin Radio","published_at":"2025-06-10","quote":"One of the NWT government’s signature infrastructure projects is now expected to cost between $2 billion and $3 billion, Caroline Wawzonek told Yellowknife city council on Monday."},{"url":"https://www.cbc.ca/lite/story/1.7557852","outlet":"CBC News","published_at":"2025-06-11","quote":"\"I mean, we're into the billions, somewhere between $2 billion and $3 billion,\""}]},{"kind":"scope_change","statement_date":"2025-06-09","date_precision":"day","speaker":{"type":"government","name":"Government of the Northwest Territories"},"scope":{"description":"Expand generation to about 60 MW and connect the Taltson and Snare grids with a cable under Great Slave Lake."},"headline":"Current scope: tripled capacity and a link to the Snare grid","sources":[{"url":"https://www.nationalobserver.com/2026/03/30/news/northwest-territories-taltson-hydro-expansion","outlet":"Canada's National Observer","published_at":"2026-03-30","quote":"The expansion project is estimated to cost between $2 and $3 billion and include two initiatives: nearly tripling the generation station's capacity to 60 MW, which could be enough to power between 32,000 and 70,000 homes, and connecting the Taltson grid to the Snare grid through an underwater cable across Great Slave Lake."}]}]},{"slug":"trans-mountain-expansion","name":"Trans Mountain Expansion Project","short_name":"Trans Mountain","sector":"pipeline","jurisdiction":"federal","status":"complete","owner":"Government of Canada (via Trans Mountain Corporation, a federal Crown corporation); proponent until 2018 was Kinder Morgan","url":"https://www.overruns.ca/projects/trans-mountain-expansion","first_announced":"2011-10-19","first_price":"$3.8B","first_price_date":"2012-02-21","first_price_speaker":"Kinder Morgan Energy Partners","latest_estimate":"$28.6B","latest_estimate_date":"2025-03-06","latest_estimate_speaker":"Trans Mountain Corporation","cost_basis":"capital cost","multiple_after_inflation":5.69,"multiple_as_announced":7.53,"delay_months":77,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A second oil pipeline alongside the 1950s Trans Mountain line from the Edmonton area to Burnaby, B.C., nearly tripling capacity. Ottawa bought the line and the project in 2018 and finished it as owner.","observations":[{"kind":"announcement","statement_date":"2011-10-19","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Energy Partners"},"headline":"Kinder Morgan tests shipper demand for a bigger Trans Mountain","note":"Kinder Morgan's first public notice of the expansion. No cost given.","sources":[{"url":"https://www.sec.gov/Archives/edgar/data/888228/000150630711000117/kmpex991q3_2011nr.htm","outlet":"Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1)","published_at":"2011-10-19","quote":"Trans Mountain pipeline plans to conduct a binding public open season beginning Oct. 20 and ending Jan. 19, 2012, to assess shipper interest to expand the pipeline."}]},{"kind":"cost","statement_date":"2012-02-21","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Energy Partners"},"cost":{"low":null,"high":null,"point":3.8,"currency":"CAD","dollar_year":2012,"covers":"capital cost"},"headline":"About $3.8B","note":"For a twin line carrying over 600,000 barrels a day, from Kinder Morgan's annual report. The currency isn't stated; treated as Canadian dollars.","sources":[{"url":"https://www.sec.gov/Archives/edgar/data/888228/000088822812000012/form10k_2011.htm","outlet":"Kinder Morgan Energy Partners (SEC Form 10-K, 2011)","published_at":"2012-02-21","quote":"Based on shipper response, we would construct a twin pipeline that could boost system capacity to over 600,000 barrels per day. Our current estimate of total construction costs on the project is approximately $3.8 billion."}]},{"kind":"cost","statement_date":"2012-04-12","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Canada (Ian Anderson, president)"},"cost":{"low":null,"high":null,"point":5,"currency":"CAD","dollar_year":2012,"covers":"capital cost"},"headline":"Formal launch at about $5B, for 850,000 barrels a day","sources":[{"url":"https://www.cbc.ca/lite/story/1.1272944","outlet":"CBC News","published_at":"2012-04-12","quote":"The Kinder Morgan pipeline company is rolling out plans to spend $5 billion to nearly triple the capacity of its Trans Mountain pipeline that carries crude oil from the Alberta oilsands to tankers in Vancouver."},{"url":"https://www.sec.gov/Archives/edgar/data/888228/000150630712000036/kmpex991q1_2012.htm","outlet":"Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1)","published_at":"2012-04-18","quote":"The approximately $5 billion project (which is larger than initially anticipated due to strong binding customer support)"}]},{"kind":"completion_target","statement_date":"2012-04-12","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Canada (Ian Anderson, president)"},"target":{"date":"2017-01-01","precision":"year","event":"completion"},"headline":"In operation by 2017","sources":[{"url":"https://www.cbc.ca/lite/story/1.1272944","outlet":"CBC News","published_at":"2012-04-12","quote":"If our application is approved, construction is currently forecast to commence in 2016 with the proposed project operating by 2017,\" said Anderson."}]},{"kind":"cost","statement_date":"2012-07-18","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Energy Partners"},"cost":{"low":null,"high":null,"point":4.1,"currency":"CAD","dollar_year":2012,"covers":"capital cost"},"headline":"Trimmed to $4.1B for 750,000 barrels a day","sources":[{"url":"https://www.sec.gov/Archives/edgar/data/888228/000150630712000082/kmpex991q2_12.htm","outlet":"Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1)","published_at":"2012-07-18","quote":"The proposed $4.1 billion expansion would increase capacity on Trans Mountain from 300,000 bpd to 750,000 bpd."}]},{"kind":"cost","statement_date":"2013-01-10","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Canada"},"cost":{"low":null,"high":null,"point":5.4,"currency":"CAD","dollar_year":2013,"covers":"capital cost"},"headline":"Scaled up: $5.4B for 890,000 barrels a day","sources":[{"url":"https://www.cbc.ca/lite/story/1.1387525","outlet":"The Canadian Press, via CBC News","published_at":"2013-01-10","quote":"The expansion represents a capital investment of $5.4 billion and will complete the twinning of the existing pipeline from Strathcona County, Alta., to Burnaby, B.C."},{"url":"https://www.sec.gov/Archives/edgar/data/888228/000088822813000003/kmpexhibit991january162013.htm","outlet":"Kinder Morgan Energy Partners (SEC Form 8-K, Exhibit 99.1)","published_at":"2013-01-16","quote":"These additional commitments will result in an increase in the proposed expansion capacity from 750,000 bpd to 890,000 bpd and increase the capital investment in the project from $4.1 billion to $5.4 billion."}]},{"kind":"scope_change","statement_date":"2013-01-10","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Canada"},"scope":{"description":"Planned capacity raised from 750,000 to 890,000 barrels a day."},"headline":"Capacity raised to 890,000 barrels a day","sources":[{"url":"https://www.cbc.ca/lite/story/1.1387525","outlet":"The Canadian Press, via CBC News","published_at":"2013-01-10","quote":"Subsidiary Kinder Morgan Canada said Thursday that increased long-term commitments from shippers have convinced it to ramp up the proposed expansion capacity to 890,000 barrels per day from a previously planned 750,000."}]},{"kind":"milestone","statement_date":"2013-12-01","date_precision":"month","speaker":{"type":"proponent","name":"Kinder Morgan Canada"},"milestone":{"title":"Regulatory application filed with the National Energy Board","achieved":true},"headline":"Application filed with the National Energy Board","sources":[{"url":"https://www.cbc.ca/lite/story/1.3327875","outlet":"The Canadian Press, via CBC News","published_at":"2015-11-20","quote":"Kinder Morgan, the company behind the pipeline project, doesn't yet have a formal estimate of how the price tag has changed since its regulatory application was filed in December 2013."}]},{"kind":"cost","statement_date":"2015-10-21","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Canada (Ian Anderson, president)"},"cost":{"low":null,"high":null,"point":6.8,"currency":"CAD","dollar_year":2015,"covers":"capital cost"},"headline":"\"Looking more like $6.8 billion\"","note":"Said on an Oct. 21, 2015 analyst call.","sources":[{"url":"https://www.cbc.ca/lite/story/1.3327875","outlet":"The Canadian Press, via CBC News","published_at":"2015-11-20","quote":"But on a conference call with analysts and investors last month, Kinder Morgan Canada president Ian Anderson said it's looking more like $6.8 billion"}]},{"kind":"status","statement_date":"2016-11-29","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Prime Minister Justin Trudeau)"},"new_status":"approved","headline":"Federal cabinet approves the expansion","sources":[{"url":"https://www.cbc.ca/lite/story/1.3872828","outlet":"CBC News","published_at":"2016-11-29","quote":"Prime Minister Justin Trudeau announces his government is approving Kinder Morgan's proposal to triple the capacity of its Trans Mountain pipeline from Alberta to Burnaby, B.C."}]},{"kind":"cost","statement_date":"2017-03-09","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan"},"cost":{"low":null,"high":null,"point":7.4,"currency":"CAD","dollar_year":2017,"covers":"capital cost"},"headline":"$7.4B, including financing","note":"This figure included financing costs.","sources":[{"url":"https://www.theglobeandmail.com/report-on-business/industry-news/energy-and-resources/price-tag-for-trans-mountain-expansion-rises-to-74-billion/article34247660/","outlet":"The Globe and Mail","published_at":"2017-03-09","quote":"The price tag for Kinder Morgan Inc.'s Trans Mountain expansion has increased again, this time to $7.4-billion – but the company says it still has strong commercial support for the long-awaited project."},{"url":"https://www.canada.ca/en/department-finance/news/2020/02/building-the-trans-mountain-expansion-project.html","outlet":"Department of Finance Canada","published_at":"2020-02-07","quote":"In 2017, Kinder Morgan publicly announced a Project cost estimate of $7.4 billion (including financing costs), with an estimated in-service date of December 2019."}]},{"kind":"completion_target","statement_date":"2017-03-09","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan"},"target":{"date":"2019-12-01","precision":"month","event":"completion"},"headline":"In service by December 2019","sources":[{"url":"https://www.canada.ca/en/department-finance/news/2020/02/building-the-trans-mountain-expansion-project.html","outlet":"Department of Finance Canada","published_at":"2020-02-07","quote":"In 2017, Kinder Morgan publicly announced a Project cost estimate of $7.4 billion (including financing costs), with an estimated in-service date of December 2019."},{"url":"https://www.theglobeandmail.com/report-on-business/industry-news/energy-and-resources/price-tag-for-trans-mountain-expansion-rises-to-74-billion/article34247660/","outlet":"The Globe and Mail","published_at":"2017-03-09","quote":"Construction is set to begin this fall, according to the company, with an in-service date slated for late 2019."}]},{"kind":"milestone","statement_date":"2018-05-29","date_precision":"day","speaker":{"type":"government","name":"Department of Finance Canada"},"milestone":{"title":"Ottawa agrees to buy the pipeline and the expansion project from Kinder Morgan","achieved":true},"headline":"Ottawa agrees to buy the pipeline","note":"The price covered the existing pipeline and the expansion, so it isn't a construction cost.","sources":[{"url":"https://www.canada.ca/en/department-finance/news/2018/05/agreement-reached-to-create-and-protect-jobs-build-trans-mountain-expansion-project0.html","outlet":"Department of Finance Canada","published_at":"2018-05-29","quote":"In addition, the Government of Canada has reached an agreement with Kinder Morgan to purchase the company's Trans Mountain Expansion Project and related pipeline and terminal assets for $4.5 billion."}]},{"kind":"cost","statement_date":"2018-08-07","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Canada (SEC filing for the sale)"},"cost":{"low":null,"high":9.3,"point":null,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"Sale documents show scenarios up to $9.3B","note":"The highest of several scenarios. A finance official said it didn't reflect the expected final cost.","sources":[{"url":"https://www.cbc.ca/news/canada/calgary/kinder-morgan-trans-mountain-pipeline-costs-could-rise-completion-delayed-1.4776643","outlet":"The Canadian Press, via CBC News","published_at":"2018-08-07","quote":"Kinder Morgan has long said it would cost $7.4 billion to build a second pipeline parallel to the first in order to triple its capacity, but the financial documents present a number of different construction cost scenarios, with the highest one being $9.3 billion."}]},{"kind":"completion_target","statement_date":"2018-08-07","date_precision":"day","speaker":{"type":"proponent","name":"Kinder Morgan Canada (SEC filing for the sale)"},"target":{"date":"2021-12-01","precision":"month","event":"completion"},"headline":"Construction complete December 2021","sources":[{"url":"https://www.cbc.ca/news/canada/calgary/kinder-morgan-trans-mountain-pipeline-costs-could-rise-completion-delayed-1.4776643","outlet":"The Canadian Press, via CBC News","published_at":"2018-08-07","quote":"The documents also suggest construction won't be complete until December 2021 — a full year beyond its previous projection of December 2020."}]},{"kind":"status","statement_date":"2018-08-30","date_precision":"day","speaker":{"type":"other","name":"Federal Court of Appeal"},"new_status":"paused","headline":"Court quashes the approval; Ottawa closes the purchase","sources":[{"url":"https://www.cbc.ca/lite/story/1.4804503","outlet":"CBC News","published_at":"2018-08-30","quote":"The vote came just 30 minutes after the Federal Court of Appeal quashed the federal government's approvals to build the massive project, handing a huge victory to Indigenous groups and environmentalists opposed to it."}]},{"kind":"cost","statement_date":"2019-01-31","date_precision":"day","speaker":{"type":"watchdog","name":"Parliamentary Budget Officer"},"cost":{"low":null,"high":null,"point":9.3,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"Budget officer: $9.3B if finished by end of 2021","sources":[{"url":"https://www.cheknews.ca/?p=530180","outlet":"The Canadian Press, via CHEK News","published_at":"2019-01-31","quote":"Expanding the pipeline’s capacity will come at an estimated cost of $9.3 billion if the project is completed by Dec. 31, 2021, the PBO estimates."}]},{"kind":"status","statement_date":"2019-06-18","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Prime Minister Justin Trudeau)"},"new_status":"approved","headline":"Cabinet approves the project a second time","sources":[{"url":"https://www.cbc.ca/lite/story/1.5180269","outlet":"CBC News","published_at":"2019-06-18","quote":"Prime Minister Justin Trudeau and his cabinet have again approved the Trans Mountain expansion project, a crucial next step for the much-delayed pipeline project designed to carry nearly a million barrels of oil from Alberta's oilpatch to the B.C."}]},{"kind":"cost","statement_date":"2020-02-07","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation"},"cost":{"low":null,"high":null,"point":12.6,"currency":"CAD","dollar_year":2020,"covers":"capital cost"},"headline":"Crown corporation's first estimate: $12.6B","sources":[{"url":"https://www.canada.ca/en/department-finance/news/2020/02/building-the-trans-mountain-expansion-project.html","outlet":"Department of Finance Canada","published_at":"2020-02-07","quote":"On February 3, 2020, the Trans Mountain Corporation’s (TMC) Board of Directors approved a total cost estimate of $12.6 billion to bring the Trans Mountain Expansion Project into service by the end of 2022."},{"url":"https://cfjctoday.com/?p=817049","outlet":"The Canadian Press, via CFJC Today","published_at":"2020-02-07","quote":"The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion."}]},{"kind":"completion_target","statement_date":"2020-02-07","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation (Ian Anderson, CEO)"},"target":{"date":"2022-12-01","precision":"month","event":"completion"},"headline":"In service by December 2022","sources":[{"url":"https://cfjctoday.com/?p=817049","outlet":"The Canadian Press, via CFJC Today","published_at":"2020-02-07","quote":"He says the project is now expected to be in service by December 2022."}]},{"kind":"cost","statement_date":"2022-02-18","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation"},"cost":{"low":null,"high":null,"point":21.4,"currency":"CAD","dollar_year":2022,"covers":"capital cost"},"headline":"$21.4B; Ottawa says no more public money","sources":[{"url":"https://docs.transmountain.com/220218-Project-Update-FINAL.pdf","outlet":"Trans Mountain Corporation (project update)","published_at":"2022-02-18","quote":"The increase in costs, from $12.6 billion to $21.4 billion, can be attributed to five broad categories"},{"url":"https://globalnews.ca/news/8631044/trans-mountain-pipeline-cost-climbs/","outlet":"Global News","published_at":"2022-02-18","quote":"But Canada’s oil and gas industry remains staunchly behind a project it says remains essential to the national interest, in spite of newly disclosed budget overruns that peg the new cost of the Trans Mountain expansion at $21.4 billion, up from an earlier estimate of $12.6 billion."}]},{"kind":"completion_target","statement_date":"2022-02-18","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation"},"target":{"date":"2023-07-01","precision":"quarter","event":"completion"},"headline":"Mechanical completion in Q3 2023","sources":[{"url":"https://docs.transmountain.com/220218-Project-Update-FINAL.pdf","outlet":"Trans Mountain Corporation (project update)","published_at":"2022-02-18","quote":"Mechanical completion of the Project is anticipated to occur in the third quarter of 2023."},{"url":"https://globalnews.ca/news/8631044/trans-mountain-pipeline-cost-climbs/","outlet":"Global News","published_at":"2022-02-18","quote":"The company also pushed back the projected completion date to the third quarter of 2023."}]},{"kind":"cost","statement_date":"2023-03-10","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation"},"cost":{"low":null,"high":null,"point":30.9,"currency":"CAD","dollar_year":2023,"covers":"capital cost"},"headline":"$30.9B","sources":[{"url":"https://www.kitco.com/news/off-the-wire/2023-03-10/trans-mountain-expansion-project-pipeline-be-service-q1-2024","outlet":"Reuters, via Kitco News","published_at":"2023-03-10","quote":"The total cost is now estimated at approximately $30.9 billion, the company said in a press release, adding, \"Trans Mountain is in the process of securing external financing to fund the remaining cost.\""},{"url":"https://globalnews.ca/news/9544129/trans-mountain-pipeline-cost-increase-march-2023/","outlet":"The Canadian Press, via Global News","published_at":"2023-03-10","quote":"The estimated cost of the Trans Mountain pipeline expansion project has increased once again, this time to $30.9 billion."}]},{"kind":"completion_target","statement_date":"2023-03-10","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation"},"target":{"date":"2024-01-01","precision":"quarter","event":"completion"},"headline":"In service in Q1 2024","sources":[{"url":"https://www.kitco.com/news/off-the-wire/2023-03-10/trans-mountain-expansion-project-pipeline-be-service-q1-2024","outlet":"Reuters, via Kitco News","published_at":"2023-03-10","quote":"March 10 (Reuters) - Canada's government-owned Trans Mountain Corp on Friday announced that the Trans Mountain Expansion Project pipeline will be in service by the first quarter of 2024."}]},{"kind":"completion_target","statement_date":"2024-02-26","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation (filing to the Canada Energy Regulator)"},"target":{"date":"2024-05-01","precision":"day","event":"completion"},"headline":"Firm service from May 1, 2024","sources":[{"url":"https://boereport.com/2024/02/27/trans-mountain-pipeline-sees-second-quarter-service-date-higher-cost/","outlet":"Reuters, via BOE Report","published_at":"2024-02-27","quote":"Trans Mountain said in the filing on Monday to the Canada Energy Regulator, however, that commencement for firm service contracts with shippers is May 1."}]},{"kind":"status","statement_date":"2024-05-01","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation"},"new_status":"complete","headline":"Expanded pipeline enters commercial service","sources":[{"url":"https://docs.transmountain.com/Corporate-Reports/TMC-12.31.24-Management-Report-Final.pdf","outlet":"Trans Mountain Corporation (Management Report, year ended Dec. 31, 2024)","published_at":"2025-03-06","quote":"The commercial commencement date for the Expanded System was May 1, 2024."}]},{"kind":"cost","statement_date":"2024-11-08","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation (estimate reported by the Parliamentary Budget Officer)"},"cost":{"low":null,"high":null,"point":34.2,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Total cost estimate rises to $34.2B","note":"Trans Mountain's own estimate, reported by the Parliamentary Budget Officer.","sources":[{"url":"https://www.pbo-dpb.ca/en/publications/RP-2425-021-S--trans-mountain-pipeline-2024-report--reseau-pipelines-trans-mountain-rapport-2024","outlet":"Office of the Parliamentary Budget Officer","published_at":"2024-11-08","quote":"the total project cost estimate for the TMEP increased from $21.4 billion to $34.2 billion."}]},{"kind":"cost","statement_date":"2025-03-06","date_precision":"day","speaker":{"type":"proponent","name":"Trans Mountain Corporation"},"cost":{"low":null,"high":null,"point":28.6,"currency":"CAD","dollar_year":2024,"covers":"capital cost"},"headline":"Final construction cost: $28.6B","note":"Actual spending reported after completion. Another $5.1B in financing costs was capitalized, for $33.7B in all. The first figure, in 2012, was a construction cost, so the construction figure is the one compared.","sources":[{"url":"https://docs.transmountain.com/Corporate-Reports/TMC-12.31.24-Management-Report-Final.pdf","outlet":"Trans Mountain Corporation (Management Report, year ended Dec. 31, 2024)","published_at":"2025-03-06","quote":"Since the inception of the project, $28.6 billion in construction capital spending has been incurred plus $5.1 billion in financial carrying costs have been capitalized."}]}]},{"slug":"valley-line-southeast-lrt","name":"Valley Line Southeast LRT (Edmonton)","short_name":"Valley Line Southeast","sector":"transit","jurisdiction":"AB","status":"operational","owner":"City of Edmonton, with federal and provincial funding","url":"https://www.overruns.ca/projects/valley-line-southeast-lrt","first_announced":"2016-02-26","first_price":"$1.8B","first_price_date":"2016-02-26","first_price_speaker":"City of Edmonton","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost (P3 contract)","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":35,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A 13 km low-floor light rail line from downtown Edmonton to Mill Woods, built and operated by the TransEd consortium under a public-private partnership.","observations":[{"kind":"cost","statement_date":"2016-02-26","date_precision":"year","speaker":{"type":"government","name":"City of Edmonton"},"cost":{"low":null,"high":null,"point":1.8,"currency":"CAD","dollar_year":2016,"covers":"capital cost (P3 contract)"},"headline":"$1.8B public-private partnership","note":"Signed with the TransEd consortium in 2016.","sources":[{"url":"https://www.cbc.ca/1.7016686","outlet":"CBC News","published_at":"2023-11-03","quote":"The $1.8-billion project, a public-private partnership with Trans-Ed, was supposed to be operational in December 2020."}]},{"kind":"completion_target","statement_date":"2016-02-26","date_precision":"year","speaker":{"type":"government","name":"City of Edmonton"},"target":{"date":"2020-12-01","precision":"month","event":"first_service"},"headline":"Open December 2020","sources":[{"url":"https://thenuggetonline.com/long-awaited-valley-line-southeast-lrt-open-to-the-public/","outlet":"The Nugget","published_at":"2023-11-16","quote":"The Valley Line Southeast was originally meant to be operational in December 2020."}]},{"kind":"status","statement_date":"2016-04-22","date_precision":"month","speaker":{"type":"government","name":"City of Edmonton and TransEd"},"new_status":"construction","headline":"Ground broken","sources":[{"url":"https://www.cbc.ca/1.7016686","outlet":"CBC News","published_at":"2023-11-03","quote":"A groundbreaking ceremony, in which then-mayor Don Iveson was joined by then-federal infrastructure minister and current Mayor Amerjeet Sohi, was held in April 2016, as the ink dried on the city's new contract with TransEd."}]},{"kind":"completion_target","statement_date":"2021-10-01","date_precision":"month","speaker":{"type":"proponent","name":"TransEd"},"target":{"date":"2022-01-01","precision":"quarter","event":"first_service"},"headline":"Delayed to early 2022","sources":[{"url":"https://thenuggetonline.com/long-awaited-valley-line-southeast-lrt-open-to-the-public/","outlet":"The Nugget","published_at":"2023-11-16","quote":"This second delay pushed the opening date to early 2022."}]},{"kind":"completion_target","statement_date":"2021-12-01","date_precision":"month","speaker":{"type":"proponent","name":"TransEd"},"target":{"date":"2022-10-01","precision":"quarter","event":"first_service"},"headline":"Delayed to late 2022","sources":[{"url":"https://thenuggetonline.com/long-awaited-valley-line-southeast-lrt-open-to-the-public/","outlet":"The Nugget","published_at":"2023-11-16","quote":"Unfortunately, two months later in December 2021, the completion date was pushed back to late 2022."}]},{"kind":"status","statement_date":"2023-11-04","date_precision":"day","speaker":{"type":"government","name":"City of Edmonton"},"new_status":"operational","headline":"Opened nearly three years late","sources":[{"url":"https://thenuggetonline.com/long-awaited-valley-line-southeast-lrt-open-to-the-public/","outlet":"The Nugget","published_at":"2023-11-16","quote":"After almost a three-year delay, the long-awaited Valley Line Southeast LRT finally opened for passenger service on November 4, 2023."}]}]},{"slug":"valley-line-west-lrt","name":"Valley Line West LRT (Edmonton)","short_name":"Valley Line West LRT","sector":"transit","jurisdiction":"AB","status":"construction","owner":"City of Edmonton (with federal and Alberta funding)","url":"https://www.overruns.ca/projects/valley-line-west-lrt","first_announced":"2011-01-01","first_price":"$1.8B","first_price_date":"2011-01-01","first_price_speaker":"City of Edmonton","latest_estimate":"$2.6B","latest_estimate_date":"2020-03-13","latest_estimate_speaker":"City of Edmonton","cost_basis":"capital cost","multiple_after_inflation":1.26,"multiple_as_announced":1.44,"delay_months":null,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":"2026-11-19","last_monthly_review":"2026-11-05","summary":"A 14-kilometre, mostly street-level LRT from downtown Edmonton to Lewis Farms in the west end, the second stage of the Valley Line. Built by Marigold Infrastructure Partners under a design-build-partially-finance contract signed in December 2020.","observations":[{"kind":"cost","statement_date":"2011-01-01","date_precision":"year","speaker":{"type":"government","name":"City of Edmonton"},"cost":{"low":null,"high":null,"point":1.8,"currency":"CAD","dollar_year":2011,"covers":"capital cost"},"headline":"$1.8B under the 2011 recommendations","note":"Dated to the 2011 design recommendations the city's 2018 report compared against. The original 2011 document is not yet sourced.","sources":[{"url":"https://globalnews.ca/news/4080794/edmonton-transit-west-lrt-valley-line-cost/","outlet":"Global News","published_at":"2018-03-13","quote":"Changing the design at a couple of intersection crossings in the west, compared to the 2011 recommendations, will increase the cost from $1.8 billion to $2.24 billion."}]},{"kind":"cost","statement_date":"2018-03-13","date_precision":"day","speaker":{"type":"government","name":"City of Edmonton"},"cost":{"low":null,"high":null,"point":2.24,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"City report: $2.24B with seven design changes","note":"Includes inflation, assuming construction from 2019.","sources":[{"url":"https://globalnews.ca/news/4080794/edmonton-transit-west-lrt-valley-line-cost/","outlet":"Global News","published_at":"2018-03-13","quote":"“The Valley Line West capital construction cost is currently estimated at $2.24 billion. This project cost estimate includes the seven design recommendations noted above and factors in inflation, assuming a construction start in 2019.”"}]},{"kind":"cost","statement_date":"2018-03-23","date_precision":"day","speaker":{"type":"media_estimate","name":"Global News (unattributed)"},"cost":{"low":null,"high":null,"point":2,"currency":"CAD","dollar_year":2018,"covers":"capital cost"},"headline":"Council drops an underpass: about $2B","note":"The report does not say who gave the estimate, so it is not used as the official figure.","sources":[{"url":"https://globalnews.ca/news/4103343/councillors-vote-in-favour-of-valley-line-lrt-plan-to-keep-train-at-street-level-at-busy-west-edmonton-intersection/","outlet":"Global News","published_at":"2018-03-23","quote":"The cost for the western leg of the Valley Line is now estimated to be about $2 billion and the city said the project could be ready for procurement by the end of the year."}]},{"kind":"cost","statement_date":"2020-03-13","date_precision":"day","speaker":{"type":"government","name":"City of Edmonton"},"cost":{"low":null,"high":null,"point":2.6,"currency":"CAD","dollar_year":2020,"covers":"capital cost"},"headline":"$2.6B at procurement","sources":[{"url":"https://www.edmonton.ca/projects_plans/transit/project-history","outlet":"City of Edmonton","published_at":"2020-03-13","quote":"March 2020: Procurement Update The City has shortlisted 3 teams to participate in the next stage of its procurement competition for the contract to design, build and partially finance the $2.6 billion Valley Line West LRT."}]},{"kind":"status","statement_date":"2020-12-23","date_precision":"day","speaker":{"type":"government","name":"City of Edmonton"},"new_status":"construction","headline":"Contract signed with Marigold","sources":[{"url":"https://www.edmonton.ca/projects_plans/transit/project-history","outlet":"City of Edmonton","published_at":"2020-12-23","quote":"On December 23, 2020, the City reached financial close with Marigold Infrastructure Partners, which was selected as the preferred proponent to design, build and partially finance the $2.6-billion Valley Line West LRT."}]}]},{"slug":"west-coast-oil-pipeline","name":"West Coast Oil Pipeline (Pacific Link)","short_name":"West Coast pipeline","sector":"pipeline","jurisdiction":"AB","status":"planning","owner":"Government of Alberta (proponent); Trans Mountain Corporation, Alberta Petroleum Marketing Commission and Pembina Pipeline (ownership group)","url":"https://www.overruns.ca/projects/west-coast-oil-pipeline","first_announced":"2025-10-01","first_price":"$35.2–43.7B","first_price_date":"2026-07-02","first_price_speaker":"Government of Alberta (submission to the Major Projects Office)","latest_estimate":null,"latest_estimate_date":null,"latest_estimate_speaker":null,"cost_basis":"capital cost","multiple_after_inflation":null,"multiple_as_announced":null,"delay_months":0,"delay_is_minimum":false,"scope_changed":false,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"A proposed one-million-barrel-a-day oil pipeline from Bruderheim, Alta., to a deepwater port near Delta, B.C., along a southern route. Proposed by the Government of Alberta; the ownership group is Trans Mountain Corp. (federal), the Alberta Petroleum Marketing Commission and Pembina. Designated in the national interest on Oct. 1, 2026.","observations":[{"kind":"announcement","statement_date":"2025-10-01","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta (Premier Danielle Smith)"},"headline":"Alberta says it will propose the pipeline itself","note":"No cost given. Alberta put $14M into the proposal.","sources":[{"url":"https://www.cbc.ca/lite/story/1.7648452","outlet":"CBC News","published_at":"2025-10-02","quote":"On Wednesday, Smith said the provincial government will propose its own project, with help from an advisory group that includes the pipeline companies South Bow, Enbridge and Trans Mountain."}]},{"kind":"cost","statement_date":"2026-07-02","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta (submission to the Major Projects Office)"},"cost":{"low":35.2,"high":43.7,"point":null,"currency":"CAD","dollar_year":2026,"covers":"capital cost"},"headline":"$35.2–43.7B","sources":[{"url":"https://www.cbc.ca/news/canada/calgary/alberta-pipeline-proposal-ottawa-major-projects-9.7254251","outlet":"CBC News","published_at":"2026-07-03","quote":"The estimated cost of the project, according to the Alberta government's submission, would be $35.2 billion to $43.7 billion, including contingencies."},{"url":"https://boereport.com/2026/10/01/a-timeline-for-pacific-link-the-national-interest-alberta-b-c-pipeline-plan/","outlet":"The Canadian Press, via BOE Report","published_at":"2026-10-01","quote":"The preliminary price tag is estimated at a range of $35.2 billion to $43.7 billion."}]},{"kind":"completion_target","statement_date":"2026-07-02","date_precision":"day","speaker":{"type":"government","name":"Government of Alberta (submission to the Major Projects Office)"},"target":{"date":"2032-01-01","precision":"year","event":"completion"},"headline":"Completed between 2032 and 2034","sources":[{"url":"https://www.cbc.ca/news/canada/calgary/alberta-pipeline-proposal-ottawa-major-projects-9.7254251","outlet":"CBC News","published_at":"2026-07-03","quote":"It expects the approximately 1,200- to 1,250-kilometre pipeline project to be completed between 2032 and 2034."}]},{"kind":"milestone","statement_date":"2026-10-01","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (Prime Minister Mark Carney) and Alberta"},"milestone":{"title":"Listed on Schedule 1 of the Building Canada Act","achieved":true},"headline":"First project listed in the national interest","sources":[{"url":"https://www.cbc.ca/news/politics/west-coast-pipeline-national-interest-9.7365037","outlet":"CBC News","published_at":"2026-10-01","quote":"Listing the West Coast Pacific Link oil pipeline on Schedule 1 of the Building Canada Act means the federal government has moved from considering whether it should be built to how it will be built by fast-tracking and consolidating the approval process, including environmental assessments."}]},{"kind":"completion_target","statement_date":"2026-10-01","date_precision":"day","speaker":{"type":"government","name":"Government of Canada (senior official)"},"target":{"date":"2032-01-01","precision":"year","event":"completion"},"headline":"Running by 2032-33","sources":[{"url":"https://www.cbc.ca/news/politics/west-coast-pipeline-national-interest-9.7365037","outlet":"CBC News","published_at":"2026-10-01","quote":"1, 2027, allowing construction to begin, with a view to having the pipeline up and running by 2032-33."}]}]},{"slug":"yonge-north-subway-extension","name":"Yonge North Subway Extension (Line 1)","short_name":"Yonge North subway","sector":"transit","jurisdiction":"ON","status":"procurement","owner":"Metrolinx (Province of Ontario), with federal funding","url":"https://www.overruns.ca/projects/yonge-north-subway-extension","first_announced":"2007-06-01","first_price":"up to $3B","first_price_date":"2007-06-01","first_price_speaker":"TTC and York Region (2007 approved plan)","latest_estimate":"$5.6B","latest_estimate_date":"2021-03-18","latest_estimate_speaker":"Metrolinx (initial business case)","cost_basis":"capital cost","multiple_after_inflation":1.47,"multiple_as_announced":1.87,"delay_months":null,"delay_is_minimum":false,"scope_changed":true,"last_reviewed":null,"last_monthly_review":"2026-11-05","summary":"An extension of Toronto's Line 1 subway north from Finch station into Markham and Richmond Hill, led by Metrolinx.","observations":[{"kind":"cost","statement_date":"2007-06-01","date_precision":"year","speaker":{"type":"government","name":"TTC and York Region (2007 approved plan)"},"cost":{"low":null,"high":3,"point":null,"currency":"CAD","dollar_year":2007,"covers":"capital cost"},"headline":"2007 plan: under $3B","sources":[{"url":"https://stevemunro.ca/2021/03/20/metrolinx-trims-yonge-north-subway/","outlet":"Steve Munro","published_at":"2021-03-20","quote":"The fundamental problem which the IBC and its supplement seek to address is that the cost of the extension had grown to $9 billion in 2019 from an original estimate in the 2007 approved plan of less than $3 billion."}]},{"kind":"cost","statement_date":"2019-01-01","date_precision":"year","speaker":{"type":"government","name":"TTC"},"cost":{"low":null,"high":null,"point":9.3,"currency":"CAD","dollar_year":2019,"covers":"capital cost"},"headline":"TTC: $9.3B for the six-station plan","sources":[{"url":"https://amp.cbc.ca/lite/story/1.5955340","outlet":"CBC News","published_at":"2021-03-19","quote":"The analysis shows that if the six-station plan were to go ahead as planned, the price of the project would reach $9.3 billion, as estimated by the TTC in 2019."}]},{"kind":"scope_change","statement_date":"2021-03-18","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx"},"scope":{"description":"Cut from six stations to five, with sections above ground, to fit a $5.6B budget."},"headline":"Fewer stations to fit the budget","sources":[{"url":"https://amp.cbc.ca/lite/story/1.5955340","outlet":"CBC News","published_at":"2021-03-19","quote":"The province's provisional budget is $5.6 billion."}]},{"kind":"cost","statement_date":"2021-03-18","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx (initial business case)"},"cost":{"low":null,"high":null,"point":5.6,"currency":"CAD","dollar_year":2021,"covers":"capital cost"},"headline":"Budget $5.6B after cuts","sources":[{"url":"https://www.masstransitmag.com/rail/infrastructure/article/21215163/yonge-north-subway-extension-business-case-less-stations-but-within-budget","outlet":"Mass Transit","published_at":"2021-03-19","quote":"Within the document, Metrolinx says it is “committed to delivering a YNSE that offers an optimized program within the available funding envelope” of C$5.6 billion (US$4.48 billion)."}]},{"kind":"completion_target","statement_date":"2021-03-18","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx (initial business case)"},"target":{"date":"2029-01-01","precision":"year","event":"first_service"},"headline":"Service 2029 to 2030","sources":[{"url":"https://www.masstransitmag.com/rail/infrastructure/article/21215163/yonge-north-subway-extension-business-case-less-stations-but-within-budget","outlet":"Mass Transit","published_at":"2021-03-19","quote":"The schedule included in the document estimates a contract could be awarded in September 2023 with construction starting in 2024 and the line entering service between 2029 and 2030."}]},{"kind":"milestone","statement_date":"2025-08-06","date_precision":"day","speaker":{"type":"proponent","name":"Metrolinx and Infrastructure Ontario"},"milestone":{"title":"Advance tunnelling contract awarded","achieved":true},"headline":"$1.44B tunnelling contract awarded","sources":[{"url":"https://urbantoronto.ca/news/2025/08/contract-awarded-yonge-north-subway-extension-tunnels.59140","outlet":"UrbanToronto","published_at":"2025-08-06","quote":"The Yonge Line 1 North Subway Extension is taking a major step forward, as Infrastructure Ontario and Metrolinx have awarded a $1.44 billion contract for the project’s advance tunnelling phase."}]}]}]}